Peet v. City of East Grand Forks
Can I rely on this case?
Yes — no negative treatment found
- —
Analysis generated from citing opinions in this archive. Not legal advice.
Peet v. City of East Grand Forks
Opinion of the Court
This case presents another phase of the litigation which has resulted from the attempt of the city of East Grand Forks to grade its public
In 1902 P. H. Thornton entered into a contract with the city of East Grand Eorks to grade, macadamize, and curb its streets. The contract covered five pieces of work, and provided that each piece should impose a separate obligation on Thornton, independent of and without reference to any other part of the work. This writing constituted five separate contracts. According to the terms of the general contract and the plans and specifications, the character of the work and the kind of material required to be used were particularly specified, and the contractor’s compensation fixed at a definite price per cubic yard for excavation, a definite price per square yard for paving, and a definite price per lineal foot for curbing. A party by the name of Lawson was named as engineer and charged with the general supervision of the work, and upon his monthly estimate of the work performed the city agreed to pay Thornton. Thornton entered upon the performance of contract No. 3, made extensive excavations, and performed other acts in execution of the contract, and the engineer issued to him an estimate of the amount and value thereof. This estimate was presented to the city council, and by that body approved; but no warrant was issued for its payment, because there was no money in the city treasury available for that purpose. Thornton then abandoned the work and assigned and transferred the estimate to "William E. Beet, who is the respondent in the present action.
In an action by Peet against the city the defense was interposed that Thornton, having abandoned his contract and refused to complete the same, was not entitled to recover for the work performed, and, further, that the work so far as it had progressed was not in accordance with the contract, or plans and specifications. The trial court found as a fact that the work to where abandoned was in all respects in substantial compliance with the contract, and that the failure of the city to pay the amount of the estimate at the time provided by the contract justified Thornton in abandoning the work.
The present action was commenced by Peet to recover upon the engineer’s estimate issued under contract No. 1 which covered a piece of work to be performed under the general contract above referred to. The amount certified by the engineer to be due was $11,-I01.'84, and the action was brought by the assignee of the contractor to recover this amount. The city interposed the defense that the contractor had failed to substantially perform his contract in the respect pointed out in the answer, and that the estimate was fraudulently issued by the engineer with full knowledge and connivance of the contractor. The case was tried without a jury, and the court found both defenses true, but ordered judgment in favor of the plaintiff for the difference between the amount certified and the damage found to have been occasioned to the city by the failure of the contractor to substantially perform his contract. On appeal to this court the judgment was reversed. Peet v. City of East Grand Forks, 101 Minn. 523, 112 N. W. 1005. The case was then retried, and the questions whether Thornton was justified in abandoning the work, and whether the work actually done was substantially done as required by the contract, were submitted to the jury, which found in favor of the plaintiff on both issues, and rendered a verdict against the city for $11,432.93. The present appeal is from an order deny
As originally drawn the complaint stated a cause of action upon the contract. After the case was remanded, the court, upon the application of the plaintiff and over the objection of the defendant, allowed the complaint to be amended so as to,‘ it is claimed, allege the right to recover upon a quantum meruit, and to allege a waiver by the city of strict performance, and also facts justifying the application of the doctrine of equitable estoppel. As we read the original and amended complaints, there is little, if any, substantial difference between them; but, however that may be, the error, if any, in allowing the amendment, is not assigned as error, and cannot be considered.
The claim that the city is estopped, or waived its right, to assert that the contract was not strictly performed requires no consideration, because it was taken from the jury. As stated by the appellant in its brief, the court instructed that “there was no question of waiver or estoppel in the case.”
The issues presented were thus clearly defined, and were submitted to the jury under instructions which correctly stated the law. The jury were told that the city claimed that Thornton had abandoned the work without cause, and that in so far as the work was done it was not done in substantial performance of the contract. Whether the contract was abandoned without cause was left for the jury to determine, with the instructions that “failure by defendant city to make payment according to the terms of the contract and the city charter, whether it had had available funds or not, was a breach of the contract on its part, and justified an abandonment of the work by the contractor.”
The question whether the work so far as performed was substantially as required by the contract was also properly submitted. The evidence is quite conclusive, and need not be reviewed. We have read it all carefully, and think that it fully justifies the finding of the jury. The court instructs that: “Substantial performance of a contract is had when a contractor gives the other party to the contract in substance what he bargained for. The rule as to the substantial performance of a contract, where of necessity the owner of
But the appellant contends with much earnestness that the estimate of the engineer was fraudulent and did not represent the honest judgment of that official, and that the doctrine of substantial performance is not therefore available to the plaintiff. That would be true if it was shown that Thornton was a party to the fraud, and that the fraud affected the work actually done. Fraud in inducing the making of the contract would not necessarily prevent the contractor from collecting for work actually done in good faith under the contract and in substantial performance of the contract according to its terms; but, if there is a wilful or fraudulent failure to strictly perform the contract as actually made, the contractor cannot claim the benefits of the equitable doctrine of substantial] per
The judgment is affirmed.
Reference
- Full Case Name
- WILLIAM F. PEET v. CITY OF EAST GRAND FORKS
- Cited By
- 2 cases
- Status
- Published