Missouri Court of Appeals · Decided February 13, 1900 · Bland
83 Mo. App. 204; 1900 Mo. App. LEXIS 152

Fidelity & Deposit Co. v. Colvin

Opinion of the Court

BLAND, P. J.

The petition in substance alleges that the plaintiff is a Maryland corporation, but doing business and having an office in the city of St. Louis, Missouri, where it is engaged in the general surety business; that in April, 1896, at the request of one J. W. Neal, it executed a bond as surety for said Neal to C.E. Simmons, conditioned that said Neal would erect a certain building in the city of St. Louis, for said Simmons, according to certain plans and specifications; that said Neal failed to erect said building, and that plaintiff, to save itself as the surety of said Neal and by his written consent, completed said building; that in September, 1896, plaintiff entered into a written contract with defendant Oolvin, whereby Colvin, in consideration of $780 to be paid to him, contracted and agreed to furnish all the material and do all the work necessary for doing the painting and glazing of said building according to specifications; that Colvin and defendant Jackson for a consideration, executed and delivered to plaintiff their certain bond (sued on), in the penal sum of $800, conditioned for the faithful performance of Colvin’s painting and. glazing contract made with plaintiff. Eor breaches of the conditions of this bond plaintiff alleged that Colvin failed to perform his contract, failed to do all the work, or to furnish all the material necessary for the completion of his contract, but after partially completing said work and after having received from plaintiff $375 on account of work done on said contract, he quit and abandoned the work and left it in an unfinished condition; that to complete said work the plaintiff was compelled to, and did pay out for material *208and labor tbe sum of $695.07 over and above tbe contract price agreed between it and Colvin, that the total cost of said work and labor was tbe sum of $1,173.07, and prayed judgment for tbe penalty of said bond and for execution for its actual damages, $695.07. With tbe petition was filed an itemized account of tbe cost in material and labor for the glazing and painting. Tbe answer of defendants, omitting caption, is as follows:

“Now comes said defendants, leave of court first being bad and obtained, and for their amended answer to tbe amended petition of plaintiff, deny each and every allegation and averment therein contained, except such allegations as are hereinafter specifically admitted.”

Further answering tbe defendants allege:

“That defendant Colvin did on or about tbe first day of September, 1896, submit to plaintiff a proposition to do tbe painting and glazing of a certain three story store and flat building of one C. F. Simmons, then in tbe course of erection on tbe south side of Clark avenue in tbe city of St. Louis, Missouri, for tbe sum of $780, which proposition was accepted by plaintiff, and that, at about said time tbe defendants executed to plaintiff a bond in tbe sum of $800 for tbe faithful performance of said proposition by tbe said Colvin. Defendants admit that said Colvin did not complete tbe work he offered to do under tbe terms of said proposition; but allege that the reason of bis failure to complete said work, was because of plaintiff’s wrongful refusal to‘ allow him to complete said work, and further allege that plaintiff failed to put said building in condition so that- said Colvin could perform said work according to tbe terms of said proposition, and so failed and refused to keep its part of tbe agreement, entered into between said Colvin and plaintiff, that plaintiff was prevented from completing said work.
“And now having 'fully answered, defendants asked to be discharged with costs.”

*209Colvin admitted that plaintiff paid him $375 on account of the work done on his contract, and that he owed $370 (one of the items in plaintiff’s account), for glass used in the glazing of the building. Plaintiff’s testimony was to the effect, that after Colvin abandoned his contract, it completed the painting and glazing of the building at a cost of $695.07 over and above Colvin’s contract price, including the $370 glass account. On the part of defendants the evidence, and the apparent weight of the evidence is, that on Saturday, December 19, 1896, Colvin and his men were locked out of the building by Seibold, plaintiff’s superintendent; that Colvin finding himself locked out notified his workmen to réturn on Monday morning, saying he would see for what reason he was locked out; that on the following Monday morning, before Colvin appeared at the building, Seibold employed George. Meyers as foreman on the painting of the building, and then sent Meyers to Colvin with instructions to tell Colvin not to return. Meyers carried out his instructions from Seibold, and Colvin did not thereafter return or offer .to complete the work, which he says was seven-eighths done when he was notified to quit. Seibold denied that he locked Colvin out, or that he sent word to him not to return to the building. The court, among other instructions to the jury, gave the following one on behalf of defendants:

“2. The jury are instructed that although they may believe from the evidence in the cause that Colvin, without being first ordered so to do by the witness Seibold and without just cause or excuse, abandoned the contract entered into between him and the plaintiff, before the completion thereof, still unless it further appears by a preponderance of the evidence in the cause'that- plaintiff has sustained a damage by reason of such abandonment, their verdict shall be for the defendants.”

The jury found the issue for -the defendants. Plaintiff *210filed a motion to set aside the verdict and to grant a new trial, which was by the court sustained. After an unsuccessful motion to set aside the order granting a new trial defendants appealed.

The bond sued on is a penal one, conditioned that Colvin should comply with and faithfully execute his contract. If there was any breach of the bond plaintiff was entitled to recover, at least nominal damages, independent of any evidence that substantial damages had been sustained. Any breach of the bond was an invasion of plaintiff’s legal right entitling it to an action and the recovery of some damages. Sutherland on Damages, p. 13, n. 3; State to use v. Plass, 58 Mo. App. 148; Fulkerson v. Eads, 19 Mo. App. 620. Instruction number 2, given for defendants, was clearly-erroneous, and the court ruled correctly in granting a new hearing on account of this erroneous instruction, unless it clearly appears from all the evidence that the plaintiff was., not prejudiced by the instruction. To arrive at such a conclusion we should be bound to find that the verdict of the jury could not be supported on any other theory than that the jury found that Oolvin had a just cause to abandon his contract, and that as to this fact, the evidence was substantially all one way. We are not able to so state, for the jury might have found from Colvin’s testimony that seven-eighths of the work was done when he abandoned his contract; that the plaintiff could and should have finished the work at a cost not exceeding the balance that would have been due on Colvin’s contract had he finished the work. We are bound to indulge the presumption that, the court ruled correctly in granting the motion for a new trial. Indulging this presumption in the light of all the testimony, we can not say that the court erred, and affirm the judgment.

All concur.