Findlen v. Winchendon Housing Authority
Cases that cite this one
2 later published cases cite this decision.
- XL Specialty Insurance v. Massachusetts Highway Department (Massachusetts Superior Court 2013)
- Bonacorso Construction Corp. v. Commonwealth (Mass. App. Ct. 1996)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Although the construction contract between the Winchendon Housing Authority (Authority), as owner, and Fred J. Findlen & Sons (Findlen), as general contractor, contained a sweeping provision disclaiming any liability by the owner for job delays, Findlen obtained, on account of delay damages, a judgment for $29,056.82, the amount it paid in a separate action to one of its subcontractors, plus $2,500 in attorney’s fees. We conclude that through a series of memoranda and letters the owner modified the scope of the original provision exculpating it from a duty to pay delay damages and we affirm the judgment.
What caused the delays in question is not disputed. Findlen was the successful bidder on a housing job for the Authority and entered into a contract on June 11, 1975. On the basis of prior unsatisfactory experience, Findlen rejected the low filed sub-bid for roofing. See par. (1) of G. L. c. 149, § 44I, inserted by St. 1956, c. 679, § 1,
Indeed, the Authority commendably acknowledged the damage the delay had caused to Findlen and paid to Findlen $122,726 for “[ejxtra costs due to job delays.” That act, as documented, and other papers, which we detail below, point to the resolution of the controversy. Parties to a written contract may, of course, alter it subsequently, by oral modification, by their joint conduct, or, ideally, by a writing subscribed to by the persons to be bound. See M.L. Shalloo, Inc. v. Ricciardi & Sons Constr., Inc., 348 Mass. 682, 685-686 (1965); A. Leo Nash Steel Corp. v. Southern N.E. Steel Erection Co., 9 Mass. App. Ct. 377, 383-384 (1980); Worcester Air Conditioning Co. v. Commercial Union Ins. Co., 14 Mass. App. Ct. 352, 357 (1982). Words and actions of parties, such as statements in letters, may effect a waiver or modification of a provision in a contract. See Gouzoulas v. F.W. Stock & Sons, 223 Mass. 537, 539 (1916); Martiniello v. Bamel, 255 Mass. 25, 28 (1926).
In itself, the Authority’s act of paying $122,726 on account of delay stands for a waiver, at least to that extent, of the “no delay damages” clause. Standing alone, however, one might hesitate to say that a single
Two other points raised by the Authority in its brief are susceptible of cursory disposition. The Authority protests that Findlen’s claim for compensation is barred by Findlen’s having failed to join the Authority as a necessary party in the earlier action between PDM and Findlen (in which the damages sustained by PDM because of the roofing delay were established). In so arguing, the Authority subjects itself to some embarrassment. The record discloses that, in fact, Findlen invited the Authority to intervene as a party in the PDM-Findlen suit, an invitation the Authority apparently declined, whereupon Findlen moved to implead the Authority. That motion was denied. Concerning the application to this case of G. L. c. 30, § 390(a), it is sufficient to say that the plaintiff, Findlen, never made a claim under that statute. General Laws c. 30, § 390, inserted by St. 1973, c. 1164, requires an awarding authority to adjust the contract price when it makes a written order “to suspend, delay, or interrupt all or any part of the work. . . .” No such order was ever made. We do not decide, because the question has not been presented, whether “no delay damages” clauses are valid in the light of the first paragraph of § 390.
Judgment affirmed.
The cognate provision, by reason of the enactment of St. 1980, c. 579, § 55, now appears in G. L. c. 149, § 44F(4)(a).