Porter v. Moore

Court of Appeals of Kentucky
Porter v. Moore, 200 Ky. 95 (1923)
252 S.W. 97; 1923 Ky. LEXIS 3
Moorman

Porter v. Moore

Opinion of the Court

Opinion of the Court by

Judge Moorman

Reversing.

In 1919 appellees filed tlieir petition in tlie Hickman county court for the establishment of the “Bush Creek Drainage District” in Hickman county. The district was established and the plans and specifications for constructing a ditch were approved by the board of Drainage Commissioners'. Appraisers were appointed and their report of damages and benefits filed and confirmed. The board advertised for bids for constructing the ditch and awarded the contract to P. H. Porter as the lowest and best bidder. Preliminary proceedings were had for the issuance and sale of the bonds of the district, amount*97ing to $60,000.00, the estimated cost of the ditch. Thereafter some of the appellees filed suit to annul the district and discontinue the ditch, but judgment was rendered dismissing the petition. Hatchell, etc. v. Board of Drainage Commissioners of Hickman County, etc., 191 Ky. 246. After the filing of the mandate of this court in that case, and on November 5, 1921, this action was instituted by the landowners and taxpayers in the district, praying that the contract for the construction of the ditch be declared null and void, and that the board be restrained and enjoined from selling the bonds, and it, with the contractor and sheriff of Hickman county, be enjoined from attepting to collect the taxes levied in the district. The averments of the petition on which this relief was sought were controverted by answer, proof was taken, and judgment rendered by the chancellor cancelling the contract and permanently enjoining the selling of the bonds and the collection of taxes to defray the cost of constructing the ditch. Prom that judgment the contractor has appealed.

It is admitted that the district was legally established, but it is first contended by appellees that the terms of the successful bid, which were incorporated into the contract, do not conform to the advertisement, and, in consequence, there was not the competitive bidding essential to a valid letting. Three bids were made. The forms on which they were submitted were prepared by the secretary of the board and given to prospective bidders. Appellant’s bid was submitted on the regular form, but he appended to it the conditions (a) that the board should furnish a free building place, a free tearing-out place, and a free right of way for all hauling necessary to be done in the execution of the work; (b) he should not be required to begin the work until funds to pay for it were in the hands of the board; and (c) the funds should be in the hands of the board within six weeks' from the date of the contract, and that he should begin the work within a reasonable time thereafter. These conditions are said to constitute a fatal variance from the terms of the advertisement and to render the contract void. Staebler & Gregg v. Town of Anchorage, 186 Ky. 124, Mayes v. Adair County, 194 S. W. 58 (Mo.), and Diamond v. City of Mankato, 61 L. R. A. 448, are cited in support of the contention. Whether the doctrine announced in those decisions operates to defeat the contract is the question.

*98One of the conditions attached to the bid and embraced in the contract was that the. board of drainage commissioners should furnish the contractor a free building place, a free tearing-out place, and a free right of way for hauling made necessary in the execution of the work. This condition was not specifically mentioned in the advertisement. That fact, however, does not in our opinion subject the case to the interdictions of the authorities cited, for they relate to some change in the plans, ■specifications or terms that will lessen the contractor’s work, will make it easier and less expensive for him to perform it, will increase his compensation, or will impose a greater obligation upon the municipality than was contemplated in the advertisement. No such change is observable in the condition in question. Indeed it is within the spirit and meaning of the advertisement, which in itself was an invitation for bids and necessarily implied the furnishing by the board of a place in which to do the work — that is, a place in which to make clearings and excavations, with a right-of-way to do hauling, and to perform other acts necessary to an economical and proper performance of the contract. It seems clear to us, therefore, that in this particular there is no variance between the instruments.

Another condition attached to the bid was that aupellant should not be required to begin the work until the funds to pay for it were in the hands of the commissioners. This condition was evidently inserted to insure the making of payments as the work progressed. The advertisement contemplated that the work would be promptly paid for, and the form of bids prepared under the direction of the board specified that eighty per cent, of the amount earned on work completed in any month should be paid at the end of the month and that the unpaid twenty per cent, should be retained until the contract was completed. Besides, the advertisement stated that 'the bonds for the construction of the ditch had been sold, thus plainly indicating that the board had in its hands sufficient funds to pay for the work as it progressed. The obvious purpose of this statement was to obtain advantageous bids. It was in reality a representation of fact upon which the contractor had the right to rely and which he could rightfully have incorporated into his contract.

It is said, however, that the advertisement is void for uncertainty, since it did not fix any time for completing *99the work, and that alleged defect, in connection with the stipulation that the contractor should begin the work within a reasonable time after the funds to pay for it were in the hands of the board, is advanced as ground for invalidating the contract. In response to these suggestions it is, in our opinion, sufficient to say that the statute, subsection 26 of section 2380, providing that the notice shall fix the time for completing the work, is not mandatory in the sense that a contract fairly entered into is vitiated because a specified time for the completion of the work is not fixed in the advertisement. The contract provides for completing the work within twelve months, and it is neither alleged nor proved that that time was unreasonable. As the advertisement did not fix a time, the parties must be regarded as having understood what the law presumes, i. e., the work should be completed within a reasonable time. Furthermore, in the absence of a definite date for beginning the presumption must be indulged that the contractor would begin within a reasonable time from the performance of the conditions that the board had assumed in its advertisement. Hence the stipulation in respect to beginning the work was consonant with what the law construes to be the terms of the advertisement.

