State v. United States Army Corps of Engineers
State v. United States Army Corps of Engineers
Opinion of the Court
ORDER AND REASONS
Before the Court are cross-motions
BACKGROUND
“In 1943, Congress requested a report from the Chief of Engineers, Secretary of the Army, investigating ways to make the Port of New Orleans more accessible for maritime and military use.” In re Katrina Canal Breaches Litig., 696 F.3d 436, 441 (5th Cir. 2012). Pursuant to that request, the Corps planned, and Congress authorized, construction of the Mississippi River-Gulf Outlet Canal (“MRGO”), which was “built to its full dimensions by 1968” and measured 36-38 feet deep and 500-600 feet wide. Id. “MRGO was cut through virgin coastal wetlands.” Id. at 441-12. “The channel’s original designers considered and rejected armoring its banks with foreshore protection, leaving them vulnerable to erosion.” Id. at 442. In a 1988 report, “[t]he Corps refused to undertake the cost of foreshore protection unless there was local cost participation under the Water Resources Development Act, 33 U.S.C. § 2201 et seq.” Id.
“Finally, in the mid-1990s, the Corps realized that the actual costs of maintaining the foreshore protection were less than estimated in the 1988 report,” so “Congress instructed the Corps to use its available operations and maintenance funds to protect the shore to minimize future dredging costs and preserve the wetlands.” Id. at 443. However, the damage had already been done. “The Corps’ delay in armoring MRGO allowed wave wash from ships’ wakes to erode the channel considerably,” and “MRGO eventually reached a total average width of 1970 feet, well over three times its authorized width.” Id. at 443 & n. 1. “The increased channel width added more fetch
After Hurricane Katrina, Congress appropriated billions of dollars for the Gulf Coast’s recovery. On December 30, 2005, Congress passed the “Department of Defense Emergency Supplemental Appropriations To Address Hurricanes in the Gulf of Mexico, and Pandemic Influenza Act, 2006,” P.L. 109-148, 119 Stat. 2680 (referred to in this litigation as the “3rd Supplemental”). The 3rd Supplemental appropriated $327,517,000 to the Corps for operation and maintenance activities, in-
On June 15, 2006, Congress passed the “Emergency Supplemental Appropriations Act for Defense, the Global War on Terror, and Hurricane Recovery, 2006,” P.L. 109-234, 120 Stat. 418 (referred to in this litigation as the “4th Supplemental”), which appropriated certain funds under four separate headings as follows.
Under the heading of “Investigations,” Congress appropriated $3,300,000 for the Corps to “develop a comprehensive plan, at full Federal expense, to deauthorize deep draft navigation on [MRGO],” and it set deadlines for the Corps to submit a report outlining such plan. Id. tit. II, ch. 3.
Under the heading of “Construction,” Congress appropriated $549,400,000 “for necessary expenses related to the consequences of Hurricane Katrina and other hurricanes of the 2005 season,” including an earmark of $20,200,000 “to reduce the risk of storm damage to the greater New Orleans metropolitan area, at full Federal expense, by restoring the surrounding wetlands through measures to begin to reverse wetland losses in areas affected by navigation, oil and gas, and other channels and through modification of the Caernar-von Freshwater Diversion structure.” Id. Congress also earmarked $495,300,000 to raise certain levee heights “consistent with the cost-sharing provisions under which the projects were originally constructed,” and it appropriated certain funds for three projects in other states. Id.
Under the heading of “Operations and Maintenance,” Congress appropriated $3,200,000 for “dredg[ing] navigation channels and repair[ing] other Corps projects related to the consequences of Hurricane Katrina and other hurricanes of the 2005 season.” Id.
Under the heading of “Flood Control and Coastal Emergencies,” Congress appropriated $3,145,024,000 “to modify, at full Federal expense, authorized projects in southeast Louisiana to provide hurricane and storm damage reduction and flood damage reduction in the greater New Orleans and surrounding areas.” Id. Certain portions of this $3 billion appropriation were earmarked for various projects, but the 4th Supplemental required that no work could begin on any of those projects until “non-Federal interests ha[d] entered into binding agreements with the [Corps] requiring the non-Federal interests to pay 100 percent of the operation, maintenance, repair, replacement, and rehabilitation costs of the project.” Id.
