Brown v. Vinal
Brown v. Vinal
Opinion of the Court
In this action to recover damages for the breach of a covenant, the following facts were agreed on between the parties : The defendants were sub-contractors, under Stockton & Stokes of Baltimore, for carrying all the United States mails between Boston and Providence ; and for the purpose of fulfilling their contract, they entered into a sealed agreement with the plaintiffs, bearing date October 30th 1835, to carry the mails mentioned in their contract with Stockton & Stokes; and, among other things, to leave Boston, with the Providence way mail, at 5 o’clock A. M., and deliver the same in Providence at 12 o’clock, M., from the date of said agreement to the 1st of January 1837 ; for which, and for carrying the other mails as agreed by the plaintiffs, the defendants covenanted to pay them the sum of $ 1250; with this proviso, however — “if the time of the delivery of the way mail at Providence shall be changed to 3 o’clock, then in that case the said Vinal” & others “ are to pay the said Brown ” & others “ the sum of $ 1000, and no more.”
The plaintiffs carried the mad, from and after the said 30th of October, agreeably to their contract, and fully performed the
During the existence of the contract, permission was given to the plaintiffs, by the post office department, to leave Boston, with the Providence way mail, at 8 o’clock, A. JVL, instead of 5 o’clock, to be delivered in Providence at 3 o’clock. This permission was granted on the 10th of August 1836, and continued in force until the 24th of said August, when it was revoked, and the plaintiffs were obliged to leave, and did leave Boston, with the way mail for Providence, at 5 o’clock, A. M. during the residue of the time embraced in the contract: So that during the whole time, except the above 14 days, the plain tiffs left Boston with that mail at 5 o’clock, A. M.
The defendants have paid the plaintiffs in full, for carrying the mail under said contract, provided they are entitled to receive only the smaller sum of $ 1000, mentioned in the contract.
It is contended by the defendants, that this is one entire contract, and cannot be apportioned ; and as, during a part of its existence, the mails did not leave Boston until 8 o’clock, A. M. — and that by consent of the plaintiffs — the right to receive a larger sum than $1000 was waived by them ; and that although the government revoked the aforesaid permission, at the end of 14 days, yet as the contingency had happened, that the delivering of the way mail at Providence was changed from 12 o’clock to 3, the defendants were wholly released from their obligation to pay the plaintiffs a larger sum than $ 1000.
No cases have been cited on either side, which bear directly on the case at bar. But the defendants apply general reasoning, in relation to the construction of entire contracts, to the present case. It is indeed held, that an entire contract cannot be apportioned. So when an entire sum is to be paid for an entire work, the entire performance of the work is, in general, a condition precedent, and must be proved before the defendant can be called on for payment. Cutter v. Powell, 6 T. R. 326. Countess of Plymouth v. Throgmorton, 1 Salk. 65. Hulle v. Heightman, 2 East, 145. Stark v. Parker, 2 Pick. 267; and numerous their cases.
According to the stipulation of the parties, the defendants are to be defaulted, and judgment entered pursuant to their agreement.
Reference
- Full Case Name
- Thomas P. Brown & others v. Robert Vinal & others
- Status
- Published