Ford v. St. Louis, Keokuk & Northwestern Railroad
Ford v. St. Louis, Keokuk & Northwestern Railroad
Opinion of the Court
Plaintiff is a subcontractor, and sues for work and labor done in grading and constructing the roadbed of the defendant railroad company. The original contractor is made a codefendant. Judgment is prayed against him, with- a, lien on the property of the defendant railroad company. ' The answer of the railroad company is a general denial. The original contractor also files a general denial, and alleges further that the work sued for was done under a contract which plaintiff- broke, thereby causing loss and damage to said defendant, for which he prays judgment after crediting what would be due plaintiff under the contract.
Under the agreement thus made, the work sued for was begun by plaintiff, and, according to the evidence, was carried on until its further completion was prevented by an overflow of the lands, which did not subside until after the thirtieth of June. According to defend
Among the declarations of law given by the court on behalf of the plaintiff was the following, to wit: “If the court, sitting as a jury, believes from the evidence that the final agreement between Ford and Quigley was that Ford should be paid nine and one half cents per cubic yard -for all the earthwork done by him, then the court must.allow for said work at said rate, deducting only for payments made and sundries furnished.” This instruction, having been drawn apparently upon the phase of the ease presented by plaintiff’s testimony, should have been confined to the inferences- justly arising therefrom. The evidence of plaintiff in reference to his being allowed to quit, and receive pay for the work so far as done, did not, by fair construction, tend to show that he was to be allowed to do some inexpensive surface work and thereafter cease at will and get pay at the contract price for the work thus done. According to plaintiff’s testimony on this point, in the event he was unable to do the whole work in the time limited in the contract, he was to be paid for such portions as he had been able to complete up to that time,, and the uncompleted parts were .to be taken back by the defendant. According to this view, plaintiff was
No error was committed by the court in refusing to permit appellant to ask his witnesses the following question: ‘‘State whether or not there is a custom among railroad contractors that all contracts for the grading of railroads are upon the implied condition, that the right of way is secured by the railroad company and that the railroad company establish the grade in time; and, if there is such a custom, state whether it is general, uniform and certain, and of such character that all engaged in such business are presumed to have knowledge of it?” Witnesses are not legal experts. Nor is it permitted them to state that certain facts create a legal presumption. It . is for the law, not witnesses, to define presumptions. For this reason the question was objectionable in form and properly excluded. The law applicable to contracts for constructing the roadbed of a railway is announced in the case of Hammond v. Beeson, 112 Mo. 190.
For the error pointed out in the foregoing instruction, the judgment in this case will be reversed and the cause remanded.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.