State Highway Admin v. Brawner Builders

Court of Special Appeals of Maryland
State Highway Admin v. Brawner Builders, 242 A.3d 1188 (2020)
248 Md. App. 646
Wilner

State Highway Admin v. Brawner Builders

Opinion

Md. State Highway Administration v. Brawner, No. 1643, September Term 2019, Argument Date: 11/6/20

Procurement Law

A subcontractor is entitled to make a contract claim against a procurement agency only if there is a direct contract between the claimant and that agency. The subcontractor had a contract with a contractor to provide materials on a state highway project. Although the state agency had approved the materials the subcontractor would use in state highway noise barrier wall, that did not suffice to create a contract between the subcontractor and the agency. As such, the subcontractor did not have standing to present a claim against the agency. The mere approval of a company’s product as being acceptable for a project does not make that company a procurement contractor with standing to make a claim.

Timeliness

In construction contracts, a contractor must file written notice of a claim against a procurement agency within 30 days after the basis for the claim is known or should have been known and the support for the claim itself must be filed within 90 days after submission of the notice of the claim. The subcontractor alleged the contractor was obligated to pass through its complaints to the procurement agency. The court affirmed the decisions of the Maryland State Board of Contract Appeals to dismiss the claim as untimely because the contractor failed to file a written pass-through notice with the 30 days. Circuit Court for Baltimore City Case No. 24-C-19003208 REPORTED IN THE COURT OF SPECIAL APPEALS

OF MARYLAND

No. 1643

September Term, 2019

MARYLAND STATE HIGHWAY ADMINISTRATION

v.

BRAWNER BUIILDERS, INC.

Beachley, Gould, Wilner, Alan M. (Senior Judge, Specially Assigned),

JJ.

Opinion by Wilner, J.

Filed: December 18, 2020

Pursuant to Maryland Uniform Electronic Legal Materials Act (§§ 10-1601 et seq. of the State Government Article) this document is authentic.

Suzanne Johnson 2020-12-18 15:41-05:00

Suzanne C. Johnson, Clerk This case arises under the State procurement law. The State Highway

Administration (SHA) rejected claims filed by appellees Brawner Builders, Inc.

(Brawner) and Faddis Concrete Products, Inc. (Faddis) on the grounds that (1) Faddis had

no procurement contract with SHA and therefore had no standing to file a procurement

claim, and (2) the claims filed by Brawner and Faddis were untimely. In an appeal by

appellees, the Maryland State Board of Contract Appeals (MSBCA) agreed with SHA on

both of those issues and entered a Summary Decision affirming SHA’s rejection of the

claims.

In a judicial review action, however, the Circuit Court for Baltimore City had a

different view. It concluded, (1) as a matter of law, that Faddis did have a procurement

contract with SHA and was entitled to file a claim, and (2) that there was a genuine

dispute of material fact as to whether the claims were timely. It therefore vacated the

MSBCA summary decision and remanded the case for a hearing on the merits of the

claims. Before us is SHA’s appeal from that judgment. We shall reverse the Circuit

Court judgment and remand with instructions to affirm the MSBCA order.

BACKGROUND

The project that spawned this dispute was the construction of a 0.38-mile noise

barrier wall along a stretch of I-95 in Howard County. Noise abatement measures along

State highways are required both for Federal funding of highway construction projects

and by State law. As a result, in August 2011, SHA issued a Highway Noise Policy that set forth substantive requirements for precast concrete products and a procedure for SHA

certification of plants producing those products. Pre-approval of a plant by SHA was

required in order for a manufacturer to be eligible to bid on SHA highway projects.

Certification was good for one year, subject to renewal following an annual inspection of

the plant and subject also to the manufacturer continuing to operate the plant in

conformance with the SHA specifications through a Quality Control Plan. SHA charged

a cost reimbursement fee for the cost of inspection and certification. Pursuant to that

process, SHA, at some point, certified Faddis’s plant in Downingtown, Pennsylvania as

“Qualified for Sourcing on State Projects” and included that plant on its list of pre-

approved manufacturers of noise barrier systems.

The prime contract for the construction of the 0.38-mile section (Contract No.

