Commonwealth Electric Co. v. Department of Public Utilities
Commonwealth Electric Co. v. Department of Public Utilities
Dissenting Opinion
(dissenting). The Federal Power Act extends the scope of Federal regulatory jurisdiction “to the sale of electric energy at wholesale in interstate commerce.” 16 U.S.C. § 824 (b) (1) (1982). However, Congress did not limit jurisdiction to sellers at wholesale, but rather conferred jurisdiction over wholesale transactions. See, e.g., Panhandle E. Pipe Line Co. v. Public Serv. Comm’n, 332 U.S. 507, 516-518 & nn. 13, 14 (1947); Appeal of Sinclair Mach. Prods., Inc., 126 N.H. 822, 829 (1985).
Because Congress evidenced “an intent to occupy” the field of wholesale transactions, inquiries relating to the prudence of such transactions (whether focusing upon buyer or seller) would be preempted, Pacific Gas & Elec. Co. v. State Energy Resources Conservation & Dev. Comm’n, 461 U.S. 190, 203-204 (1983), were it not for the fact that Congress has given FERC the power to leave areas of its jurisdiction
It follows therefore that State review of purchaser prudence is limited. “[M]atters actually determined, whether expressly or impliedly, by the FERC” are clearly preempted. Appeal of Sinclair Mach. Prods., Inc., supra at 833. Eastern Edison Co. v. Department of Pub. Utils., supra at 298-302. Even when FERC has chosen to leave purchaser prudence inquiries to the States, it has limited those inquiries. In Pennsylvania Power & Light Co., supra at 61,019, FERC stated:
“However, we note that power supply arrangements are often negotiated on a long-term basis. It requires many years to build a generating plant and the building utility must be able to rely on long-term sales contracts in making its own capacity plans just as the purchasing utility must be able to rely on long-term contracts for stability of supply. Demand forecasts may change dramatically and*384 quickly, as we have seen in recent years. The prudence of a sales arrangement, therefore, should be judged on the circumstances prevailing at the time such a contract is entered into. If a State commission, this Commission, or a utility itself could release a party to a contract from its contractual commitments simply because the contract, based on hindsight and demand forecasts in later years, no longer appears economical, the utility industry would have no supply stability or reliable basis for constructing plant. We therefore suggest that evaluation of the prudence of a 1979 power contract on the basis of 1982 demand forecasts is neither fair nor appropriate. Thus, while we commend the New Jersey Board for its concern in protecting the ratepayers within its jurisdiction, we do not believe that this protection can be at the expense of Pennsylvania ratepayers and utilities. The latter are entitled to rely on the fact that New Jersey utilities will honor their contractual commitments to purchase capacity built at least partly to fulfill their contractual demand.”
Thus, FERC has made it clear that the prudence of entering a wholesale purchase contract at a particular purchase price level should be judged, not on hindsight but rather from the point of view of the time of the contract. Similarly, the prudence of entering into such a contract with particular provisions allocating operating/service responsibilities and risk of supply failure should not be judged on hindsight.
The majority, I submit, err in two ways. First, it was incumbent on the DPU to review the FERC order
Of course, FERC cannot delegate its jurisdiction to regulate in violation of the Federal Power Act nor, apart from that act, can States be given the power to regulate in violation of the commerce clause’s “implied limitation on the power of the States to interfere with or impose burdens on interstate commerce.” Western & S. Life Ins. Co. v. State Bd. of Equalization, 451 U.S. 648, 652 (1981). See Arkansas Elec. Coop. v. Arkansas Public Serv. Comm’n, 461 U.S. 375, 389 (1983).
Thus, Pike County Light & Power Co. v. Pennyslvania Pub. Util. Comm’n, 77 Pa. Commw. 268, 273 (1983), and Spence v. Smyth, 686 P.2d 597 (Wyo. 1984), which hold that FERC has no power under the Federal Power Act to preempt State purchaser prudence inquiries are plainly wrong. Appeal of Sinclair Mach. Prods., Inc. 126 N.H. 822, 830-833 (1985), in citing both of those cases was careful not to rule out categorically the assertion of FERC jurisdiction, and articulated the rule that preemption only extends automatically to “those matters actually determined, whether expressly or impliedly, by the FERC” (emphasis in original).
