George C. Lauer Stone & Construction Co. v. Armour & Co.
George C. Lauer Stone & Construction Co. v. Armour & Co.
Opinion of the Court
In the construction of buildings forming its packing plant in South St. Paul, defendant required, as necessary building material, large quantities of- crushed rock for use in the concrete part of the work. - Plaintiff was the owner of a stone quarry a few miles north of South St. Paul where the material could be had. Negotiations between the parties resulted on August 13, 1918, in a lease of the quarry with equipment to defendant for such time as might be necessary from the operation thereof to produce the material in the quantity required. In consideration of the grant defendant agreed to pay plaintiff: (1) Twelve and one-half cents per cubic yard for all stone removed; and (2) to loan plaintiff $10,000 to enable it to pay off and discharge certain liens and encumbrances which were a menace to plaintiff’s title and future ownership of the quarry. Defendant thereafter entered into the possession of the property and continued the operation thereof until some date in June, 1919, when the work was temporarily suspended, being again resumed in the month of September following. Defendant fully complied with the terms of the contract by paying the stipulated compensation for the stone removed, and loaning to plaintiff the agreed sum of $10,000; there was no breach of the contract in either respect. During the period when work in the quarry was suspended, and on July 18, 1919, plaintiff pre
Thereafter, on January 10, 1920, plaintiff brought this action to recover the increased rent demanded by the notice just referred to, for the period from July 23 to the commencement of the action, alleging in the complaint that the term of the lease had expired prior to the date of the notice and that defendant’s subsequent retention of the quarry was as a holdover tenant, and at the increased rent demanded.Defendant by answer joined issue upon the question whether the lease had terminated -as claimed by plaintiff; also upon the further question whether the failure of defendant to surrender the premises in response to the notice exposed it to the greater liability demanded. ,At the close of the trial -a verdict was directed for defendant on the ground t-ha;. its leasehold rights had not expired by abandonment, consent of parties or otherwise, therefore that the notice to quit or pay more rent was unauthorized, hence ineffectual for 'any purpose. Plaintiff -appealed from an order denying a new trial.
The action is founded on the theory that the term of the lease had expired at the time the notice to quit was served, and that, by thereafter retaining possession of the property and failing to return it to plaintiff, defendant by implication of law is deemed to have accepted the conditions imposed and therefore liable for the increased rent. If the theory that the leasehold term had ended at the date of the notice be sustained by the evidence, defendant’s liability for the greater rent is clear. Gardner v. Board of Co. Commrs. of Dakota County, 21 Minn. 33; Moore
We find from the record no evidence to justify the conclusion that the term of the lease had expired, either by lapse of time, by abandonment or by the failure of defendant promptly to prosecute the work in getting out and removing the material, nor evidence which would justify a submission of the question to -a jury.
The lease provides in clear language that the term thereof should continue for such period as might be necessary to enable defendant, by the exercise of reasonable diligence, having due regard to economy in handling and using the same, to quarry, crush and ship the required quantity of material to the scene of the building operations. The undertaking in which defendant was engaged was an extensive one and large quantities of this class of material were necessary, to be used from time to time as the construction work progressed. Necessarily the parties contemplated that the time necessary for the purpose would 'be indefinite and extend over a considerable period. There was no unnecessary delay by defendant. The quarry was promptly taken over and no claim is made of unreasonable or other delay during the time the operations were under way. The suspension from June to September is not shown to have been unwarranted or unnecessary, and no conclusion of abandonment can be predicated thereon. Defendant was not required by the lease to continuously operate the quarry, and, under the liberal terms and provisions thereof, neither court nor jury could find that a failure to do so was a breach of the contract. Defendant had not at the date of the notice taken out enough material for its use, and the claim that some representative of the company had stated to plaintiff without qualification that defendant was through with the quarry is not sustained by the facts disclosed. There were some negotiations or attempted negotiations between the parties during the time work at the quarry was shut down looking to a possible relinquishment of rights under the lease. But nothing came of them and defendant resumed operations in September. In this state .of the facts, of which the record leaves no room for fair doubt, defendant’s rights under the lease had
Order affirmed.
Reference
- Full Case Name
- GEORGE C. LAUER STONE & CONSTRUCTION COMPANY v. ARMOUR & COMPANY
- Status
- Published