Finally, the 4th Supplemental also amended the 3rd Supplemental to provide that the $75,000,000 which had been earmarked for operations and maintenance along MRGO “shall be used for the repair, construction or provision of measures or structures necessary to protect, restore or increase wetlands, [and] to prevent saltwater intrusion or storm surge.” Id. tit. II, ch. 3, § 2304.
On June 5, 2008, the Corps submitted the required § 7013(a)(3) report to Congress.
The Corps’ June 5, 2008 report did not provide a plan for the ecosystem restoration that was mandated by WRDA 2007 § 7013(a)(3)(B). The Corps stated it would address the ecosystem restoration plan at a later date in a supplemental report.
Plaintiff filed the complaint in the above-captioned matter on October 28, 2014, challenging the Corps’ actions and the supplemental report as arbitrary and capricious, an abuse of discretion, and otherwise not in accordance with the law pursuant to the Administrative Procedure Act (“APA”).
Judicial review of agency action is governed by the APA, 5 U.S.C. § 500 et seq. The APA provides that final agency actions are appealable to a U.S. District Court for review. See id. § 704. “The [APA] allows a federal court to overturn an agency’s ruling ‘only if it is arbitrary, capricious, an abuse of discretion, not in accordance with law, or unsupported by substantial evidence on the record taken as a whole.’ ” Buffalo Marine Servs., Inc. v. United States, 663 F.3d 750, 753 (5th Cir. 2011) (quoting Tex. Clinical Labs, Inc. v. Sebelius, 612 F.3d 771, 775 (5th Cir. 2010)).
“An executive branch agency’s interpretations of the statutes that it is authorized to administer may be entitled to the deference” pursuant to Chevron, U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984). Dhuka v. Holder, 716 F.3d 149, 154 (5th Cir. 2013). “Chevron is rooted in a background presumption of congressional intent: namely, ‘that Congress, when it left ambiguity in a statute’ administered by an agency, ‘understood that the ambiguity would be resolved, first and foremost, by the agency, and desired the agency (rather than the courts) to possess whatever degree of discretion the ambiguity allows.’” City of Arlington, Texas v. FCC, — U.S. —, 133 S.Ct. 1863, 1868, — L.Ed.2d — (2013) (quoting Smiley v. Citibank (S.D.), N.A., 517 U.S. 735, 740-41, 116 S.Ct. 1730, 135 L.Ed.2d 25 (1996)). “Chevron thus provides a stable background rule against which Congress can legislate: Statutory ambiguities will be resolved, within the bounds of reasonable interpretation, not by the courts but by the administering agency. Congress knows to speak in plain terms when it wishes to circumscribe, and in capacious terms when it wishes to enlarge, agency discretion.” Id. (citation omitted).
Chevron sets forth a two-step framework. First, the Court must determine whether the statute at issue is ambiguous. Khalid v. Holder, 655 F.3d 363, 366 (5th Cir. 2011) (citing Chevron, 467 U.S. at 842-43, 104 S.Ct. 2778), abrogated on other grounds by Scialabba v. Cuellar de Osorio, — U.S. —, 134 S.Ct. 2191, 189 L.Ed.2d 98 (2014). “ ‘If the intent of Congress is clear,’ — that is, the statute is unambiguous with respect to the question presented — ‘the court, as well was the agency, must give effect to the unambiguously expressed intent of Congress.’ ” Id. (quoting Chevron, 467 U.S. at 842-43, 104 S.Ct. 2778). “To determine whether a statute is ambiguous, [courts] employ the traditional tools of statutory construction,” beginning with the “the plain language of the statute” while also reviewing “the broader context of the statute as a whole.” Id. at 366-67 (internal citations and quotation marks omitted).
