Bill in equity, begun in the circuit court of the city of St. Louis, by the plaintiff, to enjoin the defendant from obstructing and interfering with the former’s easement or right of way across the latter’s railroad track at or near Seanlan avenue in the city of St. Louis.
A trial was had which resulted in findings and a decree for plaintiff, enjoining the defendant from further obstructing said way; and after defendant’s motion for a new trial was overruled by the circuit court, the latter duly appealed the cause to this court.
The facts are few and practically undisputed. The plaintiff is a corporation organized and incorporated •under the laws of this State, and is engaged in the manufacture and sale of brick in said city.
The plant of the plaintiff is located in the southwestern portion of the city, near the river Des Peres, <on the west side of said railway track, near the western end of Seanlan avenue. Said track, in that vicinity, runs in a southeasterly and northwesterly direction, and then runs practically east and west. Scanlan and Fyler avenues run east and west, with Bradley avenue between and paralleling them.
The right of way across the defendant’s tracks was obtained by plaintiff from defendant, for a valuable consideration by a deed in regular form, dated October 22, 1902. It conveyed to plaintiff a certain tract of real estate situate in said city, lying immediately south of Fyler avenue, together with the afore
“The said party of the first part also grants nnto the party of the second part, its successors and assigns, permission to cross over its railroad tracks at or near Scanlan avenue, with the privilege to drive over its land lying between Fyler avenue and Scanlan avenue, until such time as a street or highway may be established and opened in that vicinity across its railroad, thereby giving and securing to them as direct and convenient ingress and egress to- and from the property conveyed as is hereby granted.”
The deed was executed in behalf of defendant by Mr. C. H. Beggs, its vice-president; and the evidence showed that Mr. Beggs, together with Mr. C. D. Purdon, defendant’s engineer, conducted the negotiations which resulted in this deed and grant, and that the conveyance itself was prepared by counsel for defendant upon instructions from Mr. Beggs.
The evidence showed that on or about August 1, 1908, defendant obstructed plaintiff’s right of way by placing barriers along the .sides of its tracks at or near Scanlan avenue and by maintaining cars at that point and by removing the materials which formed the driveway across the tracks; and that defendant threatened