That order is not in the record.
Opinion of the Court
The Pilgrim Unit 1 nuclear power station (Pilgrim 1) was out of service for several months in 1981 and 1982. The Department of Public Utilities (DPU) issued a series of orders in which it found that the operator of Pilgrim 1, Boston Edison Company (Boston Edison), acted imprudently in certain aspects of the outage. We affirmed those orders. Boston Edison Co. v. Department of Pub. Utils., 393 Mass. 244 (1984). Before
We state the factual background of these proceedings. The company is a retail electric utility company distributing electricity to consumers in forty communities in southeastern Massachusetts. The company owns and utilizes its own generating facilities to meet a portion of its customers’ needs, but most of the electricity it sells is purchased at wholesale from other utility companies. On August 1, 1972, the company entered into an agreement with Boston Edison to purchase 11% of the capacity of Pilgrim 1. The agreement was filed with the Federal Power Commission (FPC) and was accepted by the FPC pursuant to § 205(d) of the Federal Power Act, 16U.S.C. § 824(d) (1982) (FPC docket no. E-8138). The agreement was in effect during 1981 and 1982. The Pilgrim 1 outage made it necessary for the company to obtain replacement power for its customers at a cost greater than the cost of power the company normally would have obtained from Pilgrim 1.
On June 3, 1982, the company notified the DPU that it intended to apply for approval of a change in the allowed fuel charge in its next quarterly filing under G. L. c. 164, § 94G (b) (1984 ed.). The DPU issued a procedural order, D.P.U. 1003-G-l, which stated that the DPU intended to determine the company’s liability for replacement power costs incurred as a result of Boston Edison’s imprudence in the Pilgrim 1 outage. A series of hearings on this issue ensued. In the interim, the DPU authorized a quarterly fuel adjustment charge subject to refund, with interest, pending the outcome of the proceedings. D.P.U. 1003-G-2.
The company appealed from the orders of the DPU, under the authority granted in G. L. c. 25, § 5 (1984 ed.). A single justice reserved and reported the appeal.
The company makes essentially three claims of error: (1) The DPU legally could not impute to the company the imprudence of Boston Edison; (2) the DPU could not issue its orders without exceeding its authority under the provisions of G. L. c. 164, § 94G (1984 ed.); and (3) the DPU could not exercise regulatory authority over the relationship between the company and its wholesale suppliers of power because the Federal government has preempted that authority.
1. Imputation of imprudence. The DPU determined that the company shared the responsibilities and obligations of a joint owner of the Pilgrim 1 unit. This finding was based on the provisions of the contract between the company and Boston Edison.
The company claims that it is in fact not an owner of the Pilgrim 1 unit. We do not read the decision of the DPU to be to the contrary. The DPU found that the company “does not have an ownership share in the Pilgrim 1 unit, [but that] its life-
The DPU’s interpretation was based on five sections of the contract set forth in the margin.
Assuming that the contract provisions shifting responsibility and risk to Boston Edison are indicators of Boston Edison’s predominant ownership role, we do not agree, as the company argues, that the DPU erred in finding enough indicators of the company’s responsibilities and obligations to justify the conclusion that the company’s role is the same as partial ownership for the purposes of the instant inquiry.
The DPU rested its decision on the imputed imprudence of Boston Edison and did not reach the question of the company’s own imprudence. The company argues that it cannot be held responsible for Boston Edison’s acts, absent proof of its control over Boston Edison.
In our view, reliance on tort analogies to define a public utility’s responsibility in a regulated area of rate and fuel costs is unpersuasive. We find ample justification for the DPU’s decision in the policy manifested by the statutory scheme of public utility regulation. The DPU was warranted in finding that the provisions of the contract reveal the company’s intent
The utility and its shareholders are protected from the risks associated with competition.
