Mitsui Sumitomo Ins. USA, Inc. v. Denham-Blythe Co.
Mitsui Sumitomo Ins. USA, Inc. v. Denham-Blythe Co.
Opinion of the Court
This matter comes before the Court on Defendant Denham-Blythe Company, Inc's ("Denham-Blythe") Motion to Dismiss Pursuant to Federal Rule of Civil Procedure 12(b)(6) [DE 20] and Defendant BlueScope Buildings North America, Inc.'s ("BlueScope") Motion for Judgment on the Pleadings [DE 28]. Having considered the matter fully, and being otherwise sufficiently advised, the undersigned will grant Defendant Denham-Blythe's Motion to Dismiss Pursuant to Federal Rule of Civil Procedure 12(b)(6) [DE 20] and deny Defendant BlueScope's Motion for Judgment on the Pleadings [DE 28].
*790FACTUAL AND PROCEDURAL BACKGROUND
This case arises from a January 31, 2011 design-build contract ("the Contract") between Asahi Bluegrass Forge Corporation ("Asahi") and Denham-Blythe for the construction of a 68,000 square foot manufacturing facility ("the Building"). [DE 20-1, at 2]. "As part of its obligations as general contractor, Denham-Blythe contracted with several Contractors to complete the design and construction process[,]" including BlueScope, Varco Pruden Buildings ("Varco") (a division of BlueScope), and Arrow Metals and Coatings, Inc. ("Arrow"). [DE 29, at 2].
"Denham-Blythe and Asahi utilized AIA Document A141 - 2004 Standard Form of Agreement Between Owner and Design-Builder, with modifications specific to this job, for the Contract." [DE 20-1, at 2 (citing [DE 20-2] ) ]. The Contract defines a "Contractor" as follows:
§ A.1.1.4 CONTRACTOR
A Contractor is a person or entity, other than the Architect, that has a direct contract with the Design-Builder to perform all or a portion of the construction required in connection with the Work. The term "Contractor" is referred to throughout the Design-Build Documents as if singular in number and means a Contractor or an authorized representative of the Contractor ....
[DE 29, at 2-3 (citing [DE 23-1, at 14] ) ]. On March 2, 2012, the roof of the Building was damaged by severe winds and was subsequently repaired by Denham-Blythe. [DE 20-1, at 2]. Again, on March 1, 2017, the roof of the Building sustained damage from severe winds, and Denham-Blythe completed both the temporary repair work and permanent repair work. Id.
After the roof was damaged on March 1, 2017, Asahi submitted property damages claims to its insurer, Plaintiff Mitsui Sumitomo Insurance USA, Inc. ("Mitsui"). Id. "According to the Complaint, Mitsui Sumitomo made payments to Asahi in response to the claims in the amount of $ 1,315,092.00 under policy PKG3126694 (hereinafter referred to as 'the Policy') with effective dates of October 1, 2016 through October 1, 2017." Id. (citing [DE 20-3] ). On February 22, 2018, Mitsui, as subrogee of Asahi, filed its Complaint [DE 1] against Denham-Blythe, BlueScope, Varco, and Arrow asserting subrogation rights against Defendants for the amounts paid to repair the property damage caused by the 2017 severe winds. [DE 1]. Mitsui's claims against Denham-Blythe include negligence, breach of contract, breach of warranty of workmanlike services, and negligent misrepresentation. Id. Mitsui's allegations against BlueScope and Varco include negligence, negligent misrepresentation, breach of warranty of workmanlike service, and breach of contract and third-party beneficiary. Id. On April 13, 2018, Denham-Blythe filed the present Motion to Dismiss [DE 20], and on February 15, 2019, BlueScope filed the present Motion for Judgment on the Pleadings [DE 28] requesting Mitsui's claims against BlueScope and Varco be dismissed. BlueScope's Motion for Judgement on the Pleadings [DE 28] is nearly identical to Denham-Blythe's Motion to Dismiss [DE 20]. The only substantial difference between the two Motions [DE 20; DE 28] is that BlueScope's Motion [DE 28] omitted Denham-Blythe's argument that the claim is barred by the dispute resolution clauses in the contract.