H02485126) was entered into with Brawner on November 19, 2012. That contract, for

whatever reason, was not placed in evidence in the court proceeding and therefore is not

included in the record. In February 2013, Brawner and Faddis entered into a subcontract,

evidenced by a purchase order, for Faddis to furnish 40,910 noise wall panels and three

access doors. All materials and work were required to be in conformance with the

conditions and specifications pertaining to the prime contract. The purchase order was

contingent on SHA approval of Faddis as a supplier and made clear that Brawner was

obligated to pay for all products ordered, produced, and shipped regardless of any

payment to Brawner by SHA. There were to be no set-offs. Brawner reserved the right

2 to cancel the subcontract if Faddis was in breach of any of its obligations, including the

performance or delivery of non-conforming work or materials.

In September 2013, Faddis furnished SHA with a sample panel which, on

September 27, SHA approved for use on the project. Based on that approval, Faddis

began manufacturing the panels for Brawner to erect pursuant to its (Brawner’s) contract

with SHA.

SHA employed an outside agency to furnish inspectors to assure compliance with

the SHA standards, one of whom was Nick Patras. Mr. Patras was stationed at Faddis’s

Downingtown plant for the purpose of inspecting panels destined for the SHA project.

No panels were to be shipped without his approval. It appears, at least from SHA’s

perspective, that Mr. Patras was not doing his job properly, and he eventually was

dismissed. In March 2014, SHA’s Office of Materials and Technology concluded that

panels manufactured by Faddis after November 27, 2013 contained aggregate from an

unapproved source, which was a violation of the noise barrier standards, and, as a result,

the required strength of the panels could not be determined. Investigations led the

Assistant Division Chief for Field Operations (Christopher Gale) to conclude, among

other things, that, throughout the production of the panels, Faddis had (1) failed to

provide adequate documentation of the source material for the exposed aggregate panels,

(2) altered cylinder test data to reflect values higher than what the material actually

achieved, (3) used a mix design that did not meet SHA specifications, and (4) was

extremely uncooperative about making changes to meet specifications.

3 On May 2, 2014, SHA’s District Engineer, David Coyne, informed Brawner of

those conclusions and requested a response as to how Brawner intended to remedy the

problem. Faddis was not copied on that letter. Brawner’s project manager responded six

days later, on May 8, that the problem was not Brawner’s to remedy, that it involved

instead “a breakdown in the fabrication, inspection, and acceptance procedure at an SHA

pre-approved concrete precast facility.” The letter requested a temporary partial

shutdown of the project and advised that Brawner was reserving its rights to extended

contract performance, including monetary compensation. Brawner added that “we are

not requesting either at this time but reserve our right to do so should it become

necessary.”

On May 9, in a letter to Kevin Iddings, Faddis’s Operations Manager, Mr. Gale set

forth in detail the concerns of SHA, which included failure to provide adequate

documentation regarding the exposed aggregate material used in the panels, mixing

concrete “of inconsistent and questionable quality,” failure to comply with Faddis’s own

Quality Control Plan, and using a coarse aggregate from an unapproved source that was

not in conformance with Maryland Department of Transportation standards. The letter

gave notice that further purchases were suspended for 180 days during which Faddis

would be required to take certain specified remedial action. On May 21, Mr. Iddings

responded to the points made by Mr. Gale, asserting that, although Faddis “disagree[d]

with many of the representations made in the SHA letter,” it remained committed to

resolving the outstanding issues to SHA satisfaction.

4 Exacerbating the situation, on June 9, 2014, SHA’s Chief of Concrete Technology

Division, Michelle Armiger, sent e-mails to officials at the Virginia and Pennsylvania

Departments of Transportation advising them of the problems SHA had been having with

Faddis and asking whether they had experienced similar issues. Ten days later, the

Director of SHA’s Office of Materials Technology sent an e-mail to those agencies

clarifying that the issues mentioned by Ms. Armiger were in dispute, that there was an

administrative process in which SHA and Faddis were engaged, and there had been no

final determination by SHA.

