Seastrand v. D. A. Foley & Co.
Can I rely on this case?
Citation treatment has not been reviewed for this case. The notes below come from the citation graph and the Minnesota Revisor's amendment records, not from a review of how later courts treated this decision.
(as of 9/30/2026)
Last cited by a Minnesota appellate court in 2024, among the opinions in this site’s citation index.
Not a substitute for Shepard’s or KeyCite — verify before relying.
See our Terms of Use before relying on these notes. Report an error
Cases that cite this one
16 later published cases cite this decision.
- Olson v. Synergistic Technologies Business Systems, Inc. (Minn. 2001)
- Wunder v. Wunder (Minn. 1932)
- Klass v. Twin City Federal Savings and Loan Ass'n (Minn. 1971)
- Youngstown Mines Corp. v. Prout (Minn. 1963)
- St. Paul Hospital Workers Health & Welfare, Inc. v. Bethesda Lutheran Hospital (Minn. 1963)
- Roske v. Ilykanyics (Minn. 1951)
- Hillyard v. Smither & Mayton, Inc. (D.C. 1950)
- In re Estate of Stratman (Iowa 1942)
- Twenty Associates, Inc. v. First National Bank & Trust Co. (Minn. 1937)
- Kubat v. Zika (Minn. 1932)
- Faltis v. Berkner (Minn. 1923)
- W. G. Reddingius Co. v. Enkema (Minn. 1923)
- Seastrand v. D. A. Foley & Co. (Minn. 1922)
- Hoven v. Leedham (Minn. 1922)
- Nelson v. Rohweder (Minn. 1920)
- David Carl Hepfl v. Jodine Patrice Meadowcroft (Minn. 2024)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
The complaint alleges: In 1912 Aitkin county let a contract to defendant for the construction of a drainage ditch. Defendant was to excavate 158,545.06 cubic yards of earth, at 13 cents a ouibic yard, with stipulated amounts for bridges and othér work, making the total consideration $25,526.86. Defendant sublet the work to plaintiff, -at 9% cents a cubic yard for excavation, and the same stipulated price for bridges and other work, the consideration amounting in the aggregate -to $20,-324.14. Defendant further agreed to pay plaintiff for excavation of extra yardage required to be done by the engineer in charge 9y2 cents per cubic yard. During the progress of the work the engineer directed plaintiff to perform certain extra work, and this extra work, computed on the terms of plaintiff’s contract, amounted to $5,589.68. The county could pay, under the drainage law, for extra work, a sum not in excess of ten per cent of the original contract price. The county paid to the defendant the price specified in its contract with defendant plus ten per cent, and, in addition thereto, the sum of $600.27. Defendant paid plaintiff the price stipulated in the contract between them and -also all but $32.52 of the ten per cent that defendant received from the county for extra work. Plaintiff had, therefore, performed extra work for which it had not been paid of the value, at the price stipulated in his contract, of $3,069.54,
Thereafter the legislature of Minnesota passed a law, chapter 269, page 406, Laws of 1917, under which the county was empowered, but not required, to make payment for the unpaid portion of said extra work, and, on November 24, 1917, the county paid to defendant the sum of $4,307.13, making the full value of said extra work. This action was brought to recover from defendant the sum of $2,436.75, the balance of the value of the extra work, computed at the price per yard specified in plaintiff’s contract with defendant. The court sustained a demurrer to the complaint, holding that it failed to state a cause of action.
'The trial court was of the opinion, as indicated by a memorandum filed, that the judgment in the former action, denying the right of plaintiff to recover more than the amount above stated, is res adjudicata, and on that ground sustained the demurrer to the complaint.
The best considered modem cases adhere to this broad view. In Highway Commissioners v. Bloomington, 253 Ill. 164, 97 N. W. 280, Ann. Cas. 1913A, 471, it was said that the obligation arises not from consent, as in the case of contracts, but from the law or natural equity. None of the elements of a contract are present. The intention of the parties is entirely disregarded, while in contract, express or implied, intention is of the essence of the transaction. In the case of contracts the agreement
There has been some disposition to narrow the application of this form of action and to limit it to the eases to which it has previously been applied. See, for example, Sergeant v. Stryker, 16 N. J. Law, 464, 32 Am. Dec. 404. But we will do well not to restrict the scope of a remedy which was intended to relieve against the too narrow procedure of the law. The remedy is now neither legal nor equitable, since under the code neither legal nor equitable remedies longer exist, but in its inception it was regarded as equitable in spirit, Dresser v. Kronberg, 108 Me. 423, 81 Atl. 487, 36 L.R.A.(N.S.) 1218, Ann. Cas. 1913B, 542, as resembling a bill in equity, Osborn v. Bell, 5 Denio, 370, 376, 49 Am. Dec. 275, as an action at law, equitable in nature, Northrop's Exr's. v. Graves, 19 Conn. 548, 50 Am. Dec. 264. As above stated, it is not necessary that there be contract, privity or promise. It is not necessary that the party from whom defendant received the money intended it for plaintiff’s benefit. Brand v. Williams, 29 Minn. 238, 13 N. W. 42.
Order reversed.
Case-law data current through September 30, 2026. Source: CourtListener bulk data.