Godchaux v. Chicago Lumber & Coal Co.
Godchaux v. Chicago Lumber & Coal Co.
Opinion of the Court
Plaintiff sued to recover a balance of $7,590.13 alleged to he due for cypress lumber sold and delivered to the defendant under two contracts, one for 500,-000, and the other for 1,000,000, feet. It is admitted that 414,874 feet of the total amount of lumber covered by these contracts was never delivered. Defendant averred that the nondelivery of the lumber was a breach of contract, and reconvened for damages in the sum of $2,074.37 for loss of profits. There was judgment in favor of the plaintiff for $3,840.27, and the reconventional demand was rejected. Defendant has appealed.
The appellant contends that the judgment in favor of the plaintiff should be for $3,475, less the amount of damages claimed in re-convention. Our learned brother below, in a well-considered opinion in which the figures are given, found a balance of $3,840.27 due the plaintiff on a settlement of accounts, after rejecting several small credits claimed by the defendant as not proven or as not due. Defendant’s counsel has not pointed out wherein the trial judge erred in rejecting the items of demurrage and interest.
The real issue in the case is the question of damages, the consideration of which requires a brief statement of the facts of the case.
Our learned brother below found on the evidence that the defendant, after accepting two deliveries of lumber under the contract from temporary lessees of the plaintiff, who had assumed his obligations, refused to accept lumber from them, when “the price of lumber had gone down in’ October, 1907, and the panic came on, and there was a general shrinkage in the value of lumber.” The fact that over half a million feet of lumber delivered under the contract was on the mill yards in February, 1908, when it. was destroyed by fire indicates that the lumber could not be marketed at a profit. ■
Judgment affirmed.
Reference
- Full Case Name
- GODCHAUX v. CHICAGO LUMBER & COAL CO.
- Cited By
- 3 cases
- Status
- Published
- Syllabus
- (Syllabus by the Court.) 1. Contracts (§ 278*) — Action fob Breach. A party cannot claim damages for the breach of a contract as to which he himself is in default. [Ed. Note. — For other cases, see Contracts, Cent. Dig. §§ 1207-1213; Dec. Dig. § 278.*] 2. Sales (§ 406*) — Failure to Deliver — Default in Payments. A purchaser, who had not paid in full for lumber delivered and accepted, cannot sue for damages for the nondelivery of other lumber covered by the same contract, without first paying or tendering the balance due for the lumber already received by him. [Ed. Note. — For other cases, see Sales, Cent. Dig. §| 1156-1158; Dec. Dig. § 406.*] 3. Sales (§ 405*) — Failure to Deliver — Action fob Damages. A purchaser, who has himself breached a contract for the sale and delivery of lumber by refusing to accept lumber tendered for account of the vendor, cannot sue for damages for nonperformance of the contract. [Ed. Note. — For other cases, see Sales, Cent. Dig. §§ 1147-1155; Dec. Dig. § 405.*]