Page v. Huntoon
Opinion of the Court
Underlying this appeal is an action filed in December 1988 against a contractor for negligence, breach of contract, and violation of 93A. Summary judgment entered against the plaintiff on the negligence and 93A counts, and a trial judgment entered against Mr. Page on the breach of contract claim under the common ruling that the actions were barred by statutes of limitation. This appeal challenges those rulings.
We begin our review with an examination of the trial judge’s written decision. In his findings of fact, the trial judge determined that Mr. Page, acting as a general contractor, orally contracted with Mr. Huntoon for the installation of Sheetrock on an addition to Page’s home. Finding that the work had been completed by October of 1982, the judge ruled that this action was barred unless the defective work was inherently unknowable or the defendant had concealed the defect or prevented the plaintiff from discovering it. These tolling conditions were inapplicable, the Court ruled, as the plaintiff, an expert in spray painting, had complained in October of 1982 to the defendant on his defective application of primer to the Sheetrock.
Although not contained in his decision, the trial judge’s report discloses additional evidence on the parties’ agreements and subsequent acts. According to the report, the defendant expressly warranted that the work would match the quality of previous work and that he “would stand behind his work.” Once notified by Page of workmanship complaints, the defendant renewed this promise to stand behind the work. Influenced by this reaffirmation, Page allowed Huntoon to finish the job. By 1985, though, the paint began flaking and peeling and, in 1986 and 1987, the peeling and flaking increased and spread through the first and third floors. Inspection by Sherwin-Williams through an electronic microscope disclosed the cause of the flaking and peeling to be an overly thick primer application. Notified of the Sherwin-Williams finding, the defendant failed to correct the work and ultimately refused, suggesting
Massachusetts General Laws Chapter 260, §2A, allows three years for filing a negligence action. “A negligence action ... in [general] accrues when the [act] happens and the person is injured.” International Mobiles Corp. v. Corroon and Black/Fairfield and Ellis, Inc., 29 Mass. App. Ct. 215, 218 (1990). However, where the negligence or harm is unknowable, the limitations’ clock starts upon the happening of an event “likely to put the plaintiff on notice” that a negligent act took place and that “appreciable harm was sustained.” Id. at 218.
Defendant suggests that we need not compute this negligence count’s starting date, as this action in any event is barred by M.G.L Chapter 260, §2B, a statute of repose.
We now turn to the contract count M.G.Lc. 260, §2, allows she years for filing a contract claim. A contract action for purposes of §2 accrues “at the time of breach... and this rule applies even though a specific amount of damage is unascertainable at the time of breach or even if damages may not be sustained until a later time.” International Mobiles Corp., Id. at 221; also see DiGregorio v. Commonwealth, 10 Mass. App. Ct. 861, 62 (1980); Campanella & Cardi Construction Co. v. Commonwealth, 351 Mass. 184, 187 (1966). Under this time line, summary judgment was correct, as the breach occurred and was complained of in October, 1982, over six years before the filing of this complaint
This bar, though, plaintiffs counsel argues, is avoided by the additional promise of defendant to stand behind his work that was not breached until 1987 when the defendant refused to correct the work. “‘Plaintiffs argument is in essence that by failing to remedy its first breach, the defendant committed a second breach, giving rise to a brand-new cause of action and starting anew the limitations period. The fallacy of this approach is apparent. If we adopted plaintiffs position, limitations periods could be extended for virtually infinite time. We doubt that the Legislature intended such a result.’” New England Power v. Riley Stoker Corp., 20 Mass. App. Ct. 25, 30-31 (1985), quoting Centennial Ins. Co. v. General Elec. Co., 77 Mich. App. at 172, 253 N.W.2d 696.
The 93A count sets forth as unfair or deceptive acts:
Judgments for defendant are affirmed, and the report is dismissed.
In reviewing summary judgment, Appellate review is not limited to the motion judge’s stated reason but extends to any ground supporting the judgment. See Hanson Housing Authority v. Dryvit Systems, Inc., 29 Mass. App. Ct. 440, 444 (1990); Champagne v. Commissioner of Correction, 395 Mass. 382, 386 (1988).
Plaintiffs complaint
Case-law data current through December 31, 2025. Source: CourtListener bulk data.