DISCUSSION
First, the Court addresses defendants’ assertion of a statute-of-limitations defense with respect to the closure component of the MRGO closure and ecosystem restoration project that was authorized by § 7013. Second, the Court addresses Congress’s intent regarding cost sharing.
I. Statute of Limitations
As stated, the June 5, 2008 report to Congress provided that the federal government would pay all costs of construction for the closure, but that the non-federal sponsor (that is, plaintiff) was to provide all real estate acquisitions and maintain the closure structure at no cost to the federal government.
Defendants contend that no later than the transmission of the June 5, 2008 report to Congress, the Corps had taken its final agency action.
“As a general matter, two conditions must be satisfied for agency action to be ‘final’: First, the action must mark the ‘consummation’ of the agency’s decisionmaking process — it must not be of a merely tentative or interlocutory nature. And second, the action must be one by which ‘rights or obligations have been determined,’ or from which ‘legal consequences will flow.’ ” Bennett v. Spear, 520 U.S. 154, 177-78, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997) (citations omitted); see also Belle Co. v. U.S. Army Corps of Eng’rs, 761 F.3d 383, 388-90 (5th Cir. 2014); Nat’l Pork Producers Council v. EPA 635 F.3d 738, 755 (5th Cir. 2011). “On the other hand, the Supreme Court has defined a nonfinal agency order as one that ‘does not itself adversely affect complainant but only affects his rights adversely on the contingency of future administrative action.’ ” Am. Airlines, Inc. v. Herman, 176 F.3d 283, 288 (5th Cir. 1999) (quoting Rochester Tel. Corp. v. United States, 307 U.S. 125, 130, 59 S.Ct. 754, 83 L.Ed. 1147 (1939)). “In evaluating whether a challenged agency action meets these two conditions, this court is guided by the Supreme Court’s interpretation of the APA’s finality requirement as ‘flexible’ and ‘pragmatic.’” Belle Co., 761 F.3d at 388 (quoting Qureshi v. Holder, 663 F.3d 778, 781 (5th Cir. 2011)). The Court finds that the June 5, 2008 transmission of the report to Congress (or the January 29, 2008 letter on which such report was based) was not a final agency action.
The Court finds that the first Bennett condition is met by the June 5, 2008 report. Such report was obviously a definitive statement of the agency’s position regarding the real estate and ongoing maintenance obligations.
Regarding the second Bennett condition, however, the report stated that its closure plan and recommendation was “subject to the non-Federal sponsor executing an agreement with the Department of the Army prior to the Federal Government initiating construction of the closure structure and agreeing to comply with all applicable Federal laws and policies.”
Because the second Bennett condition was not satisfied by the June 5, 2008 report, the transmission of the report could not have been a “final agency action” for the purpose of the accrual of plaintiffs cause of action. The earliest possible final agency action was the October 31, 2008 execution of the MOA and, therefore, the earliest possible date for the accrual of plaintiffs cause of action was within the six-year statute of limitations. Accordingly, the Court need not address plaintiffs assertion with respect to the September 28, 2012 supplemental report, and defendants’ argument with respect to the statute of limitations is without merit.
II. Cost Sharing
The parties agree,
As noted above, WRDA 2007 states: “(b) COST SHARING. — Activities authorized by [section 7012(a) ] and section 7013 shall be carried out in a manner that is consistent with the cost-sharing requirements specified in the [4th Supplemental].” Id. § 7012(b). Section 7012(a) describes nine different projects which are also mentioned in the 4th Supplemental. Section 7013(a)(1) mandates the deauthorization of MRGO, and § 7013(a)(3) directs the Corps to develop the MRGO closure and ecosystem restoration plan. Section 7013(a)(4) directs the Corps to begin acting immediately: “(4) CONSTRUCTION. — The [Corps] shall carry out a plan to close [MRGO] and restore and protect the ecosystem substantially in accordance with the plan required under [§ 7013(a)(3) ], if the Secretary determines that the project is cost-effective, environmentally acceptable, and technically feasible.”
