Martin v. Warren
Cases that cite this one
6 later published cases cite this decision.
- Wildey v. Gillett (Mich. 1912)
- Vander Horst v. Kalamazoo Apartments Corp. (Mich. 1927)
- Holliday v. Mathewson (Mich. 1906)
- Dittmer v. Bath (Mich. 1898)
- Barnard v. McLeod (Mich. 1897)
- Wiltsie v. Harvey (Mich. 1897)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
This case is ruled by Sterner v. Haas, 108 Mich. 488. It is contended that it should not-be held to fall within the spirit, although within the letter, because in the present case more than 60 days had elapsed after the full completion of the work by the contractor at the time the hill was filed, and hence there was no chance for a lien to be perfected and enforced against said premises by subcontractors, laborers, or material men. If this contention is sound, the landowner must determine, at his peril, when said 60 days expires. If he
Case-law data current through December 31, 2025. Source: CourtListener bulk data.