Mt. Clemens Sugar Co. v. Grand Trunk Railway Co.
Mt. Clemens Sugar Co. v. Grand Trunk Railway Co.
Opinion of the Court
Plaintiff owns and operates a sugar factory near Mt., Clemens which is connected with defendant’s railroad system by means of a spur track about two miles north of Mt. Clemens. During the sugar making seasons of 1906-7, 1908-9, 1909-10, 1911-12, plaintiff, under threat of being deprived of the switch engine and crew, paid certain demurrage charges under protest to defendant, amounting to nearly $20,000. It was claimed that these charges should not have been demanded because plaintiff was not responsible for the delay in unloading the cars during the free time allowed by law, but that the fault lay with defendant because of its failure to
1. Plaintiff, to establish its contention, showed that its daily capacity was from 35 to 40 cars of beets; that its tracks would hold 159 cars, and that if defendant had had sufficient trackage to have stored the consigned cars and taken care of the empties, there would have been little or no delay in unloading them; that defendant’s track facilities at Mt. Clemens consisted of a single main track, a passing track three-quarters of a mile in length, a team track which would hold not to exceed 40 cars, and a private siding which it used holding 18 cars; that its track and yard facilities in these years were no greater than they were 30 years ago when Mt. Clemens was much smaller and the traffic much less than at the present time. It was further shown that the spur track to plaintiff’s factory connected directly with the main line track instead of with the siding, and this was the cause of much delay on the part of the switching crew, as they
On the other hand, testimony was offered tending to discredit some of plaintiff’s testimony in this regard, and other testimony tending to show that the cars were delivered as rapidly as plaintiff could take care of them. The testimony presented a clean-cut question of fact, and was such that the jury might have determined it either way. Counsel’s contention that a verdict should have been directed for defendant on this issue, in the face of this testimony, is not easily understood. We shall simply have to dispose of it by saying we disagree with them.
2. Counsel argue that the trial court was in error in refusing to instruct the jury that the switching service on the spur which plaintiff counts upon as not having been performed or properly performed was “plant switching” for which defendant was not liable. The interstate commerce commission has drawn a distinction between “plant switching” and “terminal switching,”' holding that the former is outside of the contract of the carrier, and, therefore, unlawful as a rebate, while the latter is within its contract of carriage (14 I. C. C. 237-246). This distinction has been discussed by the Federal courts. See Los Angeles Switching Case, 234 U. S. 294. Much controversy was indulged in at the trial as to whether the switching service on the spur at the plant, which was contracted for and rendered by'defendant, was “plant
“I think, gentlemen of the jury, that there is no question but that in this case this railroad company was not obliged to do this switching in the yard of the complainant of these cars, and that whatever was done was volunteered, and that the complainant cannot find fault with reference to that or require it; and that the failure of the company, if there was any failure, and I may not say that there was, if there was any failure that that cannot be considered in this case by you, this failure to do this switching. So no claim of delay can be made on this ground.”
We refrain from any comment as to the correctness of this instruction, but refer to it solely for the purpose of showing that the trial court instructed the jury in accordance with defendant’s contention. In view of this elimination by the court we can see no occasion for discussing the question as to whether switching service on the spur and at the plant should be denominated “plant switching” or “terminal switching.”
“The defendant company had the right to assess demurrage upon cars consigned to plaintiff which were held at Milwaukee Junction, Durand, or any station upon its road, because of the plaintiff’s inability to receive and dispose of them at the factory, and was not called upon to wait until it had brought said cars to Mt. Clemens before charging demurrage upon the same.”
As the trial court agreed with counsel in this contention, it will receive no further consideration.
4. It was urged upon a motion for a new trial that the verdict was against the overwhelming weight of the testimony. The issue of fact was submitted to the jury as favorably to defendant’s case as the proofs would permit, and we think the conclusion reached by them is amply justified by the record. The record is quite persuasive that the real difficulty lay in the lack of terminal facilities of defendant at Mt. Clemens, and in the fact that the switching crew had to use the main track for switching purposes which would have been unnecessary had plaintiff’s spur been connected with the siding. Had it been so connected switching operations could have gone forward while main line trains were passing. The application for a new trial upon this ground was properly overruled.
The judgment must be affirmed.