Horton v. Verhelle
Horton v. Verhelle
Opinion of the Court
In this construction lien case, defendant Michigan Homeowner Construction Lien Recovery Fund appeals as of right and defendants RBK Corporation, Clark Foundation Company, Darling Builders Supply Co., Roger D. Hunnicutt, Hunnicutt Plumbing & Heating, and Stahl & Sons, Inc., (RBK et al.) cross appeal from a judgment disposing of the various parties’ claims pursuant to motions for summary disposi
i
FACTS AND PROCEEDINGS
Defendants Richard and Lois Verhelle hired defendant Daniel Hughes, a general contractor, in July 1993 to build a house. Hughes contracted with plaintiff and the other defendants (all subcontractors) to work on the project, which was completed by the end of the year. The Verhelles paid Hughes all but $31,663.30 of the contract price, which they planned to pay at the closing. The Verhelles made their payments pursuant to documents Hughes submitted to them, which purportedly were sworn statements and waivers of lien. The authenticity, accuracy, and legal effect of these documents and payments are now in dispute. Hughes did not appear for the closing and failed to pay plaintiff and the other defendants in full. Various parties, including plaintiff and RBK et al. moved for summary disposition. The court allowed the Verhelles to pay the balance due to the court and it discharged all liens against their property pursuant to MCL 570.1203(1); MSA 26.316(203)(1). It ordered the lien
n
THE SUBCONTRACTORS’ RIGHTS TO RECOVER FROM THE LIEN
FUND
The lien fund contends that the trial court erred in granting summary disposition to plaintiff and RBK et al. The trial court’s ruling on a motion for summary disposition is reviewed de novo. Pinckney Community Schools v Continental Casualty Co, 213 Mich App 521, 525; 540 NW2d 748 (1995). A motion brought under MCR 2.116(C)(10) tests the factual support for a claim. In ruling on such a motion, the trial court must consider not only the pleadings, but also depositions, affidavits, admissions, and other documentary evidence, MCR 2.116(G)(5), and must give the benefit of any reasonable doubt to the non-moving party, being liberal in finding a genuine issue of material fact. Summary disposition is appropriate only if the court is satisfied that it is impossible for the nonmoving party’s claim to be supported at trial because of a deficiency that cannot be overcome. Morganroth v Whitall, 161 Mich App 785, 788; 411 NW2d 859 (1987).
A
EFFECT OF SUBCONTRACTORS’ FAILURE TO FILE TIMELY NOTICES OF FURNISHING
The parties appear to agree that the liens of plaintiff and RBK et al. cannot attach to the Verhelles’ property. A lien cannot attach to a residential struc
If the subcontractors seeking payment from the lien fund are able to satisfy these statutory prerequisites, the Attorney General, who defends the fund, may assert any defense to a lien claim that would have been available to the owner. MCL 570.1203(5); MSA 26.316(203)(5). One available defense is the subcontractor’s failure to provide a timely notice of furnishing. One of the requirements for establishing a valid lien is that a subcontractor provide a notice of furnishing to the owner or his designee and to the general contractor named in the notice of commencement within twenty days after furnishing the first labor or material on the job. MCL 570.1109(1); MSA 26.316(109)(1). Plaintiff and RBK et al. did not timely
i
VALIDITY OF SWORN STATEMENTS
A sworn statement is a notarized form that lists the subcontractors, suppliers, and laborers with whom the contractor contracted, the work they provided,
Of the $121,600 the Verhelles paid Hughes, $59,600 was paid pursuant to two contractors’ sworn statements. The accuracy of those statements was suspect: they indicated that some lien claimants had been paid in full and that their total contract prices were less than the amount of their liens. More significantly, the statements were not dated, signed, or notarized. While the homeowners may be entitled to rely on false sworn statements, cf. Renshaw v Samuels, 117 Mich App 649, 657; 324 NW2d 117 (1982), the statements must substantially comply with the requirements of the statute. Brown Plumbing & Heating, Inc v Homeowner Constr Lien Recovery Fund, 442 Mich 179, 183; 500 NW2d 733 (1993). The sworn statement is essentially a form affidavit attesting to the moneys owed to and paid on contracts with sub
