Burrows v. bidigare/bublys, Inc
Burrows v. bidigare/bublys, Inc
Opinion of the Court
Plaintiffs, John H. Burrows, M.D., and Eudoro Coello, M.D., are physicians. Defendants, Frederick J. Bidigare and Aligmantas V. Bublys, are professional architects. Defendant Bidigare/Bublys, Inc., is an architectural firm which was formed by the architects.
On August 3, 1976, the two doctors entered into an agreement with Bidigare/Bublys, Inc., in which the architectural firm agreed to perform architectural services relating to a medical clinic which the doctors wanted to have built in St. Clair Shores. The clinic was completed and occupied in October or November of 1977. Considerable glass was apparently used in constructing a "glass curtain wall” in the front of the building. After occupancy, water seeped in and around the windows. According to plaintiffs, water infiltration has interfered with the building’s use, produced rot and plywood delamination and decreased the building’s value. Plaintiffs indicate that after continued negotiations and failed attempts to cure by the architectural firm, the contractor and the glass subcontractor, a solution was effected by another architect and contractor at a cost of $44,725.
The doctors’ contract with Bidigare/Bublys con
On June 28, 1983, defendants moved for accelerated judgment on two grounds: (1) that the claim was barred by the two-year malpractice period of limitation, or alternatively, the three-year negligence period of limitation; and (2) that it was also barred by the ongoing arbitration proceedings. The circuit court was not persuaded by defendants’ statute of limitation argument, finding that the six-year period of limitation contained in MCL 600.5839(1); MSA 27A.5839(1) was directly applicable to claims against architects for damages arising out of the defective condition of an improvement to real property. However, the court was persuaded by defendants’ argument regarding arbitration. The. court held that any claims against both the architectural firm and the individual architects would be required to be submitted to arbitration. The court therefore granted accelerated judgment to defendants on that ground.
Plaintiffs then filed an amended demand for arbitration which included the individual architects as respondents. On August 30, 1984, the arbitrator awarded the plaintiff doctors $10,003 against Bidigare/Bublys, Inc. The doctors’s claims against the individual architects were denied. The claims of plaintiff Burrows & Coello Investment Company were denied as to all respondents.
On September 24, 1984, plaintiffs moved in the
Defendants Bidigare and Bublys appeal from the April 8, 1985, order and judgment. Plaintiffs cross-appeal from the circuit court order granting accelerated judgment for defendants and directing arbitration.
We will first address defendants’ argument that the trial court erred in denying their motion for accelerated judgment on the ground that plaintiffs’ claim was barred by the statute of limitations. Defendants contend that the proper statute of limitations to be applied is MCL 600.5805; MSA 27A.5805, which establishes a two-year limitation for actions charging malpractice and a three-year limitation for other actions to recover damages for injury to person or property, and that the trial court improperly applied MCL 600.5839; MSA 27A.5839, which provides a six-year limitation for actions to recover damages for injury to person or property arising out of unsafe or defective improvements to real property. Defendants submit that the latter statute is inapplicable to suits, such as the instant case, where the claim is for damages for deficiencies in the improvement itself.
A claim for damages for deficiencies in the improvement itself is essentially a suit for breach of contract. Defendants’ obligation to the plaintiffs in this case arose out of the contract for architectural services. The written contract itself contained no express provisions requiring that architectural services be performed skillfully, carefully and in a professional manner, but as a general rule such an obligation is implied in every contract for work or services. See, 17 Am Jur 2d, Contracts, § 371, p 814. A suit for breach of an implied provision of a written contract is a suit on the written contract.
Several other states have had occasion to rule on the issue of whether suits for damages for deficiencies in the improvement itself are within the coverage of statutes similar to MCL 600.5839; MSA 27A.5839 and have held that they are not. These cases are collected in Anno: What statute of limitations governs action by contractee for defective or improper performance of work by private building contractors?, 1 ALR3d 914. The collective cases indicate a general consensus that the appropriate statute of limitation is the one applicable to breach of contract actions. In Michigan, the pertinent statute is MCL 600.5807(8); MSA 27A.5807(8), which provides for a six-year limitation. The instant suit was brought within six years of the time the building was completed and occupied. There
Defendants next contend that the trial court erred in finding the individual defendants liable by applying the provisions of the Professional Service Corporation Act, MCL 450.221 et seq.; MSA 21.315(1) et seq. Section 6 of the act provides:
Nothing contained in this act shall be interpreted to abolish, repeal, modify, restrict or limit the law now in effect in this state applicable to the professional relationship and liabilities between the person furnishing the professional services and the person receiving such professional service and to the standards for professional conduct. Any officer, shareholder, agent or employee of a corporation organized under this act shall remain personally and fully liable and accountable for any negligent or wrongful acts or misconduct committed by him, or by any person under his direct supervision and control, while rendering professional service on behalf of the corporation to the person for whom such professional services were being rendered. The corporation shall be liable up to the full value of its property for any negligent or wrongful acts or misconduct committed by any of its officers, shareholders, agents or employees while they are engaged on behalf of the corporation in the rendering of professional services. [MCL 450.226; MSA 21.315(6).]
