Hamlin v. Lanquist & Illsley Co.

Minnesota Supreme Court
Hamlin v. Lanquist & Illsley Co., 111 Minn. 491 (Minn. 1910)
127 N.W. 490; 1910 Minn. LEXIS 749
Laggard

Can I rely on this case?

Yes — no negative treatment found

Based on 1 citing opinion

Analysis generated from citing opinions in this archive. Not legal advice.

Hamlin v. Lanquist & Illsley Co.

Opinion of the Court

Per Curiam.

The intestate of. plaintiff and respondent was employed by defendant and appellant in the construction of the new courthouse building in Duluth. Various crews of men were employed. The defendant insists that every member of these crews had a foreman or boss in ■charge of them. Deceased, according to defendant, was foreman of the crew here involved. The jury found otherwise. Pie must be here regarded as merely a member of the structural iron crew, in which work he had been engaged for years previously.

Defendant used certain large steel derricks. Each derrick had two stiff-legs, composed of timbers designed to hold the mast rigid and in an upright position. The mast and boom were equipped with the usual lines, blocks, pulleys, etc. The heel of each of these masts, when erected, rested in a steel socket or hole in a casting which tended to keep the mast from slipping sideways. Steel goosenecks were arranged at the top of each mast, through which wire cables were passed. These cables were brought down and wrapped around the steel framework of the building upon which the derrick stood. By the use of turn buckles these cables were set and fastened into position by means of these stiff-legs and cables. Defendant also provided certain dogs or clamps, which could be fastened over the heels or bottom of the masts, which had a tendency and whose function was to assist in holding the mast in position and to prevent *494tlie bottom of tbe mast from kicking ont of tbe socket or hole.. These clamps were sometimes used and sometimes not at all. The derricks were moved from place to place as the work progressed. They remained in one place until the work of raising steel for two floors-was done. They were then moved up two floors, and so on.

Immediately prior to this accident the derrick in question, was set up by the crew of iron workers of which deceased was a member, and it must be assumed for present purposes not its foreman. Anderson, the head foreman of the iron workers’ crew, was present at various times while this derrick was being put up. The derrick was set up. The dogs or clamps provided by defendant were not used. While defendant’s servants were lifting a portion of the lower derrick and placing it in position, the mast of the lifting derrick slipped out of position — i. e., out of its socket — and fell down, causing the deceased to fall. From the effects, he subsequently died. At this time the building was partially constructed. The derrick was oh the fifth floor, some sixty-five feet above the ground. There was no floor between what was known as the fifth and third floors. There was conflict of testimony as to whether there was any lashing of the mast on this derrick. The jury returned a verdict for plaintiff.

This appeal was taken from the order of the trial court denying defendant’s usual motion in the alternative.

1. The first question presented by the record is whether the trial court should have directed a verdict for defendant. It is clear that on this point the trial court ruled correctly.

The court charged in part that if the witness whose testimony appears in the record called the attention of Anderson, the head foreman, to a movement in the mast which indicated that something was-wrong in the arrangement- and operation of the derrick, and Andei’son went above to see about it, and the condition and situation were such that in the exercise of ordinary care Anderson would or should have seen a defect, and in the exercise of ordinary care would or should have remedied the same, “then you can find that the defendant was guilty, although at the time the derrick was put up it was in a proper and safe condition for operation.” The record justified the *495instruction. It follows that the trial court properly refused to direct judgment for defendant notwithstanding the verdict.

2. The question then arises whether a new trial should have been granted because the court charged the jury: “It was the duty of the defendant to exercise ordinary care in seeing to it that this derrick was properly equipped and like care in keeping it in a reasonably ■safe condition,” and because the court refused to charge that, “when a master has furnished proper and reasonably safe appliances for the work to be done, his personal duty does not extend so far as to require him to attend to the proper regulation and adjustment of the parts of the implement or machine, and if an accident occurs because of a want of care on the part of the men erecting or adjusting said machinery, the master is not liable.” There were other requested and refused instructions to the effect that the work of erecting the derrick under circumstances here presented “was part of the details of the work of construction,” and that under .the circumstances the negligence of the servants erecting the derrick was the negligence of a fellow servant, for whose negligence defendant who had provided the clamps Avas not responsible.

On this point the members of the court do not agree. A majority of the court are of the opinion that under the circumstances of this case, the height of the building and the size and weight of the derrick, it (the derrick) Avas an appliance Avhich the master undertook and was required to furnish completely set up and ready for use in a safe condition, and in this respect differed from a scaffold and most other temporary appliances, as to the construction and sufficiency of which the servants are required to exercise a discretion and assume the risk of each other’s negligence. Blomquist v. Chicago, M. & St. P. Ry. Co., 60 Minn. 426, 62 N. W. 818; Carlson v. Northwestern Tel. Exch. Co., 63 Minn. 428, 65 N. W. 914. Therefore the trial court correctly instructed the jury it was defendant’s duty to exercise ordinary care in seeing to it that this derrick was properly equipped and like care in keeping it in the same condition.

