                                                                               OFFICE OF
                               STATE OF MINNESOTA                          APPELLATE COURTS

                               IN COURT OF APPEALS                             SEP 3 0 2015

                                                                              FILED
In the Matter of the Application of
North Dakota Pipeline Company LLC                            ORDER
for a Certificate of Need for the Sandpiper
Pipeline Project in Minnesota.                               #A15-0016

In the Matter of the Application of
North Dakota Pipeline Company LLC
for a Pipeline Routing Permit for the
Sandpiper Pipeline Project in Minnesota.


      Considered and decided by Rodenberg, Presiding Judge; Cleary, Judge; and

Klaphake, Judge.*

BASED ON THE FILE, RECORD, AND PROCEEDINGS, AND BECAUSE:

       1.     We filed our opinion in this matter on September 14, 2015.      Respo~dent


Minnesota Public Utilities Commission made a motion to clarify the final sentence of the

opm10n.

      2.     No petition for rehearing is allowed in this court. Minn. R. Civ. App.

P. 140.01. The syllabus and the body of the opinion accurately describe the procedural

posture of the case and this court's holding. But we have concluded that it is appropriate

to modify the language of the concluding sentence of the opinion.




* Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to
Minn. Const. art. VI, § 10.
      IT IS HEREBY ORDERED: The attached page is substituted for page 11 of the

opinion filed on September 14, 2015.

      Dated:    9/Jtfl/(




                                       2
underestimated only to be discovered after resources have been committed or the die

otherwise cast." Robertson v. Methow Valley Citizens Council, 
490 U.S. 332, 349
, 
109 S. Ct. 1835, 1845
 (1989).

       In this case, the completion of an EIS at the certificate of need stage satisfies the

imperative identified above by ensuring decision-makers are fully informed regarding the

environmental consequences of the pipeline, before determining whether there is a need

for it. Moreover, completion of an EIS at the initial certificate of need stage seems

particularly critical here because once a need is determined, the focus will inevitably turn

to where the pipeline should go, as opposed to whether it should be built at all. We

acknowledge that the MPUC did order a high level environmental review to be

considered during the certificate of need proceedings.       But as the MPUC noted, this

review was not meant to serve as a substitute for the more rigorous and detailed review

needed to satisfy MEPA, and it cannot take the place of a formal EIS now. Accordingly,

we conclude the MPUC erred by not completing an EIS at the certificate of need stage as

MEPA requires.

                                      DECISION

       Where routing permit proceedings follow certificate of need proceedings, MEPA

requires that an EIS must be completed before a final decision is made on issuing a

certificate of need. Therefore, we reverse and remand to the MPUC to complete an EIS

before a final decision is made to grant or deny a certificate of need.

       Reversed and remanded.




                                             11


Reference

Full Case Name
In the Matter of the Application of North Dakota Pipeline Company LLC for a Certificate of Need for the Sandpiper Pipeline Project in Minnesota. In the Matter of the Application of North Dakota Pipeline Company LLC for a Pipeline Routing Permit for the Sandpiper Pipeline Project in Minnesota. [ORDER]