The Minnesota Supreme Court affirmed a judgment for plaintiff's claimed stone delivery quantity under a bridge construction contract against defendant's lower quantity assertion.
Outcome: Affirmed for plaintiff.
Steinbauer v. Stone
What happened
The facts of the case, in plain language.
Plaintiff claimed he delivered 2,021 cubic yards of stone at $6 per cubic yard under the contract; defendant admitted the contract and delivery of stone but claimed only 1,888 cubic yards were actually furnished.
Plaintiff's evidence that there was a general custom among similar contractors to ascertain cubic yards by measurements from the completed structure was struck out as insufficient, because plaintiff's knowledge came only from contracts he himself had made.
The case proceeded to the jury with measurement of cubic yards by weight as the only method for determining the disputed quantity.
Defendant's evidence tending to prove damages from plaintiff's failure to deliver stone at the contractually required rate of four cars per day was excluded as calling for speculative witness opinions.
What the court decided
This case involved a dispute over the quantity of stone furnished under a contract for a bridge construction project at Eau Claire, Wisconsin. The plaintiff claimed he delivered 2,021 cubic yards of stone at $6 per yard, while the defendant admitted the contract existed but contended only 1,888 cubic yards were actually delivered. The trial court submitted the case to the jury, which returned a verdict for the plaintiff. On appeal, the defendant challenged various evidentiary rulings and jury instructions. The Minnesota Supreme Court affirmed the verdict, finding that the trial court properly excluded speculative expert testimony about damages and that alleged minor verbal errors in the jury instructions were harmless and not prejudicial when the instructions were read as a whole.
- Evidence of trade custom is inadmissible where the witness's knowledge of the purported custom derives solely from contracts the witness personally made and performed, rather than from general market or industry practice. (*276)
- A question posed to a witness that requires the witness to state a conclusion as to the amount of additional costs or damages caused by a breach is inadmissible as calling for speculative opinion; the extent and amount of damages from a contractual failure are questions for the jury, not the witnesses. (*277)
- A verbal or technical error in a jury instruction does not warrant a new trial where, reading the charge as a whole, the jury could not have been misled, and where counsel failed to call the specific error to the trial court's attention for correction before the jury retired. (*278)
- A jury verdict on a contested question of fact that has been approved by the trial court will not be disturbed on appeal unless it is clearly and palpably against the evidence. (*279)
How the court reached its decision
The court's reasoning, step by step.
Whether plaintiff's evidence of a trade custom for measuring cubic yards by reference to the completed structure was properly excluded. Plaintiff offered testimony that persons engaged in similar contracts customarily ascertained cubic yards by measurements from the completed structure, but it clearly appeared that all he knew of any such custom came from contracts he himself had made and performed. The trial court properly struck the custom evidence; even if not fully stricken, the incomplete and valueless evidence could not have prejudiced defendant before the jury.
Whether the trial court properly excluded defendant's witness testimony about the cost consequences of plaintiff's failure to ship stone at four cars per day. Defendant asked a witness how much more it necessarily would have cost to perform the work because stone was not delivered at the rate of four cars per day. The question required the witness to reach a speculative conclusion as to the quantum of damages from the breach. The objection was properly sustained; an answer would have been a mere speculative conclusion of the witness. The damages questions were fully and fairly submitted to the jury by the trial court.
Whether verbal errors in the trial court's jury instructions — use of 'or' instead of 'and,' and omission of idle teams and machinery from the damages instruction — warranted a new trial. The court used 'or' instead of 'and' between conditions in one instruction and omitted reference to idle teams and machinery in the damages instruction. Taking the whole charge together, the jury could not have been misled by either error. Defense counsel did not call these errors to the trial court's attention to permit correction before the jury retired. Both errors were mere verbal mistakes in no way prejudicial to defendant; the assignments of error presented no reason for granting a new trial.
Whether the jury's verdict on the quantity of stone delivered was supported by sufficient evidence. The main controversy was the number of cubic yards of stone furnished. Both parties submitted evidence on this question, which was fully and fairly submitted to the jury, and the trial court approved the verdict after examining voluminous evidence. The evidence was not so clearly and palpably against the verdict as to justify setting it aside, and the order denying a new trial was affirmed.
Key quotes from the opinion
Notable passages from the opinion, in the court's own words.
Full opinion
The complete text of the court's opinion as published.
Opinion of the Court
This action was brought to recover a balance claimed to be due plaintiff for certain stone furnished by him to defendant under a contract between the parties, for use in the construction of a bridge at Eau Claire, Wisconsin. Plaintiff claimed in his complaint that he delivered to defendant two thousand twenty-one cubic yards of stone, while defendant, admitting the contract,, and that certain stone was furnished thereunder, denies that any more than eighteen hundred eighty-eight cubic yards were in fact furnished. Defendant also set up a counterclaim for damages for the alleged failure of plaintiff to furnish the stone at the time required by the contract. Plaintiff had a verdict in the court below, and defendant appealed from an order denying a new trial.