Dissenting Opinion

Laggard, T.,

(dissenting.)

One of three rulings governs this case:

First. There is no doubt as .to the general principle that a master must indemnify a servant who is injured by the negligence of a co-servant, when the delinquency consisted in a failure to discharge properly either the function of furnishing the instrumentalities with which the business is carried on or the function of keeping those instrumentalities up to the legal standard of safety while they continue to be used. 2 Labatt, Master and Servant, §§ 566, 567. And see Brown v. People, 81 Vt. 477, 71 Atl. 204, 22 L. R. A. (N. S.) 738.

Second. “If the master supplies suitable material for the construction of an appliance which he is not obliged, and has not undertaken, to furnish in a completed state, and the workmen themselves construct it according to their own judgment, the master is not liable for the manner in which they used the materials thus supplied.” 2 Labatt, Master and Servant, 1778, 1779, § 614. And see 10 Current Law, 716; 12 Current Law, 696.

Third. In view of the extreme danger of the work at a great height and with a narrow footing, of the complexity of the operations involved, the presence and necessary co-operation of many individuals so situated that independent action on their respective parts would render the place of work perilous, of the restricted opportunities of the servants to observe the imperfect condition of the completed instrumentality and of related 'circumstances, the master may be required to formulate rules governing the conduct of its employees or to supervise the erection of or to inspect the instrumentality, and may be held responsible for a failure to perform such duty.

The majority opinion places this case in either the first or third of these classes. Upon the particular record here presented to this court, it seems to me that this case does not come within either. It does not come within the first, because a breach by a servant of the general duty of the master to exercise due care in the matter of furnishing to his servant a reasonably safe place for his work is neither necessarily nor universally the negligence of a vice principal. It does not come within the third class, because, although the complaint *497does charge the master’s failure to supervise, the case was not actually tried nor actually submitted upon this issue. Whatever the result might have been upon different evidence and upon a substantially different charge, the record actually presented to us shows, in my opinion, that the familiar principle of the second class of cases controls.

There are many cases in which this principle has been applied to derricks under circumstances more or less similar to those in the case at bar. While these authorities vary greatly in their significance for present purposes, their result in the aggregate is strongly for defendant’s contention. See Holden v. Fitchburg, 129 Mass. 268, 37 Am. Rep. 343; McKinnon v. Norcross, 148 Mass. 533, 20 N. E. 183, 3 L. R. A. 320; McGinty v. Athol, 155 Mass. 183, 29 N. E. 510; Jenkinson v. Carlin, 10 Misc. 22, 30 N. Y. Supp. 530; Cregan v. Marston, 126 N. Y. 568, 27 N. E. 952, 22 Am. St. 854; Marvin v. Muller, 25 Hun, 163; Kennedy v. Jackson, 12 Misc. 336, 33 N. Y. Supp. 630; Kelly v. Jutte & Foley Co., 104 Fed. 955, 44 C. C. A. 274. And see Phoenix Bridge Co. v. Castleberry, 131 Fed. 175, 65 C. C. A. 481; Weeks v. Scharer, 111 Fed. 330, 49 C. C. A. 372; Kinncar Mnfg. Co. v. Carlisle, 152 Fed. 933, 82 C. C. A. 81; Peters v. George, 154 Fed. 634, 83 C. C. A. 408.

The decisions of this court also lead to the same conclusion on the issues as actually presented by this record. Eicheler v. Hanggi, 40 Minn. 263, 265, 41 N. W. 975; Jennings v. Iron Bay Co., 47 Minn. 111, 113, 49 N. W. 685. And see Lindvall v. Woods, 41 Minn. 212, 42 N. W. 1020, 4 L. R. A. 793; Fraser v. Red River Lumber Co., 42 Minn. 520, 44 N. W. 878; Fraser v. Red River Lumber Co., 45 Minn. 235, 47 N. W. 785; Hefferen v. Northern Pacific R. Co., 45 Minn. 471, 48 N. W. 1, 526; Ling v. St. Paul, N. & M. Ry. Co., 50 Minn. 160, 52 N. W. 378; Corneilson v. Eastern Ry. Co. of Minn., 50 Minn. 23, 52 N. W. 224; Oelschlegel v. Chicago Great Western Ry. Co., 73 Minn. 327, 76 N. W. 56, 409; Bell v. Lang, 83 Minn. 228, 86 N. W. 95.

It is true that the decision in Woods v. Lindvall, was repudiated in the federal courts. 4 U. S. App. 49, 48 Fed. 62, 1 C. C. A. 37. And it is sometimes insisted that it has not been followed in the sub*498sequent decisions in this state. On careful examination of the various cases, however, it will be found that its principle has been logically restricted to appropriate facts, and that so far as it is involved under the present circumstances the substance of the rule remains. It would unreasonably prolong this opinion to set forth the detailed examination of all the cases in this regard, except as will hereinafter appear. As to Lindvall v. Woods, see its review in Blomquist v. Chicago, M. & St. P. Ry. Co., 60 Minn. 426, 62 N. W. 818, and in note to 4 L. R. A. (N. S.) 228.

The specific authorities to which plaintiff refers do not lead to a change of the conclusion. The rule itself was applied in Attix v. Minnesota Sandstone Co., 85 Minn. 142, 88 N. W. 436 (in which the boom of the derrick was defective; the master had not supplied the proper materials); in Swanson v. Oakes, 93 Minn. 404, 101 N. W. 949 (in which the “chock” corresponding to the clamp in the instant case had not been in fact provided); and in Costello v. Frankman, 97 Minn. 522, 524, 525, 107 N. W. 739 (the “high bridge” case, in which the court said of the negligence of the master that “it amounts to a failure to provide proper appliances for the work to be carried on”).

In the case at bar the master was not negligent under the rule. He supplied proper material and proper appliances. In Blomquist v. Chicago, M. & St. P. Ry. Co., 60 Minn. 426, 62 N. W. 818, the master was held liable on the ground that he had withdraivn all discretion from the men composing the derrick crew as to when and how the derrick should be erected, and had invested the foreman with full power to devise plans for the strict and complete control of the whole matter. Por his negligence the master was held responsible. Note to 4 L. R. A. (N. S.) 229. In the case at bar the place, plan, and manner of putting up the appliances had not been so delegated to any person selected by the master.

In Borgerson v. Cook Stone Co., 91 Minn. 91, 95, 97 N. W. 734, men were placed and required to work upon different levels. To avoid obvious and necessary perils required the supervision of some competent person. The person selected by the defendant was the *499foreman of the deceased. For his negligence it was held that the defendant was responsible. The court said, at page 96 of 91 Minn., page 736 of 97 N. W.: “The mutual relations of other servants than the foreman involved risks and hazards that, in connection with the work to be done, required general supervision by one person, and this person was the foreman who had been selected by defendant. His authority was general, and involved risks which were not assumed by plaintiff, and for his negligence the defendant was responsible to the same extent as if defendant were present and directing the work himself.” In the case at bar defendant undertook to show, but — it must be here assumed — did not succeed in showing, that plaintiff was the foreman of the gang in question. The absence of supervision, though alleged in the pleading, was not, according to the charge, an issue. The Borgerson case is not controlling in any view. As previously pointed out in this case, the issue as to supervision, although raised by the complaint, was not involved in the charge of the trial court.

In Perras v. A. Booth & Co., 82 Minn. 191, 84 N. W. 739, 85 N. W. 179, the gist of the negligence was the act of the foreman in removing one of the instrumentalities used in the performance' of the work without notice or warning to the servant. Thereby the place of performance was rendered dangerous and unsafe. In consequence the servant was killed. The question whether the foreman was a fellow servant or vice principal- was for the jury. The facts in the case at bar bear no significant analogy. Here, indeed, the absence of supervision is pleaded as negligence, was not the subject of charge, and was not properly regarded one of the issues in the case.

The strongest case for plaintiff urged upon our attention is Carlson v. Haglin, 95 Minn. 347, 104 N. W. 297. The plaintiff was at work on a platform some seventy feet above the ground. In making a necessary change in the same, one of the supports, called “ledger boards,” broke from defects thereon, precipitated a number of employees to the ground, who were instantly killed, and injured plaintiff. While in that case the servants were “ordinary workmen, with *500no special knowledge of the duties of constructing tbe platform or any exigencies arising in the progress of tbe work” (Lovely, L, at page 350 of 95 Minn., page 298 of 104 N. W.), in this case plaintiff was an experienced and expert workman. There the master left it to the employees to select the material; here the master provided proper material and adequate appliances. There the duty of the master to inspect was a material consideration; here it was not litigated. That case does not distinctly repudiate the general rule which had been formerly adopted by this court and as has been here stated. It must be regarded as depending largely upon the particular facts there presented. Some of the same considerations dispose of Hagerty v. Evans, 87 Minn. 435, 92 N. W. 399, in which the-scaffold was not a temporary appliance.

On the other hand, Gittens v. William Porten Co., 90 Minn. 512, 97 N. W. 378, is not especially significant for defendant. While the instrumentality which did the damage was a derrick, the circumstances were substantially different. The damages complained of were caused by a hoist “simple in design and easily made.” No part of the material was furnished for its construction. No particular class of workmen was selected by the master to select the timber or ■construct the hoist.

It follows that under the authorities generally, and of this court in particular, the failure to use the clamp was not a mere detail of the work, and that plaintiff is not within the fellow servant rule.

Defendant has raised other objections which fail to justify reversal. It is but just to add that defendant did not strenuously urge the assignments of error addressed to contributory negligence and assumption of risk.

Affirmed.

Reference

Full Case Name
CHARLES E. HAMLIN v. LANQUIST & ILLSLEY COMPANY
Cited By
1 case
Status
Published