2. Statutory authority. The company argues that the relevant legislative grant of authority to the DPU, G. L. c. 164, § 94G, does not authorize the DPU to act as it has in this case. In particular, the company says that under § 94G {a) the DPU (1) cannot disallow costs based on vicarious liability; (2) must make a “finding” of imprudent conduct by the company before disallowing costs; and (3) cannot disallow costs of purchased power. The DPU responds that the plain language of the statute, the legislative purpose and policy, and application of principles of statutory construction demonstrate that the DPU has the authority to disallow costs of purchased power due to the company’s imputed imprudence.
It is our task to interpret the statute. Casey v. Massachusetts Elec. Co., 392 Mass. 876, 879 (1984). Cleary v. Cardullo’s, Inc., 347 Mass. 337, 334 (1964). An examination of the statute
If the company’s performance varies from its approved performance targets, the DPU may order the company to explain the variance at its next fuel charge hearing under § 94G (b). “In the course of such hearing, the department shall investigate such variance, may otherwise inquire into an issue related to the procurement or use of fuel or purchased power included in the fuel charge and properly raised by any party, and, in either event, shall make a finding whether the company failed to make all reasonable or prudent efforts consistent with accepted management practices, safety and reliability of electric service and reasonable regional power exchange requirements to achieve the lowest possible overall costs to the customers
The company, though it had received DPU approval for a fuel charge, had no approved § 94G (a) performance program in place during the relevant time periods. The DPU justified its application of § 94G (a), nevertheless, under § 7 of the Fuel Charge Act, St. 1981, c. 375. That section provides: “Any fuel charges approved subsequent to the effective date of this act and prior to the approval of the initial performance program pursuant to subsections (a) and (b) of section ninety-four G of chapter one hundred and sixty-four of the General Laws, shall be subject to review and such other provisions of said subsections (a) and (b).”
The review procedure of § 94G (a) permits the deduction of imprudently incurred fuel costs from the fuel charge for the next quarter. The statute provides for this deduction in the following sentence: “If the department finds that the company has been unreasonable or imprudent in such performance, in light of the facts which were known or should reasonably have been known by the company at the time of the actions in question, it shall deduct from the fuel charge proposed for the next quarter or such other period as it deems proper the amount of those fuel costs determined by the department to be directly attributable to the unreasonable or imprudent performance.” G. L. c. 164, § 94G (a), lines 72-79.
The Legislature did not restrict the DPU to inquiry as to the performance of a utility company “except for” the portions of its responsibility delegated to independent contractors or others. The statutory instructions are quite broad. The DPU is required to determine “whether the company failed to make all reasonable or prudent efforts consistent with accepted management practices, safety and reliability of electric service and reasonable regional power exchange requirements to achieve the lowest possible overall costs to the customers of the company for
The goal of the investigation is clearly spelled out in the statute and is reflected in our consistent and long-standing interpretation of the State’s role in regulating public utilities, see Lowell Gas Light Co. v. Department of Pub. Utils., supra; Boston v. Edison Elec. Illuminating Co., supra, in that the statute charges the DPU to assure that the utility acts “to achieve the lowest possible overall costs to the customers of the company.” G. L. c. 164, § 94G (a), lines 70-71. Restricting the inquiry to exclude performance responsibilities delegated to subcontractors clearly would not further that goal.
The company cites two cases, West Ohio Gas Co. v. Public Utils. Comm’n, 294 U.S. 63 (1935), and Minnesota Power & Light Co., 11 F.E.R.C. par. 61,313 (1981),
The company makes the argument that the process required by the Legislature includes a formal “finding” by the DPU. It relies on the following language: “[T]he department. . . shall make a finding whether the company failed to make all reasonable or prudent efforts consistent with accepted management practices, safety and reliability of electric service and reasonable regional power exchange requirements to achieve the lowest possible overall costs to the customers of the company” (emphasis added). G. L. c. 164, § 94G (a), lines 63-71. Such
The company argues from the text of the statute that the Legislature distinguished “fuel costs” from “costs of purchased power.” The statute authorizes inquiry into “the procurement or use of fuel or purchased power included in the fuel charge,” G. L. c. 164, § 94G (a), lines 65-66 & 71-72, and requires a finding on the utility company’s performance in achieving “the lowest possible overall costs ... for the procurement and use of fuel and'purchased power included in the fuel charge,” id. at lines 70-72, but provides for deduction from the upcoming fuel charge only “the amount of those fuel costs determined by the department to be directly attributable to the unreasonable or imprudent performance.” Id. at lines 77-79.