2
VALIDITY OF WAIVERS OF LIEN
The lien fund also asserts the defense that the subcontractors’ claims are defeated to the extent payments were made pursuant to a waiver of lien. MCL 570.1109(6); MSA 26.316.(109)(6). The burden of proof is on the party (in this case, the lien fund) who seeks to show a valid waiver of lien. Durant Constr, Inc v Gourley, 125 Mich App 695, 699; 336 NW2d 856 (1983). Here, the lien fund produced uncontroverted evidence that agents of Darling Builders and Hunnicutt Plumbing & Heating executed full uncondi
The lien fund also produced evidence that agents of RBK and Clark Foundation executed full unconditional waivers of lien, but those agents submitted affidavits in which they denied having given those waivers to Hughes (and implied that they did not execute the waivers), thus creating a question of fact whether the waivers were valid. The lien fund conceded that the waivers may have been forged, but argued that the forgery did not affect the homeowners’ right to rely on the waivers, which thus defeated the claimants’ lien rights. There are no reported cases involving the effect of forged waivers. We find that the issue is analogous to that of the effect of forged deeds. The law is well settled that where a deed is forged, even innocent purchasers are in no better position with respect to title than if they had purchased with notice; there can be no such thing as a bona fide holder under a forgery whose good faith gives him any right against the party whose name was forged. Horvath v Nat’l Mortgage Co, 238 Mich 354, 360; 213 NW 202 (1927); VanderWall v Midkiff, 166 Mich App 668, 685; 421 NW2d 263 (1988). Just as property owners cannot lose property rights to innocent purchasers under forged deeds, we find that lienholders cannot lose lien rights to innocent homeowners under forged waivers. Accordingly, we find that if the parties dispute whether the two lien waivers were forged, that issue must be resolved by the trier of fact. If the trier of fact finds or the parties concede
B
STAHL & SONS’ FAILURE TO ESTABLISH MEMBERSHIP IN LIEN FUND
The hen fund next contends that the trial court erred in granting summaiy disposition to defendant Stahl & Sons because it was not a member of the fund. We agree, and accordingly reverse the trial court’s judgment with respect to Stahl & Sons.
As noted, a hen claimant cannot recover from the fund unless it was a fund member. MCL 570.1203(3)(d); MSA 26.316(203)(3)(d). Residential builders, residential maintenance and alteration contractors, electrical contractors, master plumbers, and mechanical contractors become fund members by paying a fee when applying for initial or renewal licenses. MCL 570.1201(l)(a); MSA 26.316(201)(l)(a). Laborers become fund members by paying a fee when they obtain a recovery from the fund. MCL 570.1201(l)(b); MSA 26.316(201)(l)(b). Ah other hen claimants become fund members by paying a fee “prior to the date of the hen claimant’s contract for the improvement to the residential structure.” MCL 570.1201(l)(c); MSA 26.316(201)(l)(c).
The hen fund produced uncontroverted evidence that Stahl & Sons had not paid the required fee for membership in the fund, although the company’s owner was a fund member. The trial court apparently accepted Stahl & Sons’ argument that the owner’s membership constituted substantial compliance. However, the substantial compliance doctrine does
c
RBK’S FAILURE TO ESTABLISH CONTRACT WITH LICENSED ENTITY
The lien fund also argues that the trial court erred in granting summary disposition with respect to RBK because RBK failed to prove that it contracted with a licensed entity. We agree and remand.
As noted, a lien claimant cannot recover from the fund unless it proves that the contractor or subcontractor with whom it contracted was licensed if required by law to be licensed. MCL 570.1203(3)(h); MSA 26.316(203)(3)(h). RBK apparently did not have a written contract with Hughes. Rather, Hughes submitted a credit application to RBK so he could obtain building supplies on credit. He identified himself as the applicant, his company as Holt Building Company, and his position as president of Holt, a corporation. Holt was not a licensed residential builder, residential maintenance and alteration contractor, or residential salesperson.
