Pond v. Merrifield
Pond v. Merrifield
Opinion of the Court
In an action on a penal bond, there being a plain breach in not finishing the building within the time limited by the condition of the bond, as appears by reference to the contracts, there must be judgment for the plaintiff, at least for nominal damages.
But the question is, whether extra insurance, occasioned by the delay in completing the building, and paid by the plaintiff, can be recovered in this action. We think not. Take the whole finding of the jury, and the result is, that by the extra
Judgment for the plaintiff for one cent damages.
Thomas, J., did not sit in this case.