The next event in this drama consisted of three letters from Faddis on June 23,

2014. One was to SHA’s District Engineer, David Coyne, which stated that it

supplemented “notices of claims previously submitted by Brawner,” and advised that

SHA’s action had “impacted Faddis as it specifically relates to the contract between

Faddis and Brawner” (emphasis added) and had resulted in losses for which “Faddis

reserves the right to recover damages for all costs including those related to the idling of

Faddis’s plant and equipment and interferences with other contracts and Pennsylvania’s

and Virginia’s Departments of Transportation.” Faddis insisted that SHA “take

immediate steps to abate the harm to Faddis and address these claims and impacts due to

its directions and actions.”

The second letter was to Brawner, asking that it provide Faddis with “the notice of

claim letter” sent to SHA related to the contract between SHA and Brawner and that it

furnish SHA with a copy of “this letter which serves to supplement the prior notice and

5 advise the SHA” of continuing damages. The letter did not identify the alleged notice of

claim letter to which it referred. The third letter was from Faddis’s attorney, Paul Logan,

to Scott Morrell, the Assistant Attorney General who represented SHA. In that letter, Mr.

Logan took issue with the conclusions reached by SHA as specified in Mr. Coyne’s May

2 letter to Brawner, contended that SHA had acted precipitously and without legal or

factual justification, and insisted that (1) all suspensions be lifted, (2) Faddis’s panels be

accepted, and (3) the project be deemed complete with no liquidated damages or

penalties.

Mr. Morrell responded the next day through an e-mail advising Mr. Logan that

any procurement claim against SHA had to be filed with the SHA procurement officer by

Brawner – the prime contractor with which SHA had a contractual relationship – and that

any tort claim had to be filed in accordance with the Maryland Tort Claims Act.

The next event occurred on July 16, 2015, when Faddis filed a civil action against

Brawner in the U.S. District Court for the Eastern District of Pennsylvania. That action

later was transferred to the U.S. District Court for the District of Maryland. The

Complaint was based on Brawner’s failure to “pass through” Faddis’s claim to SHA,

thereby precluding Faddis’s claim from being considered by SHA. In that regard, the

Complaint alleged that, at all relevant times, “Faddis had a direct contract with Brawner,

but no direct contract with SHA” that, in accordance with COMAR regulations, “where

claims are being pursued on behalf of suppliers and subcontractors, the claim must be

initiated by the prime contractor” and that “Brawner was obligated to pass through all of

6 Faddis’s claims against the SHA and not impede the rights of Faddis to recover the

damages it sustained.” Although Faddis alleged that it was entitled to damages due to

SHA’s wrongful interference with Faddis’s status as an approved and prequalified

supplier, the action was solely against Brawner; SHA was not a party to the action.

On August 11, 2015, counsel for Brawner sent a copy of the Federal Complaint to

SHA’s District Engineer who, on August 21, acknowledged receipt and accepted it as a

Notice of Claim by Brawner. The Federal case was settled and dismissed on December 7,

2017. The record before us does not reveal the terms of the settlement. No action was

taken by SHA on the claim. On May 31, 2018, counsel for Faddis, on behalf of both

Faddis and Brawner, requested that SHA issue a written decision on the pending claims.

When SHA declined to do so, Faddis and Brawner filed an appeal with MSBCA on

September 6, 2018.1

Through a Motion for Summary Disposition, SHA argued that:

(1) Except for “contract claims” permitted under the State Finance and Procurement Article (SFP) and implementing regulations in COMAR, SHA enjoys the State’s sovereign immunity;

1 As SHA explains in its brief (p. 8, notes 1 and 2), where a claim satisfying the Code and COMAR requirements for a procurement claim is filed, the procurement agency is required to issue a written decision within 180 days after receipt of the claim. If it fails to do so, the failure may be “deemed” a denial that may be appealed to MSBCA. See SFP § 15-219(g)(2). At issue in such an appeal, if raised, is whether the claim was a cognizable one that was timely filed. 7 (2) Only a person having a contract with a procurement agency may file a contract claim, and Faddis, as a mere subcontractor with Brawner, does not have that status; (3) Even if it did have that status, having settled its Federal suit against Brawner, Faddis has received a recovery for any contract damages due to SHA’s conduct, and any damages sought as a result of having contacted the Pennsylvania and Virginia departments would not be in the nature of a contract claim; and (4) Brawner was a procurement contractor that could have filed a claim on behalf of Faddis but failed to do so timely.

