Boston v. Henderson
Boston v. Henderson
Opinion of the Court
Defendant, a sewer contractor, engaged plaintiff, for a stipulated price of $1,500, to drive the
There was no question but that defendant did use the engine for pumping purposes. His contention was, however, that he used it at plaintiff’s suggestion, with the assurance that if he (defendant) would pay the engineer, and for the fuel, there would be no charge for 'the engine. Defendant paid the engineer.* Plaintiff claimed, however, that there was no assurance that no charge would be made for the engine, but, on the contrary, that it was expressly agreed that the value of the use of- the engine should be paid. This question was fairly submitted to the jury, and we find no error in the record respecting it.
That the plaintiff was delayed by the failure of defend
The court instructed the jury as follows:
“ First, as to what damage, if any, the plaintiff is entitled to receive for the unreasonable delay that occurred through there not being timber at this sewer so as to enable him to carry out his contract. For that delay the defendant in this suit is responsible. It is not to be supposed when a man takes a contract to do a certain piece of work, such as this, that he will be delayed day after day, and week after week, without the contractor with him being responsible, unless there is a syiecial agreement, in the contract limiting the liability of the person for whom the work is done; so I say to you, as a matter of law, that if the plaintiff in this suit was delayed an unreasonable length of time, and if you believe the testimony of the plaintiff, then he was delayed an unreasonable length of time, and the defendant in this case would be responsible to him for such damage as he suffered through the delay.”
A question was raised as to whether some part of the delay was not chargeable to plaintiff. No complaint was made because of delay, nor was any claim made for loss of time until after the controversy over the use of the engine, and until this suit was brought. There was some testimony that this very matter of probable delays was talked over at the time of making the contract. It was for the jury to say whether this was the fact or not, and also, to say whether the delay was beyond that con
Testimony as to the per cliem value of the pile driver was erroneously admitted. The measure of damages in cases of this character is not the value of the use of idle tools or idle machinery, unless that idleness is enforced by the act complained of. If there had been any showing that plaintiff had the opportunity to use this machinery elsewhere, and was necessarily deprived of its use by this delay, another question would have been presented. The value of the use of machinery involves profit, and a party is not entitled, in an action for damages, to profits, unless the act complained of has deprived him of an opportunity to earn them.
It is insisted by defendant that, plaintiff and defendant having stated the contract account, plaintiff is now estopped from adding the claim for loss of time. It is sufficient to say that no such question is raised by the pleadings. Johnson v. Stellwagen, 67 Mich. 14; Wessels v. Beeman, 87 Id. 481.
For these errors the judgment is reversed, and a new trial ordered, with costs to defendant.
Reference
- Full Case Name
- Charles Boston v. Michael Henderson
- Status
- Published