Alston v. Ross
Cases that cite this one
2 later published cases cite this decision.
- Gulotta v. Swinney (La. Ct. App. 1962)
- Peterson v. Peralta (La. Ct. App. 1926)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
This suit is brought for the balance of the price' of houses built for the defendant, according to a contract, and for extra work. The defendant pleaded the general issue, but admitted, that she was indebted to the plaintiff in the sum of $963, and claimed damages, in reconvention, for the plaintiff’s delay in delivering the houses ; fof his failing to put eleven sets of window shutters to the houses ; and for neglecting to make a fence of one hundred feet in length, and to paint the houses in a workmanlike manner. In a supplemental answer, the defendant claimed in compensation a sum which she had been compelled to pay for the plaintiff, since her original answer. The court sustained the plaintiff’s claim for $1031 04-|, disallowed the defendant’s claim
It is therefore ordered and decreed, that the judgment be annulled and reversed, and that the plaintiff recover, from the defendant, the sum of $845 04-| with legal interest from judicial demand until paid, and with costs in the Parish Court, and that he pay those of this appeal.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.