Faddis and Brawner acknowledged that only a procurement contractor may file a

procurement claim, but, inconsistently with Faddis’s position in the Federal action, they

claimed that Faddis was a procurement contractor entitled to file a claim directly and that

it did so. They based that argument on Faddis’s pre-certification by SHA and the

agency’s approval of Faddis’s panels for use in SHA construction projects, which meant

that it was, in effect, agreeing to purchase those panels. They asserted that Brawner had

given notice of Faddis’s claim in the May 8, 2014 letter and that the forwarding of the

Complaint in the Federal action on August 11, 2015 constituted the claim itself.

MSBCA rejected that argument. It noted that, under COMAR 21.10.05.06D(2), it

was authorized to grant a proposed summary decision – the administrative equivalent of a

summary judgment entered by a court – if it finds, after resolving all inferences in favor

of the party against whom the motion is made, that there is no genuine issue of material

fact and that the moving party is entitled to prevail as a matter of law.

8 As noted, the Board cited two grounds for its decision: first, that, as a

subcontractor, Faddis had no standing to make a direct claim against SHA; and second,

that Brawner’s pass-through claim on Faddis’s behalf was untimely. With respect to the

first issue, citing its earlier decision in Appeal of Jorge Company, Inc. MSBCA No. 1339

(1982), it concluded:

“Faddis does not have a written ‘procurement contract’ with Respondent. Accordingly, Faddis does not have standing to file a contract claim directly with Respondent. Any contract claim Faddis had concerning the Project had to be filed as a pass-through claim by Brawner on behalf of Faddis.”

With respect to timeliness, the Board found that Faddis had actual knowledge of a

claim at least by June 23, 2014, as evidenced by its letter to Brawner on that date, in

which it expressly asked Brawner to forward the letter to SHA to supplement what it

believed was a prior notice filed by Brawner. As noted, at the time, Faddis accepted the

premise that any claim by it had to be passed through by Brawner. That required that

notice to SHA of such a claim be presented by July 24, 2014 (30 days later). The Board

rejected Faddis’s argument that Brawner’s letter of May 8, 2014, in response to SHA’s

letter of May 2, could constitute the actual filing of a claim, noting that the letter merely

reserved Brawner’s right to file a claim some time in the future. The Board found that

the pass-through claim on behalf of Faddis was not filed until August 11, 2015, long past

the deadline.

In the judicial review action, the Circuit Court correctly identified the principal

issue as being whether Faddis had a procurement contract with SHA. The court regarded

9 that as an issue of law subject to de novo review. It turned to the definitions of

“procurement” and “procurement contract” in SFP §§ 11-101(n) and (o).2 In relevant

part, “procurement” means the process of buying or otherwise obtaining supplies,

services, construction, construction related services and includes “the solicitation and

award of procurement contracts and all phases of procurement contract administration.”

With exceptions not relevant here, “procurement contract” means “an agreement in any

form entered into by a State Executive Branch agency authorized by law to enter into a

procurement contract] for procurement.”

The court construed the relationship between Faddis and SHA as falling within the

ambit of those definitions. It arrived at that conclusion not just on Faddis’s supply of

panels for this particular project but on the premise that it had been approved as “a

qualified source of its product for a multitude of purposes, not just the project that is

before the board in this dispute.” That, the court said, constitutes “an independent

procurement contract” founded on its “entitle[ment] to be possibly selected for use in a

contract with the State through another contractor.” On that premise, the court held that

the Board erred as a matter of law in its determination that Faddis was not a procurement

contractor entitled to file a claim directly with SHA.

2 At the time of those events, those definitions were codified as subsections (m) and (n) of § 11-101. Effective October 1, 2019, they were re-codified respectively and without textual change as subsections (n) and (o) due to a new definition in subsection (e) that required the relettering of subsequent definitions. We shall use the current designations. 10 Turning then to the issue of timeliness, the court concluded that the Board

inappropriately weighed evidence on whether there was timely notice of Faddis’s claim.

