Ford v. Bronaugh
Ford v. Bronaugh
Opinion of the Court
delivered the opinion of the Court.
Ford and Shanklin as parties of the one part, agreed with Bronaugh, of the other part, by written articles, to commence, prosecute, and complete in plain neat style, the wood-woi’k of a tavern house, consisting of a front building and an ell, in due time after the timber should be furnished; on the completion of which, Bronaugh and his security bound themselves to pay Ford and Shanklin $750, “it being the sum agreed on by the parties for the above named work, four hundred and fifty dollars due to the said Ford when the work of the front is complete, and the rest due to the said Shanklin when the work of the ell is complete.”
Upon this covenant, Ford brought an action of covenant in his own name, for the $450 due him by the contract on completion of the front building. The declaration makes all necessary averments as to the progress and completion of the work on that building, and also made similar averments as to the work on the ell, but alleged only the non-payment of the $450 due to the plaintiff. The defendants demurred to the declaration, and also filed a plea denying seriatim all the averments in reference to both buildings, to which the plaintiff demurred. Both demurrers were overruled, and on the trial the plaintiff, after proving all the averments as to the work on the front building and its completion, offered to introduce Shanklin the co-party to the contract as a witness, who being objected to was rejected by the Court. The plaintiff also moved to amend his declaration by striking out the averments as to the completion of the ell, which was not allowed. And there
The main questions in the case are whether the plaintiff can sue alone, and if so, whether the completion of the work on the ell is a precedent condition to his right of action for the sum due him on completion of the front building. Each of these questions depends upon the construction of the same clauses of the contract, and we think both are to be answered in favor of the plaintiff. If the provision for payment had stopped with the stipulation to pay $750 on completion of the work as previously described, the necessary construction would have been that the covenant was to pay the entire sum to both builders jointly and only upon completion of the entire work. They must therefore have sued jointly for the price, and must have averred and proved the completion of both parts of the building. But this general covenant to pay $750 on completion of the whole work, is explained and materially qualified ' by the words immediately following, which divide the work and the price, and create or shew a separate interest in the covenantees in the different parts of the price. Instead, therefore, of there being one entire debt or duty due to both jointly, or only one entire duty due to one of the builders, there are two distinct duties or payments, one of which is due upon a certain condition to one of them, and the other upon a different condition to the other.
In such a case the rule or the exception to a more general rule is expressly and well settled, “that although the covenant be in its terms joint, (as with A. andB. to pay them £10 each,) yet the distinct interest of each in a separate subject matter shall attract to
From these views it follows, 1st, that as the interest of Ford and Shanklin in the covenant for payment, and in the sum to be paid, was separate, Ford might maintain his separate action, and that Shanklin not being a party nor interested therein, was, so far as appears, a competent witness; 2nd, that as the completion of the work on the ell was not a condition precedent to the plaintiff’s right of aotion and recovery, the failure to prove it was no ground for a non-suit. And, 3rd, that
Wherefore, the judgment is reversed with costs, and the cause remanded for a new trial without payment of costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.