It is defendants’ claim that application of the statute was in error because, if allowed the opportunity, defendants would have shown that the defendant corporation was originally incorporated under the Business Corporation Act, MCL 450.1101 et seq.; MSA 21.200(101) et seq., and not the Professional Service Corporation Act. This claim is without merit. The contract could not be performed except by the personal services of pro
The arbitration award in this case held the corporate defendant liable and the individual defendants not liable. The trial judge ordered modification of the award to impose liability on the individual defendants, reasoning that if the corporation was liable, the individual defendants had to be liable also. This was error.
The principle by which the above-quoted portion of the Professional Service Corporation Act imposed liability upon individuals provides for piercing the corporate shield in a very limited situation. It does not destroy the corporate shield to impose liability on all officers, agents or stockholders as if they were partners. Neither does it impose liability upon an individual just because he worked on the project, even if he was one of only two individuals who worked on the project. Liability is imposed upon an individual only when the claimant has sustained the burden of proving that that particular individual personally committed a negligent or wrongful act or misconduct which caused the damage, or directly supervised and controlled the person who commited such an act.
The decision of the arbitrator was consistent with a finding that the proofs presented at arbitration established that the contract was performed defectively, but did not establish which, if either, of the individual defendants was at fault or di
Plaintiffs have cross-appealed from the trial court’s earlier order granting accelerated judgment to defendants on the ground that claims against the individual defendants were subject to the arbitration clause of the contract. Plaintiffs have failed to file a brief in support of their cross-appeal and the cross-appeal therefore may be considered abandoned.
We do point out, however, that the situation here differs from that of a claim against a tortfeasor for negligently inflicted damage or injury. By classic definition, a tort is a civil wrong other than a breach of contract. A classic tort action based upon a negligently inflicted injury arises when there is a breach of a duty imposed by law to use care for the safety of another or his property. The fact that the tortfeasor was an employee or agent of another person or corporation does not make him immune from suit for his breach of the duty imposed by law.
The individual defendants in the instant case owed plaintiffs no duty imposed by law. Regardless of the fact that the individual defendants did not sign the contract in their individual capacities, the defendants’ duties to the plaintiffs arose out of that contract and the claim against them is that they failed to perform that contract with professional skill and care. Because plaintiffs’ claims are based on the defendants’ failure to properly per
The order of the trial court rendering accelerated judgment to the individual defendants on the ground that the plaintiffs’ claims in the suit against them were barred by the arbitration agreement and proceeding is therefore affirmed.
The order of the trial court modifying the arbitration award is reversed.
The status of Peterson Glass Company, a fourth defendant, is not relevant to this appeal.
Plaintiffs attached to their brief copies of the written final arguments of the parties to the arbitration. Such attachments are not properly part of the record in this case. They demonstrate, however, that plaintiffs’ entire argument to the arbitrator was devoted to showing that the problems with the building were due to improper design and to defects in construction that could have been detected if proper inspection had been made. There was no attempt on the part of plaintiffs to zero in as to what individual was responsible for either the defect in design or the negligent inspection.
Dissenting Opinion
(dissenting). Because I do not believe that plaintiffs’ claims against the individual defendants were barred by the arbitration clause in plaintiffs’ contract with defendant corporation, I respectfully dissent. I feel that the majority fails to adequately distinguish between the individual architects’ liability in tort and the corporation’s liability in contract under the facts of this case.
Plaintiffs filed suit in circuit court against the individual architects alleging that they acted in a tortious manner by committing negligent acts. The circuit court granted accelerated judgment on the ground that the claims were required to be presented to arbitration pursuant to the contract between the doctors and the architectural firm, i.e., the corporation. I believe that the trial court erred by granting accelerated judgment on this ground.
Moreover, the individual architects did owe plaintiffs a duty of due care under the circumstances of this case. The individual architects had employment contracts with the architectural firm. Negligent performance of a contract can constitute a tort as well as a breach of contract. In Clark v Dalman, 379 Mich 251, 261; 150 NW2d 755 (1967), it was held that breach of a contract may give rise to an action in tort to a third person who is not a party to that contract. The Clark Court stated:
Actionable negligence presupposes the existence of a legal relationship between parties by which the injured party is owed a duty by the other, and such duty must be imposed by law. . . . Such duty of care may be a specific duty owing to the plaintiff by the defendant, or it may be a general one owed by the defendant to the public, of which the plaintiff is a part. Moreover, while this duty of care, as an essential element of actionable negligence, arises by operation of law, it may and frequently does arise out of a contractual relationship, the theory being that accompanying every contract is a common-law duty to perform with ordinary care the thing agreed to be done, and that a negligent performance constitutes a tort as well as a breach of contract. But it must be kept in mind that the contract creates only the relation out of which arises the common-law duty to exercise ordinary care. Thus in legal contemplation the contract merely creates the state of things which furnishes the occasion of the tort. This being so, the existence of a contract is ordinarily a relevant factor, competent to be alleged and proved in a*188 negligence action to the extent of showing the relationship of the parties and the nature and extent of the common-law duty on which the tort is based. [379 Mich 260-261.]