By statute, a residential builder or residential maintenance and alteration contractor must be licensed. MCL 339.601(1); MSA 18.425(601)(1), MCL 339.2401 et seq.; MSA 18.425(2401) el seq. Therefore, if Holt
m
TIME/PRICE DIFFERENTIAL FOR HORTON
The lien fund next argues that the trial court erred in granting judgment to plaintiff in an amount that included a time/price differential in addition to the balance due on his contract. We find that the judgment as entered did not comport with the court’s ruling and must be corrected.
Plaintiff claimed a lien in the amount of $8,982.75, representing $8,850 due on the contract plus a $132.75 time/price differential. In his motion for summary disposition, plaintiff noted that the lien fund did not dispute his right to recover $8,850 of his lien and requested judgment against the lien fund in that amount. The trial court granted the motion. The order submitted by counsel for RBK et al. erroneously listed
IV
LIEN FUND’S SUBROGATION RIGHTS
Finally, the lien fund claims that the trial court erred in allowing the lien claimants who were not fund members to recover pro-rata shares of the $31,663.30 paid to the court by the Verhefles. The lien fund argues that it is entitled to that money to offset the sums it must pay to lien claimants who are fund members. We disagree.
If payment is made from the fund, the Department of Licensing and Regulation “shall be subrogated to the rights of the person to whom the payment was made, and the department may maintain any action in its own name against the contractor or subcontractor who did not pay the claimant receiving payment from the fund.” MCL 570.1205(2); MSA 26.316(205)(2). This statute plainly provides that the department is subrogated to the rights of the member lien claimant, that being the only person who may obtain payment from the fund under subsection 203(3). It does not, as the lien fund contends, subrogate the department to the rights of the person from whom payment is due the contractor who did not pay the claimant, i.e., the owner. In any event, the lien fund had not paid any member claimants and thus had not acquired subrogation rights at the time the motions were heard. Even if it had acquired those rights, the lien fund did not plead a cause of action based on those rights.
v
REMAINING ISSUES
No party has directly raised the issue whether the trial court properly dismissed the Verhelles after they paid the balance due on the home to the court for distribution among non-fund members. The lien fund touched on this matter only in reference to its subrogation argument, which we have found meritless. Accordingly, we let stand the order dismissing the Verhelles. Additionally, RBK’s cross appeal issue regarding reversal of this order in the event that we upset the trial court’s disposition of the $31,663.30 paid to the court is moot.
CONCLUSION
In summary, we reach the following conclusions:
We affirm the trial court’s order as it relates to the Verhelles’ payments pursuant to the sworn statements Hughes submitted. As a matter of law, these documents are defective, and do not defeat the subcontractors’ hen rights with respect to work performed before the notices of furnishing were served. The trial court correctly determined that the subcontractors are entitled to recover from the lien fund for these payments.
We reverse the trial court’s order as it relates to the payments the Verhelles made pursuant to waivers of
We reverse summary disposition for Stahl & Sons because the lien fund raised undisputed evidence that Stahl & Sons was not a lien fund member.
We instruct the trial court to amend the judgment to reflect its ruling that Horton is entitled to recover $8,850 from the lien fund.
We affirm the portion of the trial court’s order denying the lien fund’s claim for subrogation
Affirmed in part, reversed in part, and remanded for further proceedings consistent with this opinion. We do not retain jurisdiction.
We will use the term “subcontractors” to refer to both subcontractors and suppliers.
Failure to provide a timely notice of furnishing does not affect a lien claimant’s right to liens for work performed after the notice is provided. MCL 570.1109(5); MSA 26.316(109)(5).
Concurring in Part
(concurring in part and dissenting in part). I agree that the lien claimants who did not provide timely notices of furnishing are nevertheless entitled to hens for work performed before providing notice except to the extent that payments were made to the contractor pursuant to either a contractor’s sworn statement or a waiver of hen. MCL 570.1109(6); MSA 26.316(109)(6).
Regarding the lien waivers, I agree with the conclusion that forged waivers of lien cannot defeat the valid lien rights of innocent lien claimants.
I join in the reversal with regard to Stahl & Sons, Inc., on the basis that it was not a member of the lien fund when it contracted to work on the job.
I agree that there is a genuine issue of material fact concerning RBK’s entitlement to recover from the fund under MCL 570.1203(3)(h); MSA 26.316(203)(h). RBK did not establish that Holt Building Company (Holt)
I join in the majority’s discussion of the time/price differential element of plaintiffs claim.
