Leighton v. Meserve

Massachusetts Supreme Judicial Court
Leighton v. Meserve, 117 Mass. 50 (Mass. 1875)
1875 Mass. LEXIS 146
Morton

Leighton v. Meserve

Opinion of the Court

Morton, J.

The original action is an action upon a bond, the condition of which is that Leighton should furnish marble work for six houses, in accordance with the contract previously made between the parties. The original defendant admits that he has not furnished any of the marble work called for by the bond and contract, and attempts to justify his refusal to do so upon the ground that Meserve had not finished the house conveyed by him *51to Leighton, according to his agreement in the contract. This ground can only be sustained upon the assumption that the performance by Meserve of his agreement was a condition precedent to the performance by Leighton of his undertaking to furnish marble work. But upon an examination of the contract and the relations of the parties, it is clear that such was not their intention. By the contract, Leighton agreed to furnish marble work to the amount of $6000 for a block of eleven houses according to certain specifications, in payment for a house conveyed to him by Meserve, at the time the contract was made; and as a further consideration, Meserve entered into an executory agreement, embodied in the contract, that he would finish the house thus conveyed within a limited time. Thus Meserve paid Leighton in advance the greater part of the consideration of his agreement, and the contract plainly contemplates that Leighton is to go forward furnishing the marble work before the time at which Meserve agreed to have the house finished. Both agreements were executory, to be performed in the future, and it was the intention of the parties that the work under both should go on at the same time, and such was the construction practically adopted by both of the parties. The fact therefore that Meserve has not fully performed his agreement is not a bar to his action, but Leighton’s remedy is, the one he has in fact adopted, a cross-action for the breach of such agreement. The ruling of the referee upon this point was correct. We have considered this question upon the theory adopted by the original defendant, that the bond in suit was not an independent contract, but was in substance merely a guaranty of the original contract. We have not deemed it necessary to consider whether this theory is correct, because, if it is, the ground taken by the defendant cannot prevail. The objection to the other ruling of the referee is not insisted on.

As there was no error in law in the rulings of the referee, the plaintiff is entitled to judgment unon his award.

Exceptions overruled.

Reference

Full Case Name
John W. Leighton & another v. George W. Meserve
Status
Published