See also Williams v Polgar, 391 Mich 6, 18-19; 215 NW2d 149 (1974), and Khalaf v Bankers & Shippers Ins Co, 404 Mich 134, 143; 273 NW2d 811 (1978). I believe that a common-law duty to exercise ordinary care arose out of the relation in this case.
Defendant architects have suggested that, because Bidigare/Bublys is incorporated, they are insulated from personal liability. I believe that architects are not shielded from tort liability when they render professional services on behalf of a corporation. Regardless of whether the Business Corporation Act, MCL 450.1101 et seq.; MSA 21.200(101) et seq., or the Professional Service Corporation Act, MCL 450.221 et seq.; MSA 21.315(1) et seq., is applicable, my conclusion remains the same. The mere fact that an individual architect works for a corporation is irrelevant to his tort liability to an injured third party. Basic tort principles indicate that a tortfeasor may be held liable for his or her negligent acts. The fact that the tortfeasor is an employee of, or working on behalf of, a corporation does not change this principle. Tortfeasors are not insulated from tort liability for their own negligent acts simply because their negligent conduct occurred during the Course of employment for a corporation. I must conclude that plaintiffs could assert a cause of action in tort action against the individual architects in this case.
However, liability in tort must be distinguished from liability in contract. The only party which had a contract with plaintiffs was the corporation.
While plaintiffs may have been required to submit their contract claims against the corporation to arbitration, I find no factual support for the claim that plaintiffs were required to submit their tort claims against the individual defendants to arbitration.
In addition, even if the individual architects had been parties to an agreement with the doctors, they would be required to arbitrate only matters relating to the breach of contract. Plaintiffs did not file suit for breach of contract. Rather, they filed suit for damages resulting from tortious conduct. Thus, the trial court erred in granting accelerated judgment on the ground that arbitration was required.
In light of the foregoing discussion, it is clear that the trial court also erred in modifying the arbitrator’s award. The arbitrator awarded plaintiffs $10,003 against Bidigare/Bublys, Inc., for breach of its contract with plaintiffs. I am not persuaded that corporate shareholders, officers or employees should be held responsible for a liability arising out of a contract entered into by the corporation.
Because I believe that the circuit court erred by granting accelerated judgment in favor of defendants on the ground that the claims were required to be submitted to arbitration, I must also determine whether accelerated judgment could properly have been granted on the basis of the statute of limitation. I believe that the trial court properly declined to grant accelerated judgment in favor of defendants on that ground.
The applicable statute of limitation was set forth in MCL 600.5839(1); MSA 27A.5839(1) before
No person may maintain any action to recover damages for any injury to property, real or personal, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribution or indemnity ¡for damages sustained as a result of such injury against any state licensed architect or professional engineer performing or furnishing the design or supervision of construction of such improvement more than 6 years after the time of occupancy of the completed improvement, use or acceptance of such improvement.
In O’Brien v Hazelet & Erdal, 410 Mich 1; 299 NW2d 336 (1980), the Supreme Court held that the six-year restriction on tort liability was constitutional. Moreover, this statute of limitation is specifically applicable to architects and, thus, controls over the more general malpractice or negligence statutes of limitation. See Hawkins v Regional Medical Laboratories, PC, 111 Mich App 651, 655; 314 NW2d 450 (1979), aff'd in part 415 Mich 420; 329 NW2d 729 (1982). Because plaintiffs brought their cause of action within six years after occupancy, use or acceptance, the action was timely filed.
I disagree with the majority and with the panel in Marysville v Pate, Hirn & Bogue, Inc, 154 Mich App 655; 397 NW2d 859 (1986), that a distinction should be made between a suit for injuries "arising out of’ an architectural defect and a suit "for the defect” itself.
First, the statute explicitly applies to actions to recover damages for any injury to property, real or personal, arising out of a defective condition of an
In their complaint, plaintiffs alleged that their damages included disruption of the use of the building, building deterioration, delamination of outer plywood, decrease in building value and the
In conclusion, while I believe that the trial court improperly modified the arbitration award to hold the individual architects personally liable, I also believe that the trial court improperly granted accelerated judgment in regard to plaintiffs’ circuit court complaint.
I would modify the arbitration award to eliminate the personal liability of the individual architects and remand the case to the circuit court for further proceedings regarding plaintiffs’ tort cause of actions.
I do not believe that we are bound to conclude that the claims against the individual defendants are subject to the arbitration clause of the contract simply because plaintiffs have failed to file a brief in support of their cross-appeal. In order to achieve a proper resolution of the issues in this case, it is necessary to determine whether the contract and the arbitration clause were applicable to the individual defendants. Moreover, any questions to be answered in this regard are questions of law and all the facts necessary for their resolution have been appropriately presented.
Reference
- Full Case Name
- Burrows v. Bidigare/Bublys, Inc.
- Cited By
- 7 cases
- Status
- Published