The 4th Supplemental, tit. II, ch. 3, appropriates funds for a number of different projects spread out under four different
Unlike the § 7012(a) projects, the MRGO closure and ecosystem restoration project authorized by § 7013 is not detailed in the 4th Supplemental. Although the 4th Supplemental directs the Corps to begin developing a comprehensive plan to deauthorize MRGO under the “Investigations” category, it is silent as to how such project would ultimately be funded. Defendants stop their analysis here, contending that “Congress did not provide specific direction for how the different kinds of cost-sharing in the [4th Supplemental] would apply to the activities listed in section 7013.”
What defendants ignore is § 7013(a)(4)’s characterization of Congress’s directive to carry out the MRGO closure and ecosystem restoration project as “CONSTRUCTION.” Cf. United States v. Wong Kim Bo, 472 F.2d 720, 722 (5th Cir. 1972) (“[W]ords in statutes should not be discarded as ‘meaningless’ and ‘surplusage’ when Congress specifically and expressly included them.... ”). Congress did not specify that the Corps should use the generally applicable cost-sharing rules for eeo-system restoration projects, nor did Congress remain silent on the subject of cost sharing; rather, Congress described the MRGO closure and ecosystem restoration project as a “CONSTRUCTION” project, and then referred the Corps to the 4th Supplemental for guidance as to the cost-sharing allocation.
As noted, the 4th Supplemental allocates more than $549 million to “Construction” projects. Specifically, the 4th Supplemental, tit. II, ch. 3: (1) earmarked “up to $20,200,000 [which] may be used to reduce the risk of storm damage to the greater New Orleans metropolitan area, at full Federal expense, by restoring the surrounding wetlands through measures to begin to reverse wetland losses in areas affected by navigation, oil and gas, and other channels and through modification of the Caernarvon Freshwater Diversion structure”; (2) stated that “at least $495,300,000 shall be used consistent with the cost-sharing provisions under which the projects were originally constructed to raise levee heights where necessary and otherwise enhance” certain existing projects to increase flood protection; and (3) allocated certain funds for three projects in other states.
A comparison of the language used in WRDA 2007 and the 4th Supplemental yields an unambiguous answer as to Congress’s intent with respect to cost sharing. The Corps’ plan “to close [MRGO] and restore and protect the ecosystem,” WRDA 2007 § 7013(a)(4) (emphasis added), which includes “a plan to physically modify [MRGO] and restore the areas affected by the navigation channel ” as well as “a plan to restore natural features of the
This reading of the text itself is further bolstered by a consideration of the statute’s legislative history and purpose. In President Bush’s veto statement, he described “hurricane protection for greater New Orleans” as one of “the Nation’s critical water resources needs.” 2007 WL 3231250. This sentiment was repeatedly echoed by the remarks of the Representatives and Senators who voted to override that veto. See, e.g., Water Resources Development Act of 2007 — Veto, 153 Cong. Rec. S14113-02, 2007 WL 3307877 (Nov. 8, 2007) (Senate debate regarding President Bush’s veto statement); Water Resources Development Act of 2007 — Veto Message from the President of the United States, 153 Cong. Rec. H12788-02, 2007 WL 3276604 (Nov. 6, 2007) (House debate regarding President Bush’s veto statement); see also, e.g., Water Resources Development Act of 2007 — Conference Report, 153 Cong. Rec. S11974-02, 2007 WL 2767477 (Sept. 24, 2007) (Senate debate regarding the conference report); Conference Report on H.R. 1495, Water Resources Development Act of 2007, 153 Cong. Rec. H9522-01, 2007 WL 2214160 (Aug. 1, 2007) (House debate regarding the conference report).
