Opinion of the Court
The objections made to the right of the petitioners to commence and prosecute this proceeding are untenable.
2. The position that the land was entered upon by the defendants under an agreement for its purchase, and not taken in the exercise of the right of eminent domain, is not supported by the facts in proof. The defendants could not have relied on their executory contract for the purchase of the land in entering upon it and locating their road over it. At the time of their entry and location they had no title to the estate, nor any right to take possession of it. The owners having then refused to perform their contract for the conveyance of the estate, the defendants were left to their legal and equitable remedies for its breach. The only right which they had to enter upon and take the property was under the power conferred by their charter; and the location filed by them in pursuance of Rev. Sts. c. 39, § 75, is decisive evidence that they acted under the statute and by virtue of their location in taking the land, and not under any supposed or implied assent of the owners.
3.. We are then brought to the consideration of the exceptions to the rulings of the court touching the title of the petitioners to the land and easements for the taking of which damages are claimed in this proceeding. The first raises a question as to the permanent nature of the right claimed by the petitioners in the canal which was filled up by the defendants. On this point we can entertain no doubt. The deed under which they claim conveys a privilege in the canal to hold to them and their heirs and
4. The next question arising on this branch of the case involves an inquiry into the right of the petitioners to an easement in the space immediately adjoining the wall of the canal, over which a platform had been erected resting on piles. As it is admitted that the petitioners have acquired no title by adverse use or occupation, the extent of their right must depend on the construction of the deed from the Boston Mill Corporation under which their title to the premises in controversy was derived. Qn looking at the terms of this grant, it appears that the land conveyed was described as a lot on the canal, and was bounded southwesterly thereby, “ being canal lot number two as laid down on a plan,” to which reference is made. Taking this description in connection with the plan, it is clear that the premises conveyed were bounded by the canal, and did not extend beyond it. If there were any doubt of this on the language of the grant, it is manifest from an inspection of the plan, which is to be deemed a part of the description, that the intent was to convey a lot bordering on the line of the canal, and to exclude any land comprehended within the limits of the canal itself. But it is claimed by the petitioners that the right to erect the platform is conveyed by the clause in the deed which gives to the grantees “ a privilege in said canal,” and a permission to “drive piles against such parts of the wall as have projected into the canal, from which land ties may be fastened to prevent any further pressure outwards.” We cannot think that this is a reasonable interpretation of this part of the deed. The grant of a privilege in the canal was intended only to give to the grantees a right to use it for navigation, and as adjacent to the wharf lot for the usual purposes to which a water way might be
5. It was contended by the defendants that the original grant from the Boston Mill Corporation did not include the projection in the wall which existed at the date of the deed, but was confined to the line of the wall as originally built, so that the defendants had no title beyond a straight line drawn from one corner of the lot granted upon the canal to the other. But the words of the deed, taken in connection with the plan, do not warrant such an interpretation. The premises granted were bounded by the canal, that is, by the canal as it was then practically used and constructed, and as laid down on the plan. This clearly comprehended all the land lying northerly of the wall. So it must have been understood by the parties, because by reference to the plan it will be seen that the part which projects into the canal by reason of the irregularity in the wall is laid down as part of lot number two.
6. On the question of damages, it seems to us that the instructions of the court were deficient in not being responsive to
7. The testimony relating to the nature, extent and amount of the business done by the firm of Bartlett & Co. on the
Fkcceptions sustained.