Mooney v. Cage
Mooney v. Cage
Opinion of the Court
This action is to recover the sum of $246$ 85, with legal interest, for making a quantity of bricks on the defendant’s plantation, and laying them in the erection of the walls of a sugar house, and other buildings. The petitioners allege, that they made and burned 718,520 bricks; and that they used in erecting the walls of the sugar house, and overseer’s house, 721,680, besides some used in the erection of a chimney, and for other purposes. For making the bricks, they claimed one dollar per thousand ; and for laying them, one dollar and seventy-five cents per thousand. Compensation is also claimed for extra work on different buildings. It is said, that a written contract was entered into, which the defendant has in his possession, and refuses to deliver, or give a copy of. An account is, therefore, filed, and the value of the labor and services claimed.
The answer, after a genera! denial, avers, that the defendant employed the plaintiffs to do all the brick work on the sugar house, except the setting of the kettles; but that they abandoned the work and refused to complete it, in consequence of which, the defendant was obliged to employ one John M. Brooks to finish it, whereby, from the increased price he was obliged to give, and the delay, damage to the amount of $1000 had accrued, which he claims. It is further denied, that the plaintiff ever performed the quantity of work charged, or that there was any amicable demand for settlement or payment. The defendant alleges, further, that the written contract is lost or mislaid, and that the prices charged exceed those mentioned in it. He avers, that the measurement made was ex parte ; and he prays the court to appoint experts to measure it. He further avers, that payments to the amount of $957 23 were made, and that an agreement was entered into to defer the payment of any other sum for one year, from the date of the last receipt; which period not having elapsed, the suit was declared to be premature, and its dismissal asked for.
On the application of the defendant, two experts were appointed to measure the work done by the plaintiffs, one selected by each party.
, In a supplemental answer, the defendant interrogated the
On the trial, the written contract was produced by the defendant, who alleged that he had found it a few days before. It provides that the plaintiffs are to make as many bricks as the defendant shall require, to construct the sugar house and other buildings, and also, “ to lay the bricks, and make the sugar house and other buildings, on such plan” as the defendant may direct. After various clauses, it provides how the openings, (the doors and windows,) are to be calculated in making the measurement, and recites, that it is alleged by the plaintiff to be usual to charge an extra price for chimneys, and a ratio is fixed, by which the extra price is to calculated, if the custom be shown. The setting of the sugar kettles is specially excluded from the contract. The prices for making and laying the bricks, are those mentioned in the petition. It is also agreed, that the payment of the money is not to be deferred longer than the 1st of April, 1843; and the amount is to bear interest at eight per cent, from the 1st of Jan-' uary in that year, if not previously paid.
The experts appointed by the court, reported their measurement and calculation of the number of bricks in the sugar house, and overseer’s house, at 698,463. Pellón, one of the experts, who is a planter, says, that the report shows their mode of proceeding ; that they measured all the work shown them by Hill-man, and that, including the foundation of a bell house, the whole number of bricks is 725,721, the work done by Brooks not included. The testimony of Grinage, the other expert, accords with that of Pellón. In explanation they say, that they calculated sixteen bricks to the cubic foot, relying upon the correctness of Nicholson’s tables. Neither of the experts wrnre brick-masons or mechanics; but had seen a great deal of brick work, and had had it done for themselves. The plaintiffs offered the testimony of a brick-mason, who had followed the business since the year 1806. He says that he accurately measured the work, and made the calculations; and that he furnished the statement upon which the
The second bill of exceptions was taken to permitting the plaintiffs to use the deposition of Wm. Winchester, as evidence. The objection was, that certain interrogatories, propounded by the de~
We have looked into the merits of the case, and carefully examined the testimony, to see if any material error has been committed, to ,the prejudice of the defendant; and find no sufficient reason either to reverse the judgment, or to reduce the amount. We think that the jury have come very near what is right, and have dealt fairly with the parties.
The plaintiff has asked us to amend the judgment, so as to allow him legal interest from judicial demand. This we cannot do. It was not found by the jury, nor'allowed in the inferior court; nor was the application to amend filed in proper time in this court, having been presented only the day before the cause was called for argument, and after a joinder in error. Code of Practice, art. 890.
Judgment affirmed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.