Defendants have not identified a single statement by any legislator, or any other item within the legislative history, that supports their interpretation, and the Court’s own review of the applicable portions of the Congressional Record revealed nothing to suggest that Congress intended Louisiana to pay for any part of the MRGO closure and ecosystem restoration project authorize4 by § 7013. To the contrary, there is only one statement regarding § 7012(b), the cost-sharing provision, in the Congressional Record which has been identified by the parties or uncovered by this Court. U.S. Senator David Vitter, who served on the conference committee that reconciled the House and Senate versions of WRDA 2007, stated that “[sjection 7012(b) clarifies that all work authorized pursuant to sections 7012(a)(2) through 7012(a)(9) and [sjection 7013 shall be performed at full Federal expense.” Water Resources Development Act of 2007, 153 Cong. Rec. S12769-01, 2007 WL 2891222 (Oct. 4, 2007) (statement of Senator Vit-ter).
There is nothing that requires Congress to legislate using the clearest possible language, and although the benefit of hindsight often reveals that legislation could have been more precisely worded, such retrospection does not inject ambiguity into a statute that contains none. Considering the extensive legislative history behind WRDA 2007, the context provided by the 3rd and 4th Supplemental, which tunneled billions of dollars to the Gulf Coast region for hurricane damage remediation and ecosystem restoration, and the clear
Defendants assert that Congress could not have intended that the MRGO closure and ecosystem restoration project be funded at full federal expense because “Congress used the word ‘cost-sharing’ not once, but twice.”
Defendants further argue that because WRDA 2007 § 7012(b) “did not explicitly or implicitly repeal” the generally applicable cost-sharing statute, 33 U.S.C. § 2213, such statute must apply to the MRGO closure and ecosystem restoration project because “ ‘[m]ere appropriations acts ... do not make changes in substantive law unless they do so explicitly.’ ”
Even assuming that WRDA 2007 § 7012(b) is ambiguous — a finding which this Court does not make — defendants would fail at Chevron step two because theirs is not a permissible construction of the statute. See Mortera-Cruz, 409 F.3d at 253. “[S]tep two of Chevron requires us to evaluate the same data that we also evaluate under Chevron step one, but using different criteria. Under step one we consider text, history, and purpose to determine whether these convey a plain meaning that requires a certain interpretation; under step two we consider text, history, and purpose to determine whether these permit the interpretation chosen by the agency.” Bell Alt. Tel. Cos., 131 F.3d at 1049; see also Massachusetts v. U.S. Dep’t of Transp., 93 F.3d 890, 893 (D.C.Cir. 1996) (“This second inquiry is
CONCLUSION
Ten years after Hurricane Katrina, vital ecosystem restoration remains incomplete. Rather than abide by the clear intent of Congress and begin the immediate implementation of a plan to restore that which the Corps helped destroy, defendants arbitrarily and capriciously misconstrued their clear mandate to restore an ecosystem ravaged by MRGO. Defendants would require the State of Louisiana to pay over a third of the cost of repairing the ecosystem damage that MRGO has inflicted, having not even attempted to obtain funding for the full cost of the project through the appropriations process.
Unfortunately, coastal restoration necessitated by MRGO remains stalled while the legal wrangling continues. Due to its arbitrary and capricious action, the Corps has compounded the problems that MRGO caused. The legal issues resolved by this Court will be reviewed and, if this Court’s reasoning is incorrect, the State of Louisiana may be forced to decide whether it will spend close to a billion dollars to repair the damage that resulted from a project designed and constructed not by the State of Louisiana, but by the federal government.
For the foregoing reasons,
IT IS ORDERED that plaintiffs motion for summary judgment is GRANTED, and that defendants’ motion for summary judgment is DENIED.
IT IS FURTHER ORDERED that defendants’ decision to require plaintiff to provide any funding toward the MRGO closure and ecosystem restoration project is VACATED because such decision was arbitrary and capricious and not in accordance with the law, and the issue is REMANDED to the Corps for further proceedings consistent with this opinion.
. R. Doc. Nos. 24, 25.
. "Fetch is defined as the width of open water that wind can act upon. The height of waves (such as the storm surge created by Katrina) is a function of the depth of the water as well as the width of the expanse (i.e., the fetch) over which wind impacts the water.” In re Katrina, 696 F.3d at 443 n. 2.