Regarding the lien fund’s claim of entitlement to the $31,663.30 held by the circuit court, I do not agree that the lien fund forfeited any subrogation rights it might have by failing to pay the lien claimants before asserting those rights. I do not read § 203 as evincing a legislative intent to preclude the lien fund from disputing its liability to a lien claimant and at the same time alternatively asserting a subrogation right should the court hold it hable to the hen claimant.
Additionally, the hen fund pleaded a cause of action against Hughes asserting a right to recover all sums owed to the hen claimants. In its brief in the circuit court, the hen fund asserted that all hen claimants are entitled to equal priority under subsection 119(1) of the statute, MCL 570.1119(1); MSA 26.316(119)(1), and that the $31,663.30 should not be distributed solely to those claimants who were not members of the fund. On appeal, the hen fund asserts an entitlement to the entire sum as the subrogee of the fund-member claimants. The hen fund asserts that the sum is owed by the owner to Hughes, and by Hughes to the claimants.
I would hold that the circuit court erred in ordering that the $31,663.30 be distributed to the nonmember
While I conclude that the circuit erred in ordering that the nonmembers share exclusively in the $31,663.30 and that the hen fund satisfy the fund
In its brief on appeal, the lien fund argues that the untimely filing of the notices of lien bars the lien claimants from enforcing the liens, but
I observe at this juncture that the statutory provision regarding the effect of the owner’s payment to the contractor on the subcontractor’s lien where the subcontractor has not provided a timely notice of furnishing, subsection 109(6), is not completely parallel to the provision regarding the effect of the homeowner’s payments to a contractor on the enforceability of a construction lien on residential premises, MCL 570.1203(1); MSA 26.316(203)(1). Subsection 109(6) applies to all real property and reduces the amount of the lien to the extent payment is made pursuant to sworn statements or lien waivers. Subsection 203(1) applies only to residential structures and declares that the lien will not attach if the homeowner files an affidavit with the court stating that the homeowner has paid the contractor and the amount paid, has not colluded with anyone to obtain payment from the lien fund, and has cooperated and will continue to cooperate in the defense of the lien fund. Thus, in the instant case, unsworn statements and fraudulent lien waivers do not diminish the amount of the lien, but the homeowner nevertheless is entitled to the protection of subsection 203(1), and those lien claimants who are members of the lien fund can proceed against the fund to recover the lien amounts that are valid under subsection 109(6), but do not attach under subsection 203(1).
I reject Stahl & Sons’ argument that the lien fund waived review of this issue by failing to properly identify Stahl & Sons in the fund’s docketing statement, and note that Stahl & Sons has not responded to this issue on the merits.
Hughes contracted with the Verhelles and the remaining parties using the name Cor-Al Construction.
I recognize that RBK may not rely on the fact that Hughes was licensed to establish compliance with the statute, Annex Constr, Inc v
RBK did assert in the circuit court that Holt was not required to be licensed under a different section of the statute, MCL 339.2403(e); MSA 18.425(2403)(e), but has not repeated this argument on appeal.
If one were to conclude that the failure to pay the fund members was fatal to the subrogation claim, the result would be the same. The fund members themselves would be entitled to a pro-rata share of the $31,663.30, and their claims against the lien fund would be reduced by the sums collected. Similarly, it does not matter if the lien claimants’ claims are viewed as claims against the contractor or the homeowner. The homeowner owed the contractor $31,663.30 under the contract, and that sum was subject to the subcontractors’ claims for payment from the contractor. The court permitted the homeowner to pay the sum to the court, rather than the contractor as provided in subsection 203(1), but the money was constructively the contractor’s (subject to subcontractor claims) pursuant to the contract. If the claim is viewed as one against the homeowner for the remaining $31,663.30, then the facts must be viewed from the standpoint of the money not having been paid to the court or the contractor. The homeowner, then, would not be entitled to the protection of subsection 203(1) with respect to that amount, and the lien fund members would have no claim against the lien fund for those amounts.
Reference
- Cited By
- 11 cases
- Status
- Published