Moline Plow Co. v. Hartman
Moline Plow Co. v. Hartman
Opinion of the Court
Plaintiff sued on this contract:
“ Warbensburg-, December 2, 1879.
4 4 It is hereby agreed between Hartman and Markward of this place and Moline Plow Company, of Kansas City, both of the state of Missouri, that the parties of the first part agree to pay the second named party the sum of two thousand and sixty-eight dollars and fifty-eight cents, upon the completion of the following named changes in their mill in the above named place, viz: Change the separator to a number one (1) receiving separator and furnish one (1) bevel core gear, ten (10) foot shaft; two (2) babbit boxes, two (2) collars, one (1) pulley and frame of sufficient size and capacity to drive smutter, and take the wabble out of the fly wheel, finding all freights and work to make these changes. These-signatures are annexed to the within agreement in the-presence of witnesses.
44H. W. Clark,
44 J. W. Young,
4 4 Hartman & Markward, “Moline Plow Company,
“H. E. G-ates, Agent.”
It alleged a performance of the contract on its part- and a refusal of performance on the part of defendants, admitted a payment of $1561.04, and prayed judgment for balance and for all other proper relief.
The answer admitted the execution of the contract, and says, that on said day defendants agreed to pay plaintiff the sum of two thousand and sixty-eight dollars and fifty-eight cents, when the plaintiff had done the-work and made the changes mentioned in the written instrument sued on; and had furnished defendants a separator with interchangeable sieves and one new run of stones ; had refunded to defendants the sum of twenty
Defendants asked the court to submit the trial of the cause to a jury, which was refused. They then prayed the court to submit issues to a jury, and these issues were accordingly submitted: “1. Did plaintiff, at or before the contract sued on was signed, agree to furnish defendants a separator with interchangeable sieves, one new run pf stones, to refund to them twenty dollars for running their elevator through their mill, and to pay defendants the sum of $42.79, before expended by
The jury answered by their verdict “ yes,” as to the first and second issues, and next, “We, the jury, find the value of a new run of stones to be one hundred and seventy-five dollars, and we, the jury, find that there was no evidence introduced to show the value of a number one receiving separator with interchangeable sieves ; and we also find a bill of off-sets for defendants to the amount of $134.75.” Here defendants prayed the court to submit the further trial of the cause to a jury, which the court refused to do. The court then heard additional evidence, and entered a decree reforming the contract in accordance with the finding of the jury, and found that the difference in value between the stones plaintiff was, by the contract to furnish, and a defective set which the court found plaintiff had furnished, and defendants were using, was sixty dollars, and rendered judgment for plaintiff for two hundred and twenty-five dollars, being the $507.54 sued for, less the items found by the said jury, excepting the one hundred and seventy-five dollars, for which the court substituted its finding of sixty dollars, as the difference in value of the two sets of stones, and less, also, twenty-five dollars, which the court found to be the value of the “interchangeable sieves.”
The right of trial by jury wa» not i©s$ by t&© filing of an equitable answer. R. S., secs. 3600, 3602; Wolf v. Schaeffer, 4 Mo. App. 367; 74 Mo. 164; Carter v. Prior, 78 Mo. 222. But it seems that all the Issn&s w®i?s sub
The judgment should be reversed and the cause remanded.
Reference
- Full Case Name
- The Moline Plow Company v. Hartman
- Cited By
- 1 case
- Status
- Published