Dykes v. Long
Dykes v. Long
Opinion of the Court
The opinion of the court was delivered by
In the spring of 1912 Noah Long, and others associated with him, built a dam about four feet high, of concrete and earth, across a small stream on land owned by him, creating a pond about a quarter of a m'le long and fifty or sixty feet wide, chiefly for hunting and fishing purposes. A spillway was left
Where by the erection of a dam the waters of a stream are spread over a larger area, and the increased evaporation and seepage lessen the amount of water that flows to the land of a lower proprietor, the result is regarded as a diversion. (White v. East Lake Land Co., 96 Ga. 415, 23 S. E. 393, 51 Am. St. Rep. 141; Note, 41 L. R. A. 746; 40 Cyc. 571, 607.) But whether in such a case equity will require the removal of the obstruction, or whether the injured person will be left to his remedy in damages, is a matter to be determined upon consideration of all the attendant circumstances, and is said to rest in the sound discretion of the trial court (30 A. & E. Encycl. of L. 371; Fisk et al. v. Hartford, 70 Conn. 720, 40 Atl. 906), the discretion referred to being of course not absolute, but required to be exercised in accordance with equitable principles.
Here the trial court held that the remedy in damages was adequate, and that the conduct of the plaintiff had been such as to justify the denial of an injunction. It was found that during the building of the dam he talked with some of the defendants regarding it, made no objection to it, and said in effect that he believed it would be a good thing for the country; that on the suggestion being made that he build a dam on his own place, he said he would wait and see the result of that built by the defendants. One who acquiesces in the construction of a dam, and without protest sees money so invested that returns from the investment are dependent upon
In the present case the parties were on equal footing as to knowledge of the probable consequences of the erection of the dam. That some slight diminution of the flow in hot and dry weather might result was fairly to have been anticipated. A dam at the same place had been constructed for the operation of a mill in 1878, and had been maintained until sometime between 1892 and 1897, when the mill was removed, the dam remaining as it was, except as it wore away by the flow of water across it, and by the tramping of horses and cattle over it. This may have been of some aid in judging of the results likely to ensue upon the building of the new dam. How much of the lessened flow complained of by the plaintiff was actually due to it and
“From my own inspection of the situation I am convinced that'the only reason the water did not continue to pour over the spillway of said dam was because of. the excessively hot and dry season and the failure of the springs in the marsh above the dam to supply the usual volume of water.”
A further finding was made that when the plaintiff complained of the dam the defendants offered to furnish appliances to carry water from the pond to his premises, sufficient to accommodate his stock, and to supply water in this manner twice a day — an offer which he refused. In view of the whole situation we think it can not be said that the court erred in denying the injunction and in remitting the plaintiff to his remedy in damages. This decision is not based on the theory that the plaintiff was absolutely estopped to claim the protection of a court of equity, but upon the conclusion that, giving weight to his conduct, and also to the character of his injury, to the doubt concerning its cause and permanence, and to its extent as compared with the loss to the defendants if the dam is removed, an injunction is not shown to be necessary to a just termination of the controversy.
The judgment is affirmed.