Hanley v. Noyes
Can I rely on this case?
Citation treatment has not been reviewed for this case. The notes below come from the citation graph and the Minnesota Revisor's amendment records, not from a review of how later courts treated this decision.
(as of 9/30/2026)
Last cited by a Minnesota appellate court in 1937, among the opinions in this site’s citation index.
Not a substitute for Shepard’s or KeyCite — verify before relying.
See our Terms of Use before relying on these notes. Report an error
Cases that cite this one
8 later published cases cite this decision.
- Behrens v. Kruse (Minn. 1916)
- State v. Illinois Central Railroad (Minn. 1937)
- Thoele v. Lavallee Law Book Co. (Minn. 1923)
- Fidelity & Casualty Co. of New York v. Gillette-Herzog Manufacturing Co. (Minn. 1904)
- Shove v. Martine (Minn. 1901)
- Shaw v. Chicago, Rock Island & Pacific Railway Co. (Iowa 1891)
- Fred W. Wolf Co. v. Salem (Ill. App. Ct. 1889)
- Lipsmeier v. Vehslage (U.S. Circuit Court for the District of Eastern Missouri 1886)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
We are compelled to the conclusion that the finding of the court that the settlement between the parties did not include the items of $54.83 and $3'3 is contrary to the undisputed evidence. The instrument “F” executed by plaintiff on the settlement, whether considered a receipt or a contract, is, in any view of the ease, prima facie evidence that every claim for “special” or extra work was included. Plaintiff offered no evidence in explanation of this settlement, and there is nothing to show that it was not just as the writing states — “of all special work done on defendant’s house, ” and “in full of all claims to date.”
Plaintiff, however, contends that the amount agreed on at this settlement not having been paid in full, it was a case of an unexecuted accord, or an accord without satisfaction, and therefore no bar to a suit on the original claim, just as if no settlement had ever been made. The facts are that plaintiff had an unliquidated and disputed claim against defendant for some $1,500 for alleged “extra” work on his house. The parties, by way of settlement and compromise, liquidated it at $800, which both agreed and assented to as the
Judgment reversed, and new trial ordered.