STANDARD OF REVIEW
Federal Rule of Civil Procedure 12(b)(6) provides that a complaint may be attacked for failure "to state a claim upon which relief can be granted." To survive a Rule 12(b)(6) motion to dismiss, a complaint must "contain sufficient factual matter, accepted as true, to 'state a claim to relief that is plausible on its face.' " Ashcroft v.
*791Iqbal ,
"The standard of review for a judgment on the pleadings [pursuant to Federal Rule of Civil Procedure 12(c) ] is the same as that for a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6)." Roger Miller Music, Inc. v. Sony/ATV Publishing, LLC ,
DISCUSSION
A. DEFENDANT DENHAM-BLYTHE'S MOTION TO DISMISS PURSUANT TO RULE 12(B)(6)
In support of dismissal, Defendant Denham-Blythe argues the following: (1) "Kentucky law recognizes the sacred right to contract;" (2) "[t]he claim is barred by the waiver of subrogation clause contained in the design build contract between Denham-Blythe and Asahi Bluegrass Forge Corporation;" (3) "[t]he insurance policy issued by Plaintiff to Asahi Bluegrass Forge Corporation granted Asahi the right to waive subrogation;" and (4) "[t]he claim is barred by the dispute resolution clauses in the contract." [DE 20-1, at 1].
1. KENTUCKY LAW AND THE RIGHT TO CONTRACT
Denham-Blythe correctly asserts, "Kentucky Courts have long honored the freedom to contract[,]" and "The Kentucky Supreme Court has affirmed this principle many times." [DE 20-1, at 4].
"[C]ontracts voluntarily made between competent persons are not to be set *792aside lightly. As the right of private contract is no small part of the liberty of the citizen, the usual and most important function of courts is to enforce and maintain contracts rather than to enable parties to escape their obligations on the pretext of public policy or illegality. If the legality of the contract can be sustained in whole or in part under any reasonable interpretation of its provisions, courts should not hesitate to decree enforcement."
Mullins ,
"The terms of an unambiguous contract cannot be varied by extrinsic evidence." Luttrell v. Cooper Industries, Inc. ,
"A contract is to be construed as a whole so as to ascertain and give effect to the true intent of the parties, and the circumstances under which the contract was executed and the conduct of the parties thereafter can be considered by the Court in determining what their intention was, without it becoming a violation of the parol evidence rule."
Luttrell ,
Additionally, Denham-Blythe argues that under Kentucky law, contracts with exculpatory clauses are generally treated the same as any other contract. [DE 20-1, at 5 (citing Cumberland Valley Contractors, Inc. v. Bell County Coal Corp. ,
*793Mitsui neither disputes that Kentucky law honors the basic right to contract nor contends that a public policy prohibiting or limiting waiver of subrogation clauses exists. [DE 25]. Instead, Mitsui argues the Contract [DE 20-2] is ambiguous, so the Court should deny Denham-Blythe's Motion to Dismiss [DE 20] and allow the Parties to engage in discovery to determine the intent of the contracting parties. [DE 25, at 13-17].
2. WHETHER PLAINTIFF'S CLAIM IS BARRED BY THE DISPUTE RESOLUTION CLAUSES IN THE CONTRACT
Denham-Blythe argues section A.4.3.1 of the Contract requires the Parties "submit this matter to nonbinding mediation," and in the event mediation is unsuccessful, section A.4.4.1 requires "the parties must submit this matter to arbitration." [DE 20-1, at 13]. Specifically, sections A.4.3.1 and A.4.4.1 of the Contract state the following:
§ A.4.3.1
Any claim arising out of or related to the Design-Build Contract, except those waived as provided for in Section A.4.1.10, A.9.10.4 and A.9.10.5, shall, after initial decision of the Claim or 30 days after submission of the Claim for initial decision, be subject to mediation as a condition precedent to arbitration or the institution of legal or equitable or other binding dispute resolution proceedings by either party.
§ A.4.4.1
Claims, except those waived as provided for in Sections A.4.1.10, A.9.10.4 and A.9.10.5, for which initial decisions have not become final and binding, and which have not been resolved by mediation, but which are subject to arbitration pursuant to Sections 6.2 and 6.3 of the Agreement or elsewhere in the Design-Build Documents, shall be decided by arbitration which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect at the time of the arbitration. The demand for arbitration shall be filed in writing with the other party to the Design-Build Contract and with the American Arbitration Association.