The company contends that this distinction is a manifestation of the purpose of the Legislature. By parsing the two elements of the fuel charge, the company urges, the Legislature avoided the preemption question, see infra, and focused the enforcement mechanism of the fuel conservation section of the statute on the power-generation performance of the utility, where conservation measures could be effective.
We do not agree that the distinction pressed by the company is meaningful. The Legislature specifically directed the DPU to inquire into, and make a finding on, the prudence of the company’s actions in purchasing power. Were we to accept the company’s interpretation, the Legislature’s direction to the DPU would require a hollow exercise of administrative power for no tangible purpose. Such an interpretation would be “at odds with a workable reading of the entire statute.” American Family Life Assurance Co. v. Commissioner of Ins., 388 Mass. 468, 473, cert. denied, 464 U.S. 850 (1983). The DPU is repeatedly charged to act on matters connected to fuel charges by language linking costs of fuel and purchased power. The statute is aimed at achieving “the lowest possible overall costs ... for the procurement and use of fuel and purchased power” (emphasis added). G. L. c. 164, § 94G (a), lines 70-71. If only costs of fuel used for the company’s own generating units
We do not believe that it was the Legislature’s intent to require the DPU to pursue investigation, inquiry, and oversight of costs of purchased power, yet deny any meaningful conclusion to that investigation. We reject the company’s interpretation and find that the “fuel costs” that may be deducted from the “fuel charge proposed” are the same costs that the Legislature has specified throughout the statute as comprising the “fuel charge,” that is, the “costs of fuel to be used in generating or supplying electricity to customers and power purchased for resale to customers. ” G. L. c. 164, § 94G (b), lines 106-108.
3. Preemption. The company contends that the DPU has been preempted of jurisdiction to disallow the costs at issue here by the Federal Constitution and Federal statute, and thus that its actions are invalid under the supremacy clause of the United States Constitution. Art. VI, cl. 2. The Supreme Court of the United States has observed that “state law can be preempted in either of two general ways. If Congress evidences an intent to occupy a given field, any state law falling within that field is pre-empted. ... If Congress has not entirely displaced state regulation over the matter in question, state law is still pre-empted to the extent it actually conflicts with federal law, that is, when it is impossible to comply with both state and federal law, ... or where the state law stands as an obstacle to the accomplishment of the full purposes and objectives of Congress.” (Citations omitted.) Silkwood v. Kerr-McGee Corp., 464 U.S. 238, 248 (1984).
In considering a preemption argument, we note that preemption “is not favored, and State laws should be upheld unless a conflict with Federal law is clear.” Attorney Gen. v. Travelers
Commonwealth Electric does not contend that Congress has chosen to occupy the field of regulation of electricity sales. Indeed, it could not, as Congress clearly limited the Federal role to regulation of sales of electricity at wholesale, and left regulation of sales at retail to the States. Batavia v. FERC, 672 F.2d 64, 68 n.2 (D.C. Cir. 1982). See FPC v. Southern Cal. Edison Co., 376 U.S. 205, 215-216 (1964). Commonwealth Electric might have attempted to show an “actual conflict” in State and Federal regulation due to the physical impossibility of compliance with both State and Federal direction, Florida Lime & Avocado Growers, Inc. v. Paul, 373 U.S. 132, 142-143 (1963). It did not do so. Its preemption argument thus is based on the contention that the action of the DPU is an obstacle to the realization of the purposes and objectives of Congress in passing the Federal law. See Silkwood, supra.
The Federal law involved in this case is the Federal Power Act (FPA).