In reaching that conclusion, the court relied on Engineering Mgt. v. State Highway,

375 Md. 211

(2003) for the proposition that “there should be a full hearing on the merits,

where the issue of untimely notice is a defense.” On those twin grounds, the court

“reversed and vacated” the MSBCA summary decision and remanded the case for a

hearing on the merits.

DISCUSSION

Standard of Review

The standard of review by an appellate court of the decision of an administrative

agency, such as MSBCA, was succinctly stated in Comptroller v. Science Applications,

405 Md. 185, 193

(2008), and confirmed more recently in Motor Vehicle Admin. v.

Pollard,

466 Md. 531, 537

(2019) and Burr v. Retirement & Pension System,

217 Md. App. 196, 203

(2014). We review the agency’s decision directly, not the decision of the

Circuit Court. We will affirm the agency decision if it is supported by substantial

evidence appearing in the record and is not erroneous as a matter of law, and, because

agency decisions are presumed prima facie correct, we review the evidence in a light

most favorable to the agency. Although no deference is required to be given to the

agency’s conclusions of law, courts normally give some deference to an agency’s

interpretations of the laws it is authorized to administer. Nat’l Waste Mgr’s v. Forks of 11 the Patuxent,

453 Md. 423, 441

(2017); Kim v. Board of Physicians,

423 Md. 523, 535

(2011); LVNV Funding v. Finch,

463 Md. 586, 606, n.10

(2019).

If the agency decision under review was in the form of a summary disposition, we

must determine whether that disposition was legally correct, i.e., whether there is no

genuine dispute of material fact and the moving party was entitled to that disposition as a

matter of law.

Burr, supra,217 Md. App. at 203

.

Faddis’s Status As A Procurement Contractor

There is a sharp disagreement between the parties regarding Faddis’s status as a

procurement contractor. SHA’s position is that, to be entitled to make a contract claim

against a procurement agency, the claim must arise from a direct contract between the

claimant and a procurement agency and that Faddis had no such contract.

Until late in the game, Faddis accepted that proposition. Its Federal lawsuit

against Brawner was based entirely on that proposition. As noted, Faddis alleged in its

Complaint that the COMAR regulations require that “in instances where claims are being

pursued on behalf of suppliers and subcontractors, the claim must be initiated by the

prime contractor” and that Brawner’s refusal to make such a claim on Faddis’s behalf

precluded Faddis from recovering its losses. At least inferentially, if not directly, that is a

concession that it had no standing to present its claim directly to SHA or MSBCA. Faddis

has clearly abandoned that position. Its current claim is that, by virtue of SHA’s pre-

12 approval and certification of its product, it was a direct procurement contractor and had

the right as such to make a contract claim directly on its own behalf. That takes us,

ultimately to statutory definitions.

As a preface, SHA points out that, until 1976, the State possessed full common

law sovereign immunity from contract actions against the State. See Katz v. Washington

Sub. San. Comm’n,

284 Md. 503, 507

(1979) (“[T]he doctrine of sovereign immunity

from suit, rooted in the ancient common law, is firmly embedded in the law of

Maryland” and “is applicable not only to the State itself, but also to its agencies and

instrumentalities, unless the General Assembly has waived the immunity either directly

or by necessary implication.”)

That immunity was partially, and somewhat indirectly, waived by statute in 1976.

As now codified in Md. Code, § 12-201(a) of the State Gov’t. Article, unless otherwise

expressly provided by State law, it precludes the State and its officers and units from

raising the defense of sovereign immunity “in a contract action, in a court of the State,

based on a written contract that an official or employee executed for the State or 1 of its

units while the official or employee was acting within the scope of the authority of the

official or employee.” See also Md. Code, §5-522 of the Courts and Judicial Proceedings

Article.3 Waivers of immunity, which are in derogation of common law, are strictly

3 It is interesting to note that the waiver of sovereign immunity from tort actions is direct. Section 12-104 of the State Government Article provides that, with certain exceptions, “the immunity of the State and of its units is waived as to a tort action, in a court of the State.” That is a direct waiver by the General Assembly. As we observed, § 12-201 uses different language. It prohibits the State and its units from “rais[ing] the defense of 13 construed in favor of the State. Central Collection v. DLD,

112 Md. App. 502, 513

(1996); Dept. of Public Safety v. ARA,

107 Md. App. 445, 457

, aff’d. ARA Health v. Dept.

of Public Safety,

344 Md. 85

(1996).