[DE 20-2, at 32-33].
In addition to Denham-Blythe citing the aforementioned dispute resolution provisions, Denham-Blythe asserts, "Kentucky jurisprudence favors the enforcement of private arbitration contracts[,]" and "there is a strong federal policy favoring arbitration, 'even where the results would be the possibly inefficient maintenance of separate proceedings in different forums.' " [DE 20-1, at 12 (citing Kodak Mining Co. v. Carrs Fork Corp. ,
*794Stewart Services, Inc. v. Tilford Mechanical Contractors, Inc. ,
Section A.4.2.2 of the Contract states the following:
If the parties have not identified a Neutral in Section 6.1 of the Agreement or elsewhere in the Design-Build Documents then, except for those claims arising under Sections A.10.3 and A.10.5, the Owner shall provide an initial decision. An initial decision by the Owner shall be required as a condition precedent to mediation of all Claims between the Owner and Design-Builder arising prior to the date final payment is due, unless 30 days have passed after the Claim has been referred to the Owner with no decision having been rendered by the Owner.
[DE 20-2, at 32]. Pursuant to Section A.4.2.3:
The initial decision pursuant to Sections A.4.2.1 and A.4.2.2 shall be in writing, shall state the reasons therefore and shall notify the parties of any change in the Contract Sum or Contract Time or both. The initial decision shall be final and binding on the parties but subject first to mediation under Section A.4.3 and thereafter to such other dispute resolution methods as provided in Section 6.2 of the Agreement or elsewhere in the Design-Build Documents.
According to the plain meaning of Section A.4.2.2, Asahi was required to make an initial decision as a condition precedent to the mediation of claims arising prior to the date final payment was due or within thirty (30) days of the claim being referred to Asahi for an initial decision .
Mitsui correctly asserts, "Courts must 'place arbitration agreements on equal footing with other contracts ... enforce[ing] them according to their terms.' " [DE 25, at 17-18 (citing Scott v. Louisville Bedding Co. ,
B. DEFENDANT BLUESCOPE'S MOTION FOR JUDGMENT ON THE PLEADINGS
Like Defendant Denham-Blythe, Defendant BlueScope argues the following: (1) "Kentucky law recognizes the sacred right to contract;" (2) "[t]he claim is barred by the waiver of subrogation clause contained in the design build contract between Denham-Blythe and Asahi Bluegrass Forge Corporation, under which BlueScope is a defined Contractor;" and (3) "[t]he insurance policy issued by Plaintiff to Asahi Bluegrass Forge Corporation granted Asahi the right to waive subrogation." [DE 29]. Unlike Denham-Blythe, BlueScope does not argue the claim is barred by the dispute resolution clauses in the contract. Since BlueScope fails to make the dispute resolution clause argument that required Denham-Blythe's Motion to Dismiss [DE 20] be granted, the Court will deny BlueScope's Motion for Judgment on the Pleadings [DE 28]. Nevertheless, Mitsui's claims against BlueScope, Varco, and all other Defendants shall be dismissed without prejudice because the Contract required the Parties to mediate this claim, and if mediation did not resolve the issue, to participate in arbitration.
CONCLUSION
Therefore, having considered the matter fully, and being otherwise sufficiently advised,
IT IS ORDERED as follows:
(1) Defendant Denham-Blythe Company, Inc's Motion to Dismiss Pursuant to Federal Rule of Civil Procedure 12(b)(6) [DE 20] is GRANTED;
(2) Defendant BlueScope Buildings North America, Inc.'s Motion for Judgment on the Pleadings [DE 28] is DENIED;
(3) This matter is DISMISSED WITHOUT PREJUDICE;
(4) This is a final and appealable order; and
(5) Plaintiff Mitsui Sumitomo Insurance USA, Inc. shall COMPLY with the dispute resolution provisions set forth in the Contract.
To support these assertions, Denham-Blythe cites to both Frear v. P.T.A. Industries, Inc. ,