Southwestern Coal Co. v. Calbeck
Southwestern Coal Co. v. Calbeck
Opinion of the Court
The opinion of the court was delivered by
Plaintiff sued to recover damages for defendant’s failure to accept and pay for a carload of coal. A demurrer to plaintiff’s evidence was sustained, and it appeals.
The Southwestern Coal Company buys coal from mining companies and sells to local dealers. On January 14, 1918, it had pur
It also sent to defendant a letter acknowledging receipt of the order, and stating that all orders were accepted subject to prices authorized by the government at the time of shipment, and to all the orders of the federal fuel administrator regulating the movement of coal; stating further, “we will not be responsible for damages, loss or delay to shipments in transit, nor for delays on account of labor troubles, car shortages, or other contingencies beyond our control. Mine weights shall govern settlement. Cancellation will not be accepted after cars have been set to mines for loading.” The defendant made no reply to these communications.
The car was not shipped from the mines until January 31 and did not arrive at Pratt until February 13, a month after the defendant had sent in his order. The sales manager of plaintiff testified that during the winter of 1917-1918 there was a remarkable shortage in coal and all dealers were glad to get any grade of coal and the demand for lignite at that time was good, as the mines were not able to supply enough coal to fill orders; “that most' any kind of coal, even lignite, was in demand and eagerly bought.” He testified that the term “at once” was used among the coal trade as meaning the order to be entered for shipment as quickly as conditions would permit shipment to be made; that the plaintiff had no control over them and that no definite date of shipment was meant by the term “at once.”
We do not believe the plaintiff can rely upon the acceptance of a former car earlier in the season (under wholly different conditions) as establishing a custom or usage between the parties that would bind defendant to accept the car in question after such a delay.
The order signed by the defendant was for a particular car of coal in transit, with the following modification: “If you can’t send this car, send another at once.” The order was for a particular car of coal in transit, or for some other car in transit to be shipped “at once”; not a general order for a car of coal. When plaintiff found that the particular car had been sold, instead of diverting another car in transit, it merely placed a general order with the mines for a car of coal with full knowledge that the particular kind of coal could not be sold at any price except for the abnormal demand-existing at that time. On receipt of the defendant’s order plaintiff mailed to defendant what it terms an “acceptance,” and it is contended that on receipt of this, defendant should have canceled his order, if not satisfied with the new terms and conditions offered by the plaintiff. The so-called “acceptance” introduced a number of new elements varying from the original offer; and the mere refusal of defendant to reply to the new proposition would not bind him to a contract containing the new conditions. (Hayes v. Possehl, 92 Kan. 609, 141 Pac. 559; Spiher v. Johnson, ante, p. 339, 203 Pac. 696.)
The demurrer was rightly sustained and the judgment is affirmed.