Evans v. Miller
Evans v. Miller
Opinion of the Court
This action is to compel the specific performance of an agreement of the defendants for the conveyance of a lot of land to the plaintiff or for damages. The complaint alleges the making of the agreement, and the execution by the defendants of their written obligation to convey, 'being in the form of a bond for a deed, except that it was not under seal; that pursuant thereto, the plaintiff went into possession, and erected a house, and made other improvements, at an expenditure of $1,000; alleges a tender of the agreed price as named in the writing, and the defendants’ refusal to convey. The answer admits the making and delivery of the written instrument, the possession of the plaintiff, and the erection of the house, with the consent of the defendants, subsequent to the execution and delivery of the writing; but puts in issue the alleged value of the improvements, and the tender of the price. The evidence sustained the complaint as to the matters in issue, and the court made its decision to the effect that unless within a time specified the defendants should convey the premises and accept the price tendered, the plaintiff should have judgment for $800.
As to the defendants’ contention that there was no completed contract, it is enough to say that the case, as admitted in the answer,
It is urged that the plaintiff ought not to recover on account of the-improvements on the land so long as he is still in possession. The-defendants have no reason to complain of the determination in this respect. They had the option to convey, as they were bound to do, and as they presumably might have done. The evidence justified, the finding as to the measure of the recovery.
Order affirmed.
Reference
- Full Case Name
- Frank Evans v. W. R. Miller and another
- Status
- Published