Bryer v. P. S. Thorsen
Opinion of the Court
Action of contract to recover the sum of $622.45 for labor and materials furnished as a result of delay in the performance of a contract. Except for that issue raised by the substitution of an assignee of the plaintiff’s claim for the plaintiff, all other issues in this controversy have already been considered by the Supreme Judicial Court in the opinion in P. A. Dolan Company v. P. S. Thorsen Company of Mass., 324 Mass. 376. In this opinion the liability of the defendant to the plaintiff for breach of his agreement is clearly established. The cause was remanded ‘ ‘ for further proceedings” on the issue of damages alone, the opinion having recited the rule of damages which should have been followed by the court in ascertaining the amount to which the plaintiff was entitled.
Notwithstanding the concise issue presented by the order of the Supreme Judicial Court, the defendant claims to be
We cannot agree with this contention. There is no reason why an already complicated and confused record should be further embarrassed by a retrial of issues already determined.
Nor can we seriously entertain the defendant’s objection to the evidence of Edward T. Kilmaine with respect to the damage suffered by the plaintiff. Even if some part of the evidence was incompetent no objection was specifically directed to its admission at the time it was offered, and once admitted there was no obligation on the court to disregard it or strike it out. Crowley v. Swanson, 283 Mass. 82. The report discloses that the defendant’s objection to Kilmaine’s evidence was general and directed to his testimony in its entirety. A report claimed to the court’s refusal to sustain such an objection leaves no question in issue before this court. Solomon v. Dabrowski, 295 Mass. 358. With respect to the items in issue we cannot say that the court was not in a position on the basis of the evidence reported to estimate the amount of the damage. Bradford v. Cunard Steamship Co., 147 Mass. 55, 57.
Prior to the retrial of this cause an amendment was offered substituting the plaintiff’s attorney for the plaintiff by reason of an assignment dated July 23, 1948. The amendment was allowed over the defendant’s objection. Although the court initially limited the issues in this cause to the question of damages, after the evidence had been closed, the court on its own motion reopened the cause for further hearings with respect to the validity of the assignment. To the reopening of the hearing on this issue the defendant objected.
We cannot agree with the defendant’s contention that the court by its previous ruling was prevented from modifying
It is unnecessary to elaborate on the questions raised concerning champerty. There was ample evidence to warrant the court in finding that the assignment was given to secure the assignee for advances in money and for a debt for legal services. Such an arrangement would not be illegal or champertous. Blaisdell v. Ahern, 144 Mass. 393, 395; Hadlock v. Brooks, 178 Mass. 425; Delval v. Gagnon, 213 Mass. 203. Report dismissed.