United States ex rel. Laborers' Pension Trust Fund v. Safeco Insurance Co. of America
United States ex rel. Laborers' Pension Trust Fund v. Safeco Insurance Co. of America
Opinion of the Court
MEMORANDUM OPINION AND ORDER
This case is presently before the court on defendant Safeco Insurance Company’s motion, pursuant to Fed.R.Civ.P. 12(b)(6), to dismiss use-plaintiffs’ Laborers’ Pension Trust Fund — Detroit and Vicinity, Laborers’ Vacation and Holiday Trust Fund — Detroit and Vicinity, and Laborers’ Metropolitan Detroit Health and Welfare Fund (hereafter collectively “Funds”) claim under the Miller Act, 40 U.S.C. § 270a et seq.
The Funds’ complaint reveals the following undisputed facts. Pursuant to collective bargaining agreements between various locals of the Laborers’ union and Kaltz
The Miller Act permits a person who has performed work on a government contract covered by the Act to recover under the performance bond if he or she has not been paid in full. See 40 U.S.C. § 270b(a). As remedial legislation, the Miller Act is “entitled to a liberal construction and application in order to properly effectuate the Congressional intent to protect those whose labor and materials go into public projects.” Clifford E. MacEvoy Co. v. U.S. ex rel. Calvin Tompkins Co., 322 U.S. 102, 107, 64 S.Ct. 890, 893, 88 L.Ed. 1163 (1944) (Murphy J.) (quoted in Morrison-Knudsen Co., supra 687 F.2d at 131). The class of persons entitled to invoke the protections of the Act is limited, however. Section 270b(a) contains a proviso which is clearly applicable to the present controversy:
“any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing such payment bond shall have a right of action upon the said payment bond giving written notice to said contractor within ninety days from the date on which said person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or from whom the labor was done or performed.
“[T]he right to bring suit on a payment bond is limited to ... those materialmen, laborers and subcontractors who, lacking an express or implied contractual relationship with the prime contractor, have direct contractual relationship with a subcontractor and who give the statutory notice of their claims to the prime contractor.” MacEvoy, supra 322 U.S. at 107-108, 64 S.Ct. at 894; accord U.S. ex rel. San Joaquin Blocklite v. Lloyd E. Tull, Inc., 770 F.2d 862, 865 (9th Cir. 1985); U.S. ex rel. John D. Ahem Co., Inc. v. J.F. White Contracting Co., 649 F.2d 29, 31 (1981) (notice requirement “is a strict condition precedent to the existence of any right of action”). “The purpose of notice, which is subsidiary ■ to the Act’s main purpose of protecting those whose labor and materials is used, is to protect the general contractor by fixing the date beyond which, absent notice, he will not be liable for the subcontractor’s debts.” U.S. ex rel. Kinlau Sheet Metal Works, Inc. v. Great American Insurance Co., 537 F.2d 222, 224 n. 1 (5th Cir. 1976). The nub of the present controversy is whether the Funds have properly complied with the notice provisions of § 270b.
Though Safeco has moved for dismissal for failure to state a claim upon which relief can be granted, because both parties have introduced and referred to materials
The court can only conclude that the April 21, 1988 notice is legally insufficient to preserve the Funds’ claim under § 270b. This is because April 21, 1988 is more than ninety days after the completion of work on the Kaltz subcontract under either the plaintiffs’ or defendant’s version of the facts. The question presented then is whether (and to what extent) the notice afforded before completion of work on the project will fulfill the notice requirements of § 270b. As the parties have indicated the Sixth Circuit has not ruled on this question and the court of appeals which have are split as to the proper resolution of the issue.
In Kinlau the Fifth Circuit held that notice of a claim submitted by a supplier of materials for amounts owed before completion of the job by the subcontractor “was premature and could not even be considered as possible notice for that job.” 537 F.2d at 224. The Kinlau court apparently relied on what it took to be unambiguous language in the proviso, for no reasons are given for its construction. Nor is any given in National Union Indemnity Co. v. R.O. Davis, Inc., 393 F.2d 897 (5th Cir. 1968) which was relied upon by the Kinlau court. In Dravo Corp. v. Robert B. Kerris, Inc., 655 F.2d 503 (3d Cir. 1981) the Third Circuit reached the same result in construing the terms of a performance bond issued for work on a private construction contract. The notice provisions of the bond were identical to that contained in § 270b. The Dravo court held that “[t]he plain meaning of these terms is that notice must follow the last labor or delivery and that premature notice will not be considered as timely.” 655 F.2d at 508-509. The court noted that permitting premature notice to suffice would burden the payor of the bond with the task of monitoring “a multitude of ‘possible’ claims” under the bond and potentially “frustrate payment arrangements between a subcontractor and its supplier.” 655 F.2d at 509. While state law favored the rights of materialmen to collect under such surety bonds, the Dravo court concluded that it did not override what it took to be the clear language of the bond. Id.
This court does not find that the relevant language of § 270b dictates the result reached in the Fifth Circuit and analogously in the Third. Rather “[t]he statute does not require that the notice be given only after final completion of the project. The notice is timely if given within ninety days after the performance of the last labor or supply of the last material ‘for which such claims is made.’ ” U.S. ex rel. Honeywell,
Applying this rule to the instant case, it is clear that the Funds supplied the requisite notice on July 20, 1987
IT IS SO ORDERED.
. Also before the court Is the parties' joint motion to submit a supplemental pleading. The motion is granted and the court has considered the brief in ruling on the motion.
. 40 U.S.C. § 270a provides, in relevant part, that:
Before any contract, exceeding $25,000 in amount, for the construction, or repair of any public building or public work of the United States may be awarded, such person shall furnish to the United States the following bonds, which shall become binding upon the award of the contract to such person ... (2) A payment bond with a surety or sureties satisfactory to such officer for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract for the use of said person. See U.S. ex rel. Consolidated Pipe and Supply Co. v. Morrison-Knudsen Co., Inc., 687 F.2d 129, 131 (6th Cir. 1982) (noting that the Act "is designed to provide an alternative remedy to the mechanics’ liens ordinarily available on private construction contracts.”)
. This dispute is, as is discussed infra, immaterial to resolution of this motion.
. The Ninth Circuit has also indicated, albiet in dictum, that premature notice is insufficient under the Miller Act. Blocklite, supra 770 F.2d at 866.
. Defendant does not contest the sufficiency of the notice provided.