McGown v. Inhabitants of Washington
Opinion of the Court
This was an action against the defendant town to recover for injuries alleged to have been received by the plaintiff by
There are two grounds upon which the plaintiff contends the defendant had the notice required. First, she claims that, having had notice of the defective condition of this causeway some months before, and having authorized and directed one Hubbard to repair it, the road commissioner, William W. Light, in person, in June, about two months before the accident and after Hubbard had repaired it, inspected the causeway as repaired, had an opportunity to discover the conditions constituting the alleged defect, and therefore had notice of the actual condition of the causeway which the plaintiff claims was a defect. It is the opinion of the court that the evidence in the case might warrant a jury in finding all these facts in favor of the plaintiff. Therefore inasmuch as it is not for the road commissioner to determine whether the actual condition which he saw or ought to have seen was a defect, but a question of fact for the jury, we feel clear that the case upon the evidence should be submitted to the jury to determine whether the road commissioner in June when he inspected the causeway was charged with notice of the conditions which caused the plaintiff’s injury, and whether those conditions constituted a defect. If upon this question the jury’s finding should be in the affirmative, the plaintiff would not be barred for want of notice.
Second, the plaintiff contends that the road commissioner having personally received notice of a defect in the culvert in question and having authorized George Hubbard "to fix that causeway,” George Hubbard was appointed "to act as a substitute for” the commissioner in making the repairs, under R. S., ch. 23, sec. 76, as amended in 1903, ch. 108. Section 76, with the amendment in brackets
Not so, however, in the case at bar. The case starts with an alleged defect. The road commissioner had notice of it. Under the statute he was charged in the premises with an obligation to the public. It was his positive and imperative duty after twenty-four hour’s notice to know that the defect was repaired. The statute must be regarded as mandatory upon the strict performance of this duty, for upon its full and complete execution may depend the life or limb of a lawful traveler. In case of the defect in question the road commissioner did not direct Hubbard to construct anything new, as was done in the Waterville and Rockland cases, but to repair what had become unsafe and dangerous. He did not send Hubbard to build a new piece of work which he might assume would
There is another phase of the case which requires that it should be submitted to the jury. Some eight or nine months before the date of the accident complained of, the commissioner admits he received notice of an alleged defect in the identical causeway upon which the plaintiff was injured. It also appears that Hubbard was directed to repair it. It is claimed that what he did, whatever it was, failed to accomplish the purpose; that the identical defect»of which the commissioner was notified continued unabated ; and was the one upon which the plaintiff was injured. If the jury should find affirmatively upon these questions then the notice to the commissioner would continue to be valid until it was shown that the defect was so repaired that the causeway was safe and convenient.
Exceptions sustained.