It is necessarily implicit from applying a narrow construction to the waiver of

immunity that the Legislature may impose conditions and limitations, both substantive

and procedural, on such a waiver, and it has done so with respect to the waiver of

immunity in both tort and contract actions. In particular, it has enacted a comprehensive

set of laws governing the selection of procurement contractors, what may or may not be

included in procurement contracts, the monitoring and enforcement of such contracts, and

the processing of contract claims, spread among eight titles of SFP. This case implicates

several of those statutes, principally those in SFP Titles 11 and 15 dealing with the

structure and procedure for the resolution of procurement disputes.

Both the structure and the procedure hinge on the definition of three terms that

shape the universe we are dealing with – procurement, procurement contract, and contract

claim. SFP § 11-101(n) defines “procurement” as including the process of “buying or

otherwise obtaining supplies, services, construction [and] construction related services”

as well as “the solicitation and award of procurement contracts and all phases of

sovereign immunity in a contract action, in a court of the State.” It is a distinction without a difference, however. In ARA Health v. Dept. of Public Safety,

344 Md. 85, 92

(1996), the Court held that the Legislature may “waive[ ] immunity either directly or by necessary implication, in a manner that would render the defense of immunity unavailable,” and treated § 12-201 as a waiver. See also Katz v. Washington Sub. San. Comm’n, supra,

284 Md. at 507, n.2

. 14 procurement contract administration.” With exceptions not relevant here, SFP § 11-

101(o) defines “procurement contract” to mean “an agreement in any form entered into

by a unit for procurement.” Those two definitions obviously need to be read together.

The third critical term is “contract claim,” which is defined in SFP § 15-215 (a) as “a

claim that relates to a procurement contract” and includes “a claim about the

performance, breach, modification, or termination of the procurement contract.”

The structure and procedure begin with the procurement officer, who is the

individual authorized by the agency (unit) to enter into, administer, and make

determinations and findings with respect to a “procurement contract.” SFP § 11-101(o).

With respect to construction projects, this is a two-step process. First, the

contractor must file a written notice of a claim with the procurement officer within 30

days after the basis for the claim is known or should have been known. SFP § 15-219(a).

Within 90 days after submitting that notice, the contractor must submit “a written

explanation that states the amount of the contract claim, the facts on which the contract

claim is based, and all relevant data and correspondence that may substantiate the

contract claim.” SFP § 15-219 (b). See also COMAR 21.10.04.02. The agency then has

a fixed time, depending on the amount of the claim, to investigate and render a decision

on the claim. SFP § 1-219 (d)(2). With an exception not relevant here, a contractor may

appeal an unfavorable decision to MSBCA within 30 days after receipt of the decision or

a deemed denial. SFP § 15-220.

15 Both parties appear to agree that only a “contractor” – a person who has been

awarded a procurement contract – may submit a contract claim and that Brawner

qualifies as such a person. They also appear to agree, and, as we shall note infra,

MSBCA has implicitly recognized as well, that a prime contractor may file, as a pass-

through, a claim by a subcontractor, although we are unable to find any statute or

COMAR regulation that even mentions, must less approves, such a procedure and none

has been called to our attention by the parties.

As we have observed, however, Faddis no longer relies on such a procedure but

insists that it was a procurement contractor in its own right. Its position arises from

SHA’s certification of the Downingtown plant and its acceptance of the sample panel

supplied by Faddis in September 2013. Those events, it maintains, constitute “an

agreement in any form entered into by a unit for procurement,” which thus constituted a

“procurement contract” that was entered into by a procurement agency for the acquisition

of construction or construction-related services. The Circuit Court stressed that those

events made Faddis a contractor not just for this particular SHA project but for all SHA

noise control projects.

SHA, of course, takes a very different view, insisting that “procurement contract”

means a contract entered into directly between the procurement unit and the contractor

for a particular project or set of projects. Mere approval of a company’s product as being

acceptable for some future project or even a project for which the unit has already

selected and contracted with another contractor does not make that company a

16 procurement contractor with standing to make a claim. In the proceeding before the

MSBCA, Faddis admitted that its compensation for supplying the panels would come

from Brawner, not SHA. Its purchase order subcontract confirms that point. By

interlineation, it precludes “set-offs” and specifies that “Buyer [Brawner] shall pay seller

[Faddis] for all products ordered, produced & shipped regardless of payment to buyer by

owner [SHA].”

