Samels Lumber Co. v. Kropf
Samels Lumber Co. v. Kropf
Opinion of the Court
Action to foreclose a mechanic’s lien in which defendant had judgment, from which plaintiff appealed.
It appears from the evidence and findings of the trial court that on April 24, 1908, defendant entered into a contract with one .Kropf for the construction of a school building at Jordan, this state. The contract price for the building completed was $28,980. The contractor agreed by the terms of the contract to furnish all labor and material employed or used in the work of construction. Between May 20 and October 14, 1908, plaintiff, a corporation, sold and delivered to Kropf, the contractor, lumber and material -to be, and which was, used in the construction of the building, and of the aggregate value of $496.29, no part of which has ever been paid. On February -5, 1909, plaintiff made and filed in the office of the register of deeds of Scott county its claim for a lien upon the premises on which the building was constructed, and thereafter brought this action to foreclose the same. The last item of material was furnished by plaintiff on October 14, 1908. The lien statement was not filed until February 5, 1909. It was not, therefore, filed within the time provided for by statute, and plaintiff must fail in the action, unless its contention that it in fact furnished other material subsequent to the date named, and within ninety days from the date on which the statement was filed he sustained.
The facts in reference to this claim, as appears from the stipulation of facts, are as follows: During the negotiations for lumber and material for the construction of the building, the contractor and Frank A. Saméis, president and manager of plaintiff, visited the offices of the Eddy Lumber Company, at Minneapolis, “and there it was agreed that said last-named company would furnish certain of said lumber, and ship the same to the contractor, and charge the same to said plaintiff. At the same time A. W. Eddy, the manager of said Eddy Lumber Company, was requested to ascertain from the Nelson Sash & Door Company the sum for which they would furnish said mill work. * * * That thereupon said Eddy Lumber Company obtained figures from said Nelson Sash & Door Company some days subsequent, and made known the same
The last item of material so furnished was upon November 12, 1908. And if this material is to be treated as having been furnished by plaintiff, because of the fact that its manager was instrumental in securing the same jointly with the contractor, and the fact that the price thereof was, without authority from either party, charged to plaintiff upon the books of the Nelson Company, then it is probable that plaintiff’s lien statement was filed in time. The trial court found that this material was not furnished by plaintiff, and this finding is assigned as error.
We are unable from the record to discover, within the rule guiding this court, grounds for overturning the findings of the trial court upon this question. Though there is no controversy as to the evidentiary facts, the ultimate fact was for the trial court to determine. Plaintiff was in no manner interested, as surety or otherwise, with the contractor, nor responsible for the faithful, performance of the contract. The Eddy Lumber Company had no express authority to direct the Nelson Company to charge the account to plaintiff; and though it was so charged, and plaintiff notified of the fact by the Nelson Company, yet, when the time of payment arrived, ■plaintiff protested that the bill had been charged to it, without authority, and that it was not liable therefor. The bill was in fact
Judgment affirmed.
Reference
- Full Case Name
- SAMELS LUMBER COMPANY v. ADOLPH KROPF and Others
- Status
- Published