Schwartz v. Church of Holy Cross
Can I rely on this case?
Citation treatment has not been reviewed for this case. The notes below come from the citation graph and the Minnesota Revisor's amendment records, not from a review of how later courts treated this decision.
(as of 9/30/2026)
Last cited by a Minnesota appellate court in 1968, among the opinions in this site’s citation index.
Not a substitute for Shepard’s or KeyCite — verify before relying.
See our Terms of Use before relying on these notes. Report an error
Cases that cite this one
9 later published cases cite this decision.
- Lawson & Nelson Sash & Door Co. v. Kraus-Anderson of St. Paul Co. (Minn. 1968)
- Hartman v. Smyth Sales, Inc. (N.J. 1939)
- Tri-State Terminal Co. v. Washington Wheat Growers Ass'n (Wash. 1925)
- J. L. Owens Co. v. Leland Farmers Elevator Co. (Iowa 1924)
- Lieb Packing Co. v. Trocke (Minn. 1917)
- Breen Stone Co. v. W. F. T. Bushnell Co. (Minn. 1912)
- Mobile Fruit & Trading Co. v. McGuire (Minn. 1900)
- Columbia River Door Co. v. H. F. Cady Lumber Co. (Neb. 1914)
- Baskerville v. Johnson (S.D. 1905)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
This action, which was brought to recover the contract price of three altars constructed for defendant, and set up in its church, was tried and submitted to the jury entirely upon the issues — First, whether the altars were a substantial performance of the contract between the parties; and if not, second, whether the defendant had accepted them as such. The trial court set aside a verdict in favor of the plaintiffs, and the only question on this appeal is whether the preponderance of evidence upon either or both of these issues was so “manifestly and palpably” in favor of the verdict that it was error for the court to set it aside.
1. The evidence is so strong to the effect that the altars furnished were different from and' inferior to the requirements of the contract, in style of dome, carving, profile, and general workmanship, that, even giving plaintiffs the full benefit of the doctrine of “substantial compliance,” the verdict could not have been sustained on the ground that defendant was bound to accept the altars as a performance of the contract.
2. To establish an acceptance of the altars, so as to bind the defendant to pay for them, the plaintiffs rely — First, on a trifling payment of $10 on the purchase price; and, second, the use of the main altar after it was set up in the church. The $10 was paid to an employé of plaintiffs, who had been sent up to Minneapolis to set up the main altar, as a mere matter of accommodation to him, and on his representation that he was short of funds to pay his expenses home. And, while it was undoubtedly intended as a provisional payment on the purchase price of the altars in case the contract was fully performed, yet the payment, under the circumstances, is of practically no weight whatever as tending to prove an acceptance.
3. From the time the main altar was set up, in October, in an incomplete state, the defendant’s officers expressly- and repeatedly made known to plaintiffs their objections to it, and their refusal to accept it, because not in accordance with the specifications of the
It is unnecessary to consider counsel’s contention that, undér the terms of the contract, the delivery of the altars to a carrier in lili
Order affirmed.