B & G Crane Service, Inc. v. Lamastus
B & G Crane Service, Inc. v. Lamastus
Opinion of the Court
Plaintiff, B & G Crane Service, Inc., doing business as Sun Erection Company, was awarded an $869 judgment against defendant,
“Neither shall parol evidence be admitted against or beyond what is contained in the acts, nor on what may have been said before, or at the time of making them, or since.”
Defendant, as general contractor of the Star Chrysler building, entered into a written agreement to subcontract to plaintiff the erection of the structural steel. The extent of the work plaintiff was obliged to perform was set forth in Section 5. We quote:
“SECTION 5 — STRUCTURAL STEEL —COMPLETE NO EXCEPTIONS AS APPLICABLE TO STRUCTURAL STEEL ERECTION. This subcontract agreement includes specifically the unloading, erecting, aligning, plumbing and welding of the structural steel for the new service building, the two steel stairs and the railing on the roof of the new service building.
Sun Erection Co., Inc. is to receive all materials F.O.B. Truck Delivery Job Site, tentative delivery May 24, 1971. All grouting, field painting and testing is excluded except cost of retesting due to original work not meeting specifications and cost of certification of welders. This subcontract agreement does not include the furnishing of any material that*517 forms a permanent part of this job other than welding rods.”
The contract also provided:
“(b) This subcontract contains the entire agreement between the parties and all additions thereto or changes therein shall be in writing and shall not be binding unless same are in writing.”
The steel furnished plaintiff by the defendant was ordered from Howell Steel in Jackson, Mississippi. Most of it was defective on arrival and required aligning, straightening and welding to conform to the contract specifications.
Arleigh Hays, plaintiff’s estimator, explained that the original contract did not contemplate remedial work of the material furnished. While he was aware the contract recited written authorization for “additions,” he did the remedial work at the verbal request of James Wishardt, defendant’s superintendent on the job. He explained the general contract was virtually completed and rather than delay the project waiting for written approval and consultation with the steel supplier, he “took the man [Wishardt] at his word” and agreed to undertake the straightening on verbal authorization.
At the time of the trial, Wishardt was no longer employed by defendant; he was working for a firm in Slidell, Louisiana, and was not available to appear. Defendant’s president, Ray Lamastus, testified he instructed Wishardt and Huey Breaux, his office engineer, to authorize no extra work verbally, and specifically in the case of the defective railing, to hold up the job until the matter was settled with the fabricator.
Lamastus acknowledged that he at no time communicated these thoughts directly to plaintiff’s representatives, and his testimony is somewhat vague as to how often he was on the job site while the remedial work was underway. The trial judge found these facts which we quote from his written reasons for judgment:
“The evidence is quite clear. Plaintiff had nothing to do with supplying the handrails; its job was simply to erect them. As delivered, the rails were defective and had to be remedied before they could be used. The remedial work was done by the plaintiff. The job superintendent and project engineer for the general contractor knew an extra was to be incurred; they saw the work being done and authorized it, if not specifically, then certainly tacitly. Neither the superintendent nor the engineer stopped the work or instructed the plaintiffs not to proceed with the extra work until written authorization for it was given.”
We do not view the Sun remedial work as an addition to or a change in the original contract, because the written agreement is restricted solely to the erection of fabricated steel to be furnished by the general contractor. As we view it, Wishardt’s request that plaintiff remedy the defective material was beyond the scope of the subcontract
At the time the original agreement was signed both plaintiff and defendant were assuming the material would be supplied to the job in a usable condition. When it arrived in a defective state as the contract neared completion, a situation presented itself that had not been foreseen at the time the written agreement was signed. Had defendant engaged another
For the reasons assigned, the judgment appealed from is affirmed, costs to be borne by the appellant.
Affirmed.
SCHOTT, J., concurs with written reasons.
. Ray Lamastus, president of Lamastus & Associates, Inc., was cited individually as a defendant. An exception of no cause of action was properly maintained. Chrysler Realty Corporation was cited as a defendant because it owned the building into which the iron and steel were incorporated; however it was never served with a copy of the petition. The suit against it was severed.
. The pipes warped when subjected to the hot dip process of galvanizing. They were guard rails which were to slip into sleeves embedded in concrete. In order to align the bent pipes with the sleeves it was necessary to heat and straighten them.
. The subcontract involved erection of fabricated steel, whereas the remedial work is to overcome a deficit in the processing by the supplier in its fabrication.
Concurring Opinion
(concurring).
The language of the contract between the parties prescribed that “all additions” to the contract work “shall be in writing and shall not be binding unless same are in writing.” In my opinion the work of aligning, straightening and welding the steel performed by plaintiff was clearly an addition to the work contracted for. For that reason I would hold that plaintiff is not entitled to recover except for the principles found in McGowan-Rigsby Sup., Inc. v. Charles Carter & Co., Inc., 268 So.2d 716 (La.App. 1st Cir. 1972) and Roff v. Southern Construction Corporation, 163 So.2d 112 (La.App. 3rd Cir. 1964). In the latter case the Court recognized the general rule that in a situation such as the instant case where the contract provides for no claims for extra work unless there is a written order the provision is enforceable subject to certain exceptions.
“However, recovery for extras based on parol evidence has been permitted in spite of a stipulation that authority for extra work must be in writing: (1) when the alteration was necessary and had not been foreseen ... (2) when the alteration was so great that it cannot be supposed to have been made without the knowledge of the owner . (3) when the owner was aware of the extra work and made no objection to it . . .”
The evidence shows that the defects in the handrails were unforeseen and an alteration was necessary before they could be installed. Furthermore, the trial judge found that defendant “saw the work being done and authorized it, if not specifically, then certainly tacitly.” These elements fit the exceptions discussed in the Roff case and I would allow recovery on that basis.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.