McCormick Harvesting Machine Co. v. Balfany
Can I rely on this case?
Citation treatment has not been reviewed for this case. The notes below come from the citation graph and the Minnesota Revisor's amendment records, not from a review of how later courts treated this decision.
(as of 9/30/2026)
Last cited by a Minnesota appellate court in 1950, among the opinions in this site’s citation index.
Not a substitute for Shepard’s or KeyCite — verify before relying.
See our Terms of Use before relying on these notes. Report an error
Cases that cite this one
8 later published cases cite this decision.
- Sioux Falls Adjustment Co. v. Aikens (S.D. 1913)
- J. B. Inderrieden Co. v. J. C. Johnson Co. (Minn. 1910)
- International Harvester Co. of America v. Hayworth (S.D. 1909)
- Fairbanks, Morse & Co. v. Heltsley (Ky. Ct. App. 1909)
- Thomas D. Murphy Co. v. Exchange National Bank of Hastings (Neb. 1906)
- Sherman Nursery Co. v. Aughenbaugh (Minn. 1904)
- McCormick Harvesting Machine Co. v. Calta (Minn. 1902)
- McHardy v. Standard Oil Co. (Minn. 1950)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
We assume that when plaintiff, through its agents, who went to defendant’s house for that purpose, procured and received the orders signed by defendant, made out on one of plaintiff’s blanks, and furnished to defendant a copy thereof, there was an acceptance by plaintiff of defendant’s proposition to buy a machine, and thus the order became a complete executory contract, as between these parties; the plaintiff agreeing to sell, and the defendant agreeing to buy, the “right-hand” machine therein described. See Kessler v. Smith, 42 Minn. 494, 44 N. W. 794. This contract bore date April 15, 1898, and required that plaintiff should ship the machine to defendant, consigned to the care of Gebhard & Ruth, plaintiff’s local agents, at Lamberton, Minnesota, on or about July 15 of that year.
Now, the undisputed testimony is that something over 60 of these machines, alike in every respect, were shipped by plaintiff to these local agents, reaching Lamberton about July 15. Fart of them were unloaded from the cars, and taken to the agents’ place of business or sheds, where about six of the number were unpacked and set up ready for delivery. Defendant was at the sheds soon afterwards, and was told that the machine he had ordered was ready. His reply was that he wanted a “left-hand” machine, and would not take a “right-hand.” He positively refused to take a machine answering the requirements of the order, and also positively refused to settle, either‘by paying in cash or by giving his notes. No particular machine was designated or marked as for defendant when the lot was shipped by plaintiff, none was consigned to him in care of the local agents or otherwise, and none was set apart or pointed out to defendant as the one he had ordered when he was at the agents’ place of business. Nor did the local agents designate or set apart any particular machine at any time as defendant’s, although they have constantly kept on their premises, ready for delivery to him, a machine complying in all respects with the description in the order.
There was no actual delivery of a machine to defendant; for he expressly refused to take possession, and plaintiff cannot recover the contract price therefor, .unless the facts as shown prove that
The facts now before us show conclusively that there was no constructive delivery of a machine to defendant. The order, in terms, authorized the plaintiff to select and appropriate a machine to the contract, and to defendant, by designating the same, and it expressly directed that it be consigned to him in care of the local agents. But this was not done. There was no designation of any machine as defendant’s; and none consigned to him. Nor was there at any time an appropriation of any particular machine by the agents to defendant’s contract out of the large number which had been received at their place of business. The machine was not specified to which the contract would attach, or, in legal phrase, there was no appropriation of a machine to defendant, or to his contract, and no property passed. Stating to defendant that his machine was ready to be delivered, and pointing to a number then on hand, either of which would comply with the terms of the order, did not amount to constructive delivery of any particular machine, ntfr was there any act on plaintiff’s part which would pass the title so as to vest it in defendant, and thus authorize a recovery of the contract price. The result of permitting such a recovery would be nothing more or less than enforcing specific performance of a contract for the sale and delivery of chattels, contrary to the general rule.
As on the evidence the plaintiff could not recover the contract price, it is not necessary to consider or pass upon that part of the charge which bore upon the alleged “countermand” of the order.
Order affirmed.