. Although WRDA 2007 passed through Congress with substantial bipartisan support, President Bush vetoed the legislation, explaining in part: "This bill lacks fiscal discipline. ... This bill does not set priorities. The authorization and funding of Federal water resources projects should be focused on those projects -with the greatest merit that are also a Federal responsibility.... This bill promises hundreds of earmarks and hinders the Corps’ ability to fulfill the Nation’s critical water resources needs — including hurricane protection for greater New Orleans.... ” President Bush Vetoes Water Development Act of 2007, 2007 WL 3231250 (Nov. 2, 2007).
. This point was repeatedly emphasized during floor debate in both houses of Congress, and WRDA 2007 begins with the description: "An Act To provide for the conservation and development of water and related resources, to authorize the Secretary of the Army to construct various projects for improvements to rivers and harbors of the United States, and for other purposes.” (emphasis added). See also WRDA 2007 § 7012(b) ("Activities authorized by subsection (a) and section 7013....”) (emphasis added); R. Doc. No. 24-1, at 6 ("[Sjection 7013 provided authorization for the Corps to implement an ecosystem restoration project in accordance with the 7013(a)(3) plan if the Secretary determines that the ecosystem-restoration project is cost-effective, environmentally acceptable, and technically feasible.”) (emphasis added); R. Doc. No. 25-2, at 26 ("The above authorization [in WRDA 2007 § 7013(a)(4)] is important as it is a deviation from the standard congressional practice of requiring a separate enactment to authorize the [Corps] to construct a project, and makes the project self-authorizing, following the submission of a feasibility report.”) (emphasis added).
The distinction between authorization bills and appropriations bills is a crucial one. "Congress has established a process that provides for two separate types of measures— authorization measures and appropriation measures. These measures perform different functions. Authorization acts establish, continue, or modify agencies or programs.... Appropriations measures provide new budget authority for programs, activities, or agencies previously authorized. Congress is not required to provide appropriations for an authorized discretionary spending program.” Jessica Tollestrup, Cong. Research Serv., RL 42388, The Congressional Appropriations Process: An Introduction 10-11 (2014), available at http://www.senate.gov/CRSReports/ crs-publish.cfm?pid=% 260BL% 2BP%;3% 3C%3 B3% 0A (last accessed August 27, 2015).
.R. Doc. No. 24-2, ¶ 1; R. Doc. No. 35-2, ¶ 1. The report was based on a January 29, 2008 letter by R.L. Van Antwerp, Lieutenant General, U.S. Army, Chief of Engineers. See Administrative Record (“AR”) 2432.
. R. Doc. No. 24-2, ¶ 3; R. Doc. No. 35-2, ¶ 3; AR 2428.
. R. Doc. No. 24-2, ¶4; R. Doc. No. 35-2, ¶ 4; AR 2428-2431.
. R. Doc. No. 24-2, ¶ 9; R. Doc. No. 35-2, ¶ 9; see also, e.g., AR 2730.
. See R. Doc. No. 24-2, ¶¶ 9-14; R. Doc. No. 35-2, ¶¶ 9-14; AR 2743.
. R. Doc. No. 24-2, ¶ 15; R. Doc. No. 35-2, ¶ 15.
. R. Doc. No. 24-2, ¶ 16; R. Doc. No. 35-2, ¶ 16; AR 2427-2428.
. R. Doc. No. 25-1, ¶ 11; R. Doc. No. 34-1, ¶ 11; AR 1777-1791.
. R. Doc. No. 25-1, ¶ 24; R. Doc. No. 34-1, ¶ 24; AR 1779.
. R. Doc. No. 25-1, ¶ 25; R. Doc. No. 34-1, ¶ 25; AR 1779-1780.
. See R. Doc. No. 25-1, ¶ 26; R. Doc. No. 34-1, ¶ 26; AR 1780.