Neither side cites a case that controls this issue, and we have found none. There

are, however, two prior decisions of MSBCA that are relevant and that were relied on by

MSBCA in this case. Appeal of Jorge Company, Inc. involved a sub-subcontractor

whose claim was rejected by the Mass Transit Administration and who appealed to

MSBCA. The Board dismissed the appeal for lack of jurisdiction, holding that, as the

statute defined a contractor as “any person having a contract with a State agency” and as

Jorge did not have such a contract, it was not entitled to appeal to the Board. The Board

observed that, ordinarily, it could dismiss the appeal “without prejudice to the right of the

subcontractor to refile its appeal in the name of the prime contractor,” but declined to do

so because the claim also was untimely.

That is the case in which MSBCA, at least implicitly, recognized the pass-through

procedure for presenting claims of subcontractors. The rulings in Jorge were confirmed

by MSBCA in Appeal of Davidsonville Diversified Services, MSBCA 1339 (1988).

There, too, a subcontractor was on a SHA project. When its subcontract was terminated

by the prime contractor, it filed an appeal to MSBCA based on SHA’s approval of the

17 termination, without ever filing a claim with SHA. It argued that, by reason of the

extensive day-to-day control over its work by SHA’s field engineer, an implied contract

had been created between it and SHA. Citing Jorge, the Board reaffirmed the conclusion

that a subcontractor that does not have a contract with a State agency cannot maintain the

appeal in its own name. It concluded as well that it had no jurisdiction over implied

contracts, but only written ones with a procurement agency. Citing yet another of its

decisions, in Boland Trane Associates, Inc., MSBCA 1084 (1985), it stated:

“Since the Legislature sets the terms under which it waives sovereign immunity, it may prescribe what type of contracts with the State may properly be within the ambit of this Board’s jurisdiction and what contracts are to be excluded.”

Pre-approval of eligibility to provide materials, work, or services does not, in our

view, constitute a contract to do so. The State procurement law and regulations provide

for the pre-approval or certification of various classes of would-be contractors or their

products.4 Pre-approval of an entity’s status or products – of eligibility to act as a

supplier or even a preferred supplier – does not make the entity a procurement contractor

if it is not, in fact, selected by a procurement agency, through a written contract, to

provide materials, work, or services to the agency. Many of those entities may end up as

4 See, for example, (1) SFP Title 14, Subtitle 2 and COMAR 21.11.01 providing for the certification of small businesses eligible for preference under the Small Business Preference Program; (2) SFP Title 14, Subtitle 3 and COMAR 21.11.03. providing for the certification of minority businesses eligible for participation in Minority Business Enterprise Program; (3) SFP 14-415, providing a preference for certified recyclers. 18 subcontractors or sub-subcontractors that have no direct contract with the procurement

agency.

We note as well COMAR 21.10.04.02D, dealing with contract claims and

disputes, that requires each procurement contract to provide notice of the time

requirements for filing claims, acceptable methods of filing a claim, and limitations on

filing claims electronically, none of which were part of the pre-approval or certification

of Faddis’s Downingtown plant or acceptance of the test panel.

From a fair and reasonable construction of the statutes and COMAR regulations,

we believe that MSBCA was correct in its conclusion, as a matter of law, that Faddis had

no procurement contract with SHA and, as a result, was not a procurement contractor

entitled to file an independent claim with SHA or to appeal to MSBCA. Faddis’s own

assertion of that proposition in its Federal complaint against Brawner powerfully supports

that conclusion, although we do not rely on it because we do not need to do so.

Timeliness

That leaves the question of whether a timely claim was made on Faddis’s behalf

by Brawner. We start with the requirement in SFP § 15-219 (a) that, with respect to

construction contracts, a contractor must file written notice of a claim within 30 days

after the basis for the claim is known or should have been known and the requirement in

§ 15-219 (b) that support for the claim itself must be filed within 90 days after

submission of the notice of the claim.