Commonwealth Electric argues that because the rates it must pay to its wholesale suppliers are fixed by FERC regulation, oversight by the DPU of the company’s costs based on those rates is an obstacle to the realization of the purposes behind the FPA. The company cites our decision in Eastern Edison Co. v. Department of Pub. Utils., 388 Mass. 292 (1983), for the proposition that the DPU has no jurisdiction over expenses incurred under an FERC-approved rate.
The company has construed too broadly both the scope of DPU’s oversight of rates and our holding in Eastern Edison.
The DPU offers a telling analogy to the rates it approves for retail sales to clarify the difference between rate-approval and inquiry into the prudence of incurring costs. “[W]hen the [DPU] sets retail rates, retail customers are faced with a rate that has been found to be just and reasonable, and they must pay that rate if they choose to buy electricity. . . . Decisions to purchase electricity, however, present different questions for each buyer. An industrial customer, for example, may decide that, given available alternatives, the purchase of electricity from the retail company is not reasonable or prudent from his business’ point of view. He may choose to use his own power generation equipment or another source of energy, such as oil, natural gas, or coal. He may decide to leave the geographic area altogether. Similarly, a retail electric company may decline to execute a wholesale supply contract upon the discovery of less expensive alternatives. If it chooses to ignore those alternatives and execute the wholesale contract, however, or if it incurs wholesale costs as a result of its imprudence . . . , it may be ruled imprudent notwithstanding the fact that the rate at which it purchased wholesale electricity was approved by FERC.”
The company has failed to sustain its burden of demonstrating by hard evidence how the action of the DPU will frustrate the full purposes and objectives of Congress in enacting the FPA. We conclude that the DPU was not preempted from the action it took in this case.
The company makes three additional related arguments: first, that the DPU is attacking collaterally (and therefore impermissibly) the FERC administrative decision to approve the company’s contracts with its wholesale suppliers; second, that the DPU action is prohibited by the commerce clause of the Constitution of the United States, art. I, § 8, cl. 3; and third, that the disallowance of recovery of incurred costs constitutes a confiscation of property without due process of law. We address each of these arguments briefly.
a. Collateral attack on an administrative decision. The company contends that the DPU — by refusing to allow the cost recovery — is attempting to circumvent the FERC administrative procedures for rate approval and the provisions for judicial review of that approval, see 16 U.S.C. § 8251 (1982), by collaterally attacking the approved rate. Cf. Tacoma v. Taxpayers of Tacoma, 357 U.S. 320, 339-341 (1958) (State could not raise in later proceeding between same parties issue that should have been raised in review of FPC [predecessor to FERC] decision); Commonwealth of Mass., Dep’t of Pub. Utils. v. United States, 729 F.2d 886, 886 (1st Cir. 1984) (State cannot order utility to seek FERC approval of State-proposed change in utility’s FERC-regulated rates and practices but must itself follow statutory procedure by filing complaint seeking FERC action). This argument would have merit if we were convinced that the issue is one over which FERC has jurisdiction. As stated above, we do not agree with that contention. Because FERC does not have jurisdiction over retail rates,
b. The commerce clause. The company suggests that the action of DPU violates the commerce clause of the Constitution of the United States, art. I, § 8, cl. 3. The company cites three factors demonstrating the unconstitutional burdens allegedly imposed by the DPU action: the benefit of an “added level of review of prudence of power supply costs” would not outweigh the burdens of uncertainty of the finality of FERC approval, possible disparate State-by-State treatment, and discouragement of long-term contracts.
“Although the criteria for determining the validity of state statutes affecting interstate commerce have been variously stated, the general rule that emerges can be phrased as follows: Where the statute regulates even-handedly to effectuate a legitimate local public interest, and its effects on interstate commerce are only incidental, it will be upheld unless the burden imposed on such commerce is clearly excessive in relation to the putative local benefits. Huron Cement Co. v. Detroit, 362 U.S. 440, 443 [I960]. If a legitimate local purpose is found, then the question becomes one of degree. And the extent of the burden that will be tolerated will of course depend on the nature of the local interest involved, and on whether it could be promoted as well with a lesser impact on interstate activities. Occasionally the Court has candidly undertaken a balancing approach in resolving these issues, Southern Pacific Co. v. Arizona, 325 U.S. 761 [1945], but more frequently it has spoken in terms of ‘direct’ and ‘indirect’ effects and burdens. See, e.g., Shafer v. Farmers Grain Co., [268 U.S. 189 (1925)].” Pike v. Bruce Church, Inc., 397 U.S. 137, 142 (1970). See Commonwealth v. B & W Transp. Inc., 388 Mass. 799, 808, appeal dismissed sub nom. Burke Distrib. Corp. v. Massachusetts, 464 U.S. 957 (1983); Grocery Mfrs. of Am., Inc. v. Department of Pub. Health, 379 Mass. 70, 80-81 (1979).
