Clapper v. Mendell
Clapper v. Mendell
Opinion of the Court
The petition in this case declared on a Quantum meruit to recover an indebtedness alleged to be due the plaintiff for materials furnished and work done by him at the request of the defendant in building' a house, and the sum for which judgment was prayed was $451.45.
The allegations show that it was originally intended to enforce a mechanic’s lien against the property, but for some reason this purpose was abandoned and only a money judgment insisted on.
The answer set up a special contract alleged to have been made by the parties by which the plaintiff
The evidence of both sides showed that contracts were made by the parties as alleged in the answer, but the evidence for the plaintiff tended to prove that changes and alterations were made in the progress of the work by order of the defendant, which entailed considerable additional outlay on the premises for which he was to receive extra payment, and also that both the materials and work done and furnished by him were good.
The evidence for defendant, on the contrary, tended to sustain the statements of the answer in regard to the inferior quality of the work and materials and also the averment as to the amount which had been disbursed by the defendant, either in payment to plaintiff in person or for bills contracted by him.
The question on this appeal is as to the propriety of the rulings of the trial court on the instructions •which were given and refused, and without setting them all out in this opinion, for they were quite numerous, we state that several which were offered by both parties seem to have been carelessly drawn and either ignored
When buildings or other improvements have been placed on the property of another by a contractor, even though there was a special contract between the parties which the contractor did not perfectly comply with, he is entitled to recover the reasonable value of the improvements, not to exceed the contract price, because of the benefit rendered to the owner, and this has been the law in this State throughout its history. Thompson v. Allsman, 7 Mo. 531; Yeates v. Ballentine, 56 Mo. 530; Moore v. Gaus, 113 Mo. 98.
The trial court instructed the jury on that theory, but failed to submit clearly to them the right of defendant to be credited with payments he had made and to recover -on his counterclaim to the extent the jury might find he had made it good. The first and second instructions given at the request of plaintiff will illustrate the errors to which we refer.
‘ ‘ 1. The court instructs the jury if they find from the evidence the work and labor mentioned in plaintiff’s petition, and the materials described therein, were furnished and that defendant used, possessed and enjoyed the same, and still is in possession and enjoyment of the same, then you should find for the plaintiff, notwithstanding you may believe from the evidence plaintiff may have failed to comply with his special contract with defendant, in such sum as the real value of the work and material as shown by the evidence, together with six per centum per annum from the date of the institution of this suit, to-wit, March 6, 1901, and if any work required by the contract between plaintiff and defendant was not done, or was done in an imperfect manner, a proportional deduction should be made from the contract price, but if the jury should believe from the evidence that after plaintiff and defendant had made said contract
“2. If the jury shall believe from the evidence that the defendant employed plaintiff to do the work and furnish the material necessary for the building, plastering and painting of defendant’s house mentioned in the evidence and that plaintiff did said work and furnished said material, then plaintiff is entitled to recover in such sum as you may find from the evidence to be the fair and reasonable value of said work and material not to exceed the contract price.
“But if the jury should believe from the evidence, that after plaintiff and defendant had made said contract defendant directed plaintiff to make changes in said house as first contracted for and agreed to pay plaintiff for making such changes and the plaintiff made such changes as directed by defendant, then in addition to the above they should allow plaintiff the reasonable value of the additional labor and materials, if any, caused by such changes, and in whatever sum you should find for the plaintiff you should add interest at the rate of six per cent per annum from the institution of this suit, viz., March 6, 1901.” '
As has been said, there was evidence tending to prove that considerable extra work was imposed on plaintiff during the progress of the job by changes which the defendant ordered and also evidence tending to prove the latter had made large payments to- • ward satisfying his indebtedness to plaintiff and that he had sustained damage by reason of defective work
A request for the following charge submitting that theory was made by the defendant and refused:
“The court instructs the jury that if they believe*48 from the evidence that the plaintiff was to do and perform said work in good and workmanlike manner, and furnish in the construction of said building good and first-class material, and if you further find from the evidence that said work was not done in a good and workmanlike manner, and that the material furnished was not good and first-class, and that the defendant was damaged by reason thereof, you must find for the defendant in such sum as you may believe he is damaged not to exceed two hundred dollars.”
No charge equivalent to that one was given and it is plain, therefore, that the defendant was not accorded the full benefit of his counterclaim.
The judgment is reversed and the cause remanded.
Reference
- Full Case Name
- MERIT CLAPPER v. DAVID MENDELL
- Cited By
- 1 case
- Status
- Published