Porter v. Moore
Porter v. Moore
Opinion of the Court
Opinion of the Court by
Reversing.
In 1919 appellees filed tlieir petition in tlie Hickman county court for the establishment of the “Bush Creek Drainage District” in Hickman county. The district was established and the plans and specifications for constructing a ditch were approved by the board of Drainage Commissioners'. Appraisers were appointed and their report of damages and benefits filed and confirmed. The board advertised for bids for constructing the ditch and awarded the contract to P. H. Porter as the lowest and best bidder. Preliminary proceedings were had for the issuance and sale of the bonds of the district, amount
It is admitted that the district was legally established, but it is first contended by appellees that the terms of the successful bid, which were incorporated into the contract, do not conform to the advertisement, and, in consequence, there was not the competitive bidding essential to a valid letting. Three bids were made. The forms on which they were submitted were prepared by the secretary of the board and given to prospective bidders. Appellant’s bid was submitted on the regular form, but he appended to it the conditions (a) that the board should furnish a free building place, a free tearing-out place, and a free right of way for all hauling necessary to be done in the execution of the work; (b) he should not be required to begin the work until funds to pay for it were in the hands of the board; and (c) the funds should be in the hands of the board within six weeks' from the date of the contract, and that he should begin the work within a reasonable time thereafter. These conditions are said to constitute a fatal variance from the terms of the advertisement and to render the contract void. Staebler & Gregg v. Town of Anchorage, 186 Ky. 124, Mayes v. Adair County, 194 S. W. 58 (Mo.), and Diamond v. City of Mankato, 61 L. R. A. 448, are cited in support of the contention. Whether the doctrine announced in those decisions operates to defeat the contract is the question.
Another condition attached to the bid was that aupellant should not be required to begin the work until the funds to pay for it were in the hands of the commissioners. This condition was evidently inserted to insure the making of payments as the work progressed. The advertisement contemplated that the work would be promptly paid for, and the form of bids prepared under the direction of the board specified that eighty per cent, of the amount earned on work completed in any month should be paid at the end of the month and that the unpaid twenty per cent, should be retained until the contract was completed. Besides, the advertisement stated that 'the bonds for the construction of the ditch had been sold, thus plainly indicating that the board had in its hands sufficient funds to pay for the work as it progressed. The obvious purpose of this statement was to obtain advantageous bids. It was in reality a representation of fact upon which the contractor had the right to rely and which he could rightfully have incorporated into his contract.
It is said, however, that the advertisement is void for uncertainty, since it did not fix any time for completing
As to the relationship existing between the secretary of the board of drainage commissioners and the contractor, it may be remarked that the record is devoid of evidence from which it could be inferred that there was any favoritism shown 'the contractor by the board or by its secretary. That relationship of itself does not, in our judgment, vitiate the contract. It is contended, however, that as the secretary was also chief engineer for the district, and it was his duty, as engineer, to examine the work as it progressed and-to determine whether it was done according to the plans and specifications, and make recommendations to the board for the payments of estimates, public policy forbids the enforcement of the contract. Among the authorities cited in support uf this view is Knott v. Jarboc, 1 Metcalf 504, where it was held that the service of a process by a sheriff in a suit in which he was plaintiff, although he had no pecuniary interest in the result, was a nullity, not only because it was violative of a statute, but also because inconsistent with public policy. Another ease relied on is Coquillard Wagon Works v. Melton, Sheriff, 137 Ky. 189, in which it was de
It is further insisted that appellant violated the contract in failing to begin the work or to complete it within a reasonable time. The contract was made on August 21, 1920, but it appears that shortly thereafter the action to annul the proceeding establishing the district and to discontinue the ditch was instituted. That litigation suspended operations under the contract until the mandate of this court was filed in the Hickman circuit court the latter part of May, 1921. The board of drainage commissioners did not then have the funds for prosecuting the work, and, owing to threatened litigation, was unable to obtain funds before this action was filed in November, 1921. Appellant was prepared at all times, as is shown in the evidence, to carry out his contract. It appears, therefore, that the delay in beginning the work was not due to any fault of the contractor, but was caused by appellees. In these circumstances they will not be granted a cancellation of the contract. Weikle v. Board of Drainage Commissioners, 192 Ky. 797, does not hold to the contrary, for there the delay did not necessarily result from the action of the landowners in placing the board of drainage commissioners in position where it could not carry out its contract. Here the board of drainage commissioners was prevented from selling the bonds by reason of litigation instituted and threatened by appellees. A part of its contract was to have the
It is the final contention of appellees that the injunction should have been granted as to the sale of the bonds and the levying and collecting of the taxes because the property owners and taxpayers had no notice of the making of the assessment roll, which was never confirmed by any order or judgment of the Hickman county court. The averments of the petition as to this ground were traversed. Appellees insist that the burden of proving notice of the assessment roll and its confirmation by the Hickman county court rested upon appellant. The theory of this argument is that appellees could not prove the negatives that they had not been given notice of the assessment roll and it had not been confirmed by order of court, whereas it was practicable for appellant to introduce a copy of the order or judgment of court and to prove the giving of notice. Hamilton v. Steele, 117 S. W. 378, Andrews v. Haydon’s Admr., 9 Ky. L. R. 440, and Whitteker v. Holcomb, 177 Ky. 790, are relied on. None of those decisions is applicable, nor does any of them depart from the general rule that the burden is upon him who asserts the affirmative of an issue, whether he be plaintiff or defendant. Appellees attaclmd the validity of the tax and proposed bonds because of the alleged irregularity in the levy. This was the ground for asking an injunction. They assumed the burden of establishing their claim, and the mere fact that they alleged a negative did not shift the burden to appellant. In the recent case of Union Central Life Insurance Co. v. Jackson, 195 Ky. 438, it was held that where a negative averment is essential to the statement of a cause of action, the party making the averment has the burden of proving it, unless it is exclusively within the power of the adverse party to produce evidence pertaining to the averment. Here it
For the reasons stated the judgment is reversed and the cause remanded for further proceedings consistent with this opinion.
Reference
- Cited By
- 1 case
- Status
- Published