The principal question on the trial in the court below with respect to the right of plaintiff to recover was as to the quantity of stone furnished by him under the contract; that is, the number of cubic yards. The contract provided that defendant should pay sis dollars per cubic yard for all stone furnished and delivered, and the main controversy below was as to the quantity actually furnished. It was contended by plaintiff, and he offered evidence for the purpose of so showing, that there was a general custom among persons engaged in similar contracts and transactions to ascertain and determine the number of cubic yards by measurements from the completed structure; but his evidence tending to show such a custom fell far short of doing so, and was stricken out. It clearly appeared from his testimony that all he knew of any custom of that nature was learned from contracts he himself had made and performed. Upon this fact appearing, the court below struck out the evidence, and the case was submitted to the jury without refer
But it is contended by appellant that, even though this evidence was not submitted to or considered by the jury, its admission resulted prejudicially to defendant. We are entirely at a loss to understand how this evidence, incomplete and valueless for any purpose, even though not stricken out, could have prejudiced the defendant before the jury, and we are unable to concur with counsel that its admission resulted to the detriment of his client’s’ cause.
Assignments of error 4, 5, 8, 10,11, and 12 refer to the exclusion by the trial court of certain evidence offered by defendant tending to prove the damages alleged to have been sustained by him in consequence of plaintiff’s failure to furnish the stone at the times called for by the contract. One question to which an objection was sustained, was as follows:
“How much, in your judgment, would it necessarily cost to do that work, more, by reason of the stone not being delivered at the rate of four cars a day, than it would have cost if they had been delivered four cars a day that year, considering the weather and the situation thereof?”
This question called for the conclusion of the witness, and the objection to it was properly sustained. Other questions complained of by these assignments of error are substantially of a similar nature and import, and an answer thereto would amount to nothing more than a mere speculative conclusion of the witness,
Appellant complains of two alleged errors in the instructions of the court to the jury. The court charged the jury as follows:
“Now, if the plaintiff was not in default in any of these particulars; if the stone was shipped in time, or if it was shipped in the proper method, and was properly cut at the time it was shipped, the defendant would have no cause to complain, and no right to recover damages in any event in this case.”
The objection to the instruction is that the word “or” between the clauses “if the stone was shipped in time” and “if it was shipped in the proper method” should have been the conjunction “and”; that because of the use of the word “or” the jury was informed by the court that if the stone was shipped in time, “or” if i't was shipped in the proper method, defendant would have no cause to complain, and no right to recover damages. Of course, if this was what the court intended, or what the jury might have understood from the instruction, it was erroneous, because it was plaintiff’s duty, by the terms of his contract, to ship the stone at the time required thereby, and in the specified method, and properly cut. But this was a mere verbal error in no way prejudicial to defendant, for, taking the whole charge together, there is no possible question that the jury was in any way misled. The same may be said with reference to the other portion of the instructions which defendant singles out and complains of to the-effect that defendant could recover on his counterclaim, if entitled to recover at all, such sum as he necessarily expended by reason of his men being laid off, or by reason of their having to do other kinds of work. The objection to this is that it takes from the considera
If counsel deemed those instructions misleading, or likely to prejudice his client’s cause before the jury, the attention of the court should have been called to the matter, so that the mistake — ■ for it was nothing more than a mistake — could have been corrected before the jury retired. Such was the firmly-established practice in this state for years prior to the passage of Laws 1901, c. 113, dispensing with the necessity of taking exceptions, and should continue to be. Prior to the passage of that act, and when exceptions were necessary to be taken in order that alleged errors might be reviewed on appeal, an exception to either portion of the charge here complained of, without specifically pointing out the particular objection urged against it, would have been wholly unavailing. The legislature did not intend by the passage of the act of 1901 to abrogate the former practice in this respect, or to permit litigants to single out, after the trial of an action, isolated, portions of the charge of the court, and secure a new trial for some technical error or mistake which could have been corrected had attention been called to it at the trial; and counsel should still perform their duty to the court, and call attention to obviously unintentional misstatements and verbal errors in the charge to the jury, that the same may be corrected, if they are deemed at all likely to be misleading. Of course, this does not apply to instructions on some controlling proposition of law, but to such misstatements of fact or technical inaccuracies in matters of law or fact as are often likely to creep into a charge orally delivered to the jury.
Appellant contends that the verdict of the jury was a great injustice to him, that the evidence is clearly and palpably against it, and that it should be set aside. We have examined the evidence with care; it is very voluminous; and find no reason for disturbing the verdict on this ground. It has been approved by the learned trial court, and its judgment on this subject is of great
The order appealed from is affirmed.
Continue your research
- Minnesota cases applying the 'clearly and palpably against the evidence' standard to jury verdicts on appeal
- Cases on foundation requirements for trade custom evidence — distinguishing personal-knowledge basis from general market practice
- Cases on counsel's duty to object to jury instruction errors during trial and effect of Minnesota Laws 1901 ch. 113 on exception-taking practice
Case-law data current through December 31, 2025. Source: CourtListener bulk data.