. R. Doc. No. 25-1, ¶ 31; R. Doc. No. 34-1, ¶ 31; AR 1777-1791, 1797, 1799-1811.
. R. Doc. No. 1.
. R. Doc. No. 25-3.
. On April 1, 2015, the Court established the briefing schedule at a status conference attended by counsel. R. Doc. No. 19. On June 26, 2015, nearly three months after the status conference and less than four weeks before the filing deadline for the motions for summary judgment, the parties filed a joint motion to continue the briefing schedule regarding such motions in order to allow for additional time to supplement the administrative record. R. Doc. No. 20. On July 1, 2015, the Court denied the parties’ motion due to a lack of good cause. R. Doc. No. 21.
. R. Doc. No. 24-2, ¶ 4; R. Doc. No. 35-2, ¶ 4; AR 2428-2431.
. R. Doc. No. 24-1, at 13-14. Section 2401 states that "every civil action commenced against the United States shall be barred unless the complaint is filed within six years after the right of action first accrues.”
. R. Doc. No. 24-1, at 14. Despite plaintiffs apparent confusion as to the nature of the Corps' defense, see R. Doc. No. 35, at 21 ("There are several reasons why 28 U.S.C. § 2401(a) and laches are inapplicable to this matter. And although any attempt to apply laches is incorrect in this matter, it is important to note that the [Corps] has not alleged that the entirety of the State’s case is time-barred.”), the briefing is clear that defendants assert a statute-of-limitations defense (not a laches argument) solely against plaintiff’s challenge to their decisions regarding the closure structure. E.g., R. Doc. No. 37, at 6 ("Plaintiffs claim that the Defendants raised the equitable defense of laches.... We did not. Instead, we argued in our opening motion that Plaintiffs brought their claim concerning cost-sharing for the closure structure beyond the applicable statute of limitations under 28 U.S.C. 2401(a).”).
.R. Doc. No. 35, at 22.
. R. Doc. No. 35, at 24.
. E.g., AR 2428, ¶ 5.
. AR 2428, ¶ 5.
. AR 2429, ¶ 10 (emphasis added).
. AR 2429, ¶ 7 (emphasis added).
. In connection with the issue of the finality of the Corps' action, the parties cite and discuss the four factors identified in Dunn-McCampbell Royalty Interest, Inc. v. Nat’l Park Serv., 112 F.3d 1283 (5th Cir. 1997), a case that was decided approximately two months after Bennett. See R. Doc. No. 24-1, at 13; R. Doc. No. 35, at 21. Recent Fifth Circuit jurisprudence regarding this issue has focused solely on the Bennett conditions, e.g., Belle Co., 761 F.3d at 388-90; Nat’l Pork Producers, 635 F.3d at 755, and the Court is not aware of other Fifth Circuit cases that have applied Dunn in this context. Accordingly, this order and reasons confines its analysis to the Bennett conditions.
. See, e.g., R. Doc. No. 24-1, at 10-11; R. Doc. No. 25-2, at 18-19.
. R. Doc. No. 24-1, at 18.
. See, e.g., R. Doc. No. 24-1, at 24 ("Recognizing that the [4th Supplemental] is ambiguous on restoration costs, the Corps looked to other statutory provisions that address cost-sharing for restoration projects to discern Congress’s intent.”); see also 33 U.S.C. § 2218 (“Unless otherwise specified, the cost sharing provisions of this subchapter shall apply to all projects in this Act.”).
. R. Doc. No. 37, at 3.
. R. Doc. No. 37, at 3 (alterations and error in original).
.R. Doc. No, 24-1, at 20 (quoting OSG Bulk Ships, Inc. v. United States, 132 F.3d 808, 813 (D.C.Cir. 1998)); R. Doc. No. 24-1, at 24.
. See supra note 4.
Reference
- Full Case Name
- The State of LOUISIANA, through the Coastal Protection and Restoration Authority Board and the Coastal Protection and Restoration Authority v. UNITED STATES ARMY CORPS OF ENGINEERS
- Status
- Published