The company’s description of the benefit of State regulation — an “added level of review of prudence of power supply
c. Confiscation without due process. The company argues that it has been deprived of its property without due process of law.
In considering a due process claim, we examine first whether the claimant has been deprived of “property,” and, if so, we consider what process is due. Regents of State Colleges v. Roth, 408 U.S. 564, 570-571 (1972). The company’s brief does not show that it has been deprived of “property.” We do not proceed any further.
4. Summary. The Department of Public Utilities did not err in imputing to Commonwealth Electric Company the impru
So ordered.
Section 3.2 of the contract provides that the company has the right to consult with Boston Edison “concerning significant decisions with respect to construction or subsequent modifications of or additions to the Unit.”
Section 8.1 explains the parties’ intent in the event of extraordinary losses: “It is the intent of this Paragraph that Buyer [company] share with Seller [Boston Edison] any risk falling on Seller and arising pursuant to this Agreement to the extent of eleven percent (11%), and in such a manner that the risk of loss falling on Buyer is identical to such risk as would befall a complete owner of eleven percent (11%) of the Unit.”
Section 9.2 is an agreement by the company to reimburse Boston Edison for 11% of the unrecovered value of the power plant in the event of a shutdown before the investment has been recovered.
In Appendix C, covering payment obligations, the parties established their intent through § C-l.l: “It is the intent of the parties that during the term of the Agreement, Buyer shall reimburse Seller during the term of this Agreement as provided herein for eleven percent (11%) of all costs incurred by Seller by virtue of: (1) the construction of, or any modifications of additions to the Unit, and (2) the operation of or maintenance to the Unit.”
Appendix A, § A-3.1, detailing performance standards, sets forth the assumption of risk of nonperformance as follows: “The intent of this provision is that Buyer shall assume the risks of non-delivery of electricity hereunder caused by the hazards of the business to the same extent as if it were itself operating the Seller’s Unit for the purpose of supplying itself with electricity . . . .”
We do not conclude that actual or constructive ownership is a prerequisite to imputation of imprudence to a public utility. The analysis of the DPU includes the finding that the contract created the obligations and privileges of a joint owner. D.P.U. 1003-G-6, at 17. It is not the company’s similarity to an owner that is dispositive, however, but its nondelegable statutory obligations. Therefore, although we have in the past construed the term “owner” broadly to effectuate the legislative purpose, see Coyle v. Swanson, 345 Mass. 126 (1962), and found that its meaning is flexible, see Northgate Constr. Co. v. State Tax Comm’n, 377 Mass. 205, 208 (1979); Animal Rescue League v. Assessors of Bourne, 310 Mass. 330, 333 (1941), there is no need to analyze today what attributes a public utility must possess to be considered an “owner” by the DPU.
In support of its argument, the company cites decisions of administrative law judges of the Federal Energy Regulatory Commission (FERC), decisions of Federal courts that examined Environmental Protection Agency (EPA) regulations imposing vicarious liability, and general principles of tort and agency law.
The DPU distinguishes the FERC administrative decisions, arguing that the statutory authority of the FERC differs from that of the DPU. Though perhaps persuasive authority by analogy, decisions of a foreign administrative agency do not control Massachusetts law. Cf. Bonitz v. Travelers Ins. Co., 374 Mass. 327, 329-330 (1978); Dexter v. State Tax Comm’n, 350 Mass. 380, 382-383 (1966). Similarly, a decision based on EPA’s lack of statutory authority to impose vicarious liability does not control our consideration of the DPU’s imputation of imprudence. Cf. Commonwealth v. Masskow, 362 Mass. 662, 667 (1972); Commonwealth v. LePage, 352 Mass. 403, 409 (1967); Dexter v. State Tax Comm’n, supra.
