The plaintiff corporation was the owner of a certain lot of ground, situated in the City of New Orleans, with improvements thereon. Desiring the demolition of the 'buildings on the property and the cleaning of the lot so as to fit it for rebuilding thereon, a contract was entered into with the defendant under the terms of which defendant was to pay plaintiff $185.00 in cash; demolish at his own expense the buildings; remove all materials, debris and rubbish from the premises; take out all old footings of the walls demolished; leave the lot clean and level with the sidewalks grade and finally to fully complete his engagement within fifteen working days from the time 'he is put in possession of the premises, to-wit: from the 17th of March.
Up to the 16th of April, 1904, defendant had not yet complied with his contract, in that he had not removed all materials, debris and rubbish from the premises and 'had not left the lot clean and level with the present sidewalk grade. In this condition of the lot the work of rebuilding was impossible. The contractor to whom the work of rebuilding had been given being unable to take any steps looking to the execution of his contract, complained to the architects under whose supervision the new structures were to be erected, who in turn made a written demand on the defendant to comply with his contract, giving him until the morning of the 19th of April for that purpose and advising him that if by that time the lot was not in a proper condition for the builders to take posses--
The debris coveted the lot at an average of 12 inches above the side-walk grade and would have taken, perhaps, weeks to remove at the rate ill which the work was being done by defendant. On the morning of the 19th of March, plaintiff contracted with another party to remove the debris, who at Once put to work sixteen carts; defendant also having on that day 5 or 6 carts at work. In due time the lot was cleaned and made ready for the builders. The cost of this extra labor is $132.60, which together with the sum of $185.00, the stipulated amount to be paid by defendant to plaintiff for the materials of the old buildings, constitute the cause of action.,
The judgment below was for the full am.ount thus claimed.
In our opinion, as it was that of the trial judge, defendant had completely failed in his contract and plaintiff was hence fully warranted in employing the extra force to do the work at defendants costs.
The judgment appealed from is affirmed.
Notice of intention to apply for writ.