Stebbins v. Conners Bros. Construction Co.
Stebbins v. Conners Bros. Construction Co.
202 Mass. 153; 88 N.E. 1135; 1909 Mass. LEXIS 816
Opinion of the Court
Upon the evidence we think that the questions whether there ever was an agreement that the giving of a bond should be a condition precedent to the validity or binding force of the contract, and whether, if there ever was such an agreement, there was a waiver of the condition, were for the jury, and that the case should have been submitted to them.
Exceptions sustained.