In our view, it is the dissenting opinion of Wright, J., in the cited case Amoco Oil Co. v. EPA, 543 F.2d 270, 279-284 (D.C. Cir. 1976), that is
In return for its shelter from the uncertainties of the competitive market place, the public utility assumes the responsibility to provide adequate service at reasonable rates. See Fitchburg II, supra, and authorities cited therein. This duty is imposed by statute and, though its performance may be delegated, the duty may not.
The ratepayers should not bear the loss where the business judgment of the company’s directors is inconsistent with valid policies of the DPU. Fitchburg Gas & Elec. Light Co. v. Department of Pub. Utils., 375 Mass. 571, 578-579 (1978) (Fitchburg I).
General Laws c. 164, § 94G (a) (1984 ed.) provides, in pertinent part: “At least once a year, on dates set by the department, each electric company
There is no dispute as to the applicability of the statute.
Minnesota Power & Light Co. (MP&L) contracted with a pollution control company controlled by one of MP&L’s directors. When the equipment installed by the contractor did not perform properly, it was abandoned, and MP&L sought approval to pass the consequent loss on to its ratepayers. The approval was denied because “MP&L acted imprudently in the entire matter.” 11 F.E.R.C. par. 61,313, at 61,659 (1981), quoting decision of the administrative law judge. The Minnesota Power case does not appear to lend support to the company’s argument. As we read the decision of FERC, MP&L was found imprudent due to “self-dealing, the selection of a questionable pollution control process, and the failure either (or both) to secure a performance guarantee and to seek damages.” 11 F.E.R.C. par. 61,313, at 61,659 (1981).
We are not bound, of course, in our interpretation of Massachusetts law, by decisions of other tribunals, except by decisions of the Supreme Court of the United States relying on the Federal Constitution. Commonwealth v. Montanez, 388 Mass. 603, 604 (1983).
Act of June 10, 1920, c. 285, as amended by Title 11 of the Public Utility Act of 1935, 49 Stat. 803, and subsequent amendments (codified at 16 U.S.C. §§ 791a-828c [1982]).
Eastern Edison Company (Eastern Edison) purchased power from its wholesale supplier, also its wholly-owned subsidiary, Montaup Electric Company (Montaup). Montaup increased its wholesale rate in order to recoup its investment in the abandoned Pilgrim Nuclear Unit No. 2 project. The wholesale rate was regulated exclusively by FERC. Eastern Edison,
The company urges that the distinction between review of rates of sale and prudence of purchase is not valid. The cited case of Consolidated Edison Co. v. Public Serv. Comm’n, 63 N.Y.2d 424 (1984), is inapposite because the State law at issue there purported to fix rates at which utilities were compelled to purchase energy produced by alternate energy producers. It is not disputed here that the approval of wholesale rates is within the Federal domain.
The company’s brief does not cite the constitutional provisions on which it relies for this argument. The due process argument is a section of the company’s argument that the DPU action is a Federal constitutional violation, however, and we presume that the company bases its claim on the Fourteenth Amendment to the United States Constitution. We express no opinion on any due process claims which might be based on the Constitution of the Commonwealth.
Even if we were to conclude that the company’s opportunity to recover the costs of providing service is “property,” we would have difficulty in finding that the company was due any process it did not receive. The company was permitted to participate in an extensive formal hearing to establish the facts upon which the DPU’s decision was based, and presented its arguments before the decision maker. The company seems to be arguing under due process guise for a different substantive standard of decision. Their due process argument is in essence a restatement of their complaint that imprudence was improperly imputed to them. We have considered that argument above, and we have rejected it.
Reference
- Full Case Name
- Commonwealth Electric Company vs. Department of Public Utilities
- Cited By
- 14 cases
- Status
- Published