19 As noted, the court believed that there was disputed evidence on that issue that

required a full evidentiary hearing. SHA acknowledged Brawner’s forwarding of

Faddis’s Federal Complaint on August 11, 2015 as a Notice of Claim “regarding the

matter of Faddis Concrete, Inc. v. Brawner Builders, Inc.” The question is whether there

was evidence of any earlier notice of claim by Brawner on behalf of Faddis.

Correspondence between Faddis and SHA that was not part of any submission by

Brawner doesn’t count.

Three documents are dispositive. The first is Faddis’s June 23, 2014 letter to

Brawner reciting, at least in general terms, Faddis’s damages from the actions of SHA

and requesting that Brawner forward that letter to SHA and advise SHA of the damages

suffered by Faddis. That shows the latest date when Faddis and Brawner both were

aware that Faddis had a claim that needed to be presented on its behalf by Brawner.

The second document is Brawner’s May 8, 2014 letter to SHA, responding to Mr.

Coyne’s May 2 letter informing Brawner of SHA’s conclusions regarding the

unacceptability of Faddis’s panels. In that May 8 letter, Brawner essentially said that

“it’s not our problem.” The letter acknowledged SHA’s position, advised that Brawner

and Faddis both had been harmed by SHA’s conduct, and asserted that “we reserve our

rights” to extended contract duration and monetary compensation “but are not requesting

either at this time but reserve our right to do so should it become necessary.” Though

recognizing that, in considering a summary disposition, the Board needed to resolve all

inferences in favor of Brawner and Faddis, the Board nonetheless concluded that

20 “nothing in [that] language could be construed to be a proper notice of Faddis’ claim by

Brawner to [SHA].” We agree. It is a direct negation of any attempt to make a claim at

that point.

The third document is Faddis’s Federal Court complaint, filed July 16, 2015,

which fully supports that conclusion by the Board. In that Complaint, Faddis alleged that

Brawner was obligated to pass through all of Faddis’s claims against SHA and not

impede Faddis’s right of recovery (¶ 33), that Faddis had provided multiple timely and

proper notices to Brawner with requests that they be presented to SHA (¶¶ 37, 38), and

that “for reasons still undisclosed to Faddis, upon information and belief, Brawner

refused to act, as of the date of this Complaint, continues to refuse to facilitate the pursuit

of any claims by or on behalf of Faddis against SHA.” (¶ 43). There can be no clearer

admission that, as of that date, no written pass-through notice of claim had been filed by

Brawner on behalf of Faddis.

It is evident, then, that Brawner failed to file the notice of claim within 30 days

after the basis for Faddis’s claim was known to Brawner, in violation of SFP 15-219 (a)

and COMAR 21.10.04.02B. The COMAR regulation states explicitly that “[a] notice of

claim, that is not filed within the time prescribed in Regulation .02 of this chapter shall be

dismissed.” (Emphasis added). There is no exception to that statement and no ambiguity

as to its meaning. Following its earlier decision in Appeal of David A. Bramble, Inc.,

MSBCA 2823 (2013), the Board held that provision mandatory. That is a reasonable

construction of the COMAR regulation.

21 We therefore conclude that there was no flaw in the Board’s findings of fact or

conclusions of law or in the entry of a summary decision. The relevant documents speak

for themselves. We acknowledge the problem that subcontractors may face when they

have a legitimate claim and the prime contractor, whether negligently or deliberately,

fails or refuses to file a timely claim on the subcontractor’s behalf. On the other hand, as

SHA acknowledged in oral argument, there may be circumstances where the prime

contractor could have a conflict of interest in filing a pass-through claim. There may be

ways to deal with that problem without allowing persons having no direct contractual

relationship with a procurement agency to file claims against that agency, but any

solution must come from the Executive or the Legislative Branch.

JUDGMENT REVERSED; CASE REMANDED TO CIRCUIT COURT FOR BALTIMORE CITY FOR ENTRY OF JUDGMENT AFFIRMING DECISION OF MARYLAND STATE BOARD OF CONTRACT APPEALS; APPELLEE TO PAY THE COSTS.

22

Reference

Cited By
4 cases
Status
Published