As to the relationship existing between the secretary of the board of drainage commissioners and the contractor, it may be remarked that the record is devoid of evidence from which it could be inferred that there was any favoritism shown 'the contractor by the board or by its secretary. That relationship of itself does not, in our judgment, vitiate the contract. It is contended, however, that as the secretary was also chief engineer for the district, and it was his duty, as engineer, to examine the work as it progressed and-to determine whether it was done according to the plans and specifications, and make recommendations to the board for the payments of estimates, public policy forbids the enforcement of the contract. Among the authorities cited in support uf this view is Knott v. Jarboc, 1 Metcalf 504, where it was held that the service of a process by a sheriff in a suit in which he was plaintiff, although he had no pecuniary interest in the result, was a nullity, not only because it was violative of a statute, but also because inconsistent with public policy. Another ease relied on is Coquillard Wagon Works v. Melton, Sheriff, 137 Ky. 189, in which it was de*100cided that a judge is disqualified to act in a case in which there is anything to be decided from which he can profit. Reference is also made to the ruling in Petrey, etc. v. Holliday, etc., 178 Ky. 410, that a judge who is related in the second degree to one of the plaintiffs is disqualified to grant an injunction for or hear or determine any motion made by the plaintiffs if timely objection is made to his sitting. These and many other authorities cited by counsel declare a wholesome rule of public policy. But they are not, as we construe them, applicable to the facts in this case, for the obvious reason that Porter’s appointment as engineer is not irrevocable, and both he and the board of drainage commissioners! are amenable to the processes of the courts to the end of preventing his acting as engineer, or, if he should act, of abusing his authority as such. With these ample remedies for preventing favoritism or dishonesty, it cannot be held that the contract itself, which may be carried out under the engineering supervision of some one besides the brother of the contractor, is invalid.

It is further insisted that appellant violated the contract in failing to begin the work or to complete it within a reasonable time. The contract was made on August 21, 1920, but it appears that shortly thereafter the action to annul the proceeding establishing the district and to discontinue the ditch was instituted. That litigation suspended operations under the contract until the mandate of this court was filed in the Hickman circuit court the latter part of May, 1921. The board of drainage commissioners did not then have the funds for prosecuting the work, and, owing to threatened litigation, was unable to obtain funds before this action was filed in November, 1921. Appellant was prepared at all times, as is shown in the evidence, to carry out his contract. It appears, therefore, that the delay in beginning the work was not due to any fault of the contractor, but was caused by appellees. In these circumstances they will not be granted a cancellation of the contract. Weikle v. Board of Drainage Commissioners, 192 Ky. 797, does not hold to the contrary, for there the delay did not necessarily result from the action of the landowners in placing the board of drainage commissioners in position where it could not carry out its contract. Here the board of drainage commissioners was prevented from selling the bonds by reason of litigation instituted and threatened by appellees. A part of its contract was to have the *101funds on hand when the work began. Appellees prevented it from carrying out the contract, and now they insist that it should be canceled, although from the beginning appellant has been willing and desirous of fulfilling it, and has not been able to do so because appellees have prevented the other party from complying with it. If the board had been able and willing to perform its part of the contract, and appellant had delayed the performance, the contention would be maintainable. But that is not the case. Appellees have caused the delays and they cannot rely on the result of their own acts to defeat the contract.

It is the final contention of appellees that the injunction should have been granted as to the sale of the bonds and the levying and collecting of the taxes because the property owners and taxpayers had no notice of the making of the assessment roll, which was never confirmed by any order or judgment of the Hickman county court. The averments of the petition as to this ground were traversed. Appellees insist that the burden of proving notice of the assessment roll and its confirmation by the Hickman county court rested upon appellant. The theory of this argument is that appellees could not prove the negatives that they had not been given notice of the assessment roll and it had not been confirmed by order of court, whereas it was practicable for appellant to introduce a copy of the order or judgment of court and to prove the giving of notice. Hamilton v. Steele, 117 S. W. 378, Andrews v. Haydon’s Admr., 9 Ky. L. R. 440, and Whitteker v. Holcomb, 177 Ky. 790, are relied on. None of those decisions is applicable, nor does any of them depart from the general rule that the burden is upon him who asserts the affirmative of an issue, whether he be plaintiff or defendant. Appellees attaclmd the validity of the tax and proposed bonds because of the alleged irregularity in the levy. This was the ground for asking an injunction. They assumed the burden of establishing their claim, and the mere fact that they alleged a negative did not shift the burden to appellant. In the recent case of Union Central Life Insurance Co. v. Jackson, 195 Ky. 438, it was held that where a negative averment is essential to the statement of a cause of action, the party making the averment has the burden of proving it, unless it is exclusively within the power of the adverse party to produce evidence pertaining to the averment. Here it *102was within the power of appellees, and indeed more convenient for them than appellant, to show whether they had been served with notice of the tax assessment. Moreover, it was in their power to produce the records of the county court and to show whether an order or judgment confirming the assessment roll had been entered. The burden being upon them, and there being no evidence to sustain it, they were manifestly not entitled to the injunction.

For the reasons stated the judgment is reversed and the cause remanded for further proceedings consistent with this opinion.

Reference

Cited By
1 case
Status
Published