Fortier v. Skibo Timber Co.
Can I rely on this case?
Citation treatment has not been reviewed for this case. The notes below come from the citation graph and the Minnesota Revisor's amendment records, not from a review of how later courts treated this decision.
(as of 9/30/2026)
Last cited by a Minnesota appellate court in 1928, among the opinions in this site’s citation index.
Not a substitute for Shepard’s or KeyCite — verify before relying.
See our Terms of Use before relying on these notes. Report an error
Cases that cite this one
4 later published cases cite this decision.
- Itasca Cedar & Tie Co. v. McKinley (Minn. 1914)
- Tiedt v. Larson (Minn. 1928)
- Carnegie Dock & Fuel Co. v. Midland Lumber & Coal Co. (Minn. 1921)
- Owen v. J. Neils Lumber Co. (Minn. 1914)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
This was an action to recover a claimed balance of the purchase price of logs sold and delivered to defendant under a contract. The logs were shipped by rail to defendant. The only dispute between the parties was the correct measurement or scale of the logs so shipped. The contract for the purchase, which was embodied in
To the order denying a new trial the learned trial judge attached a memorandum, from which we quote the following: “The dispute is over the scale of certain logs covered by contract between the plaintiff and the defendant. Practically it comes to the question whether the jury were at liberty to take the measurement of Morin in preference to that of Gorman. Perhaps neither was quite satisfactory. Morin had veiy little experience. Gorman had very
1. The provision in the contract for the taking of the measurements by a man deputized by the surveyor general of logs did not bind the parties to accept his measurements as final and conclusive.. Nelson v. Charles Betcher Lumber Co., 88 Minn. 517, 93 N. W. 661. The correct scale was, therefore, a question for the jury under the evidence, without reference to fraud or bad faith by either party. The jury was instructed: “The scale bills made * * * by the surveyor general’s office are prima facie evidence of the correctness of the scale stated in them.” This was the most defendant could claim for the measurements made by Cameron and Hyatt, so that the question of fact whether or not the measurements made by Morin and the plaintiff establish the incorrectness of the defendant’s claim and the accuracy of plaintiff’s claim was directly presented, and,, of course, was for the jury, if under the evidence reasonable men might draw different conclusions. The forceful and exhaustive arguments presented by counsel for defendant convince us that the-competency of Morin was very doubtful at least; but his ineompetency does not appear so conclusively that we would feel justified in setting aside' the judgment of the trial court upon this question. Meyers v. McAllister, 94 Minn. 510, 103 N. W. 564. There were, in addition to Morin’s testimony, many circumstances proper for the jury to take into consideration in arriving at their verdict. We have quoted at length from the memorandum of the learned trial judge for the purpose of demonstrating how very far it would be necessary for this court to go in determining the questions of fact in order to reverse the order denying a new trial. We conclude that the evidence was sufficient to sustain the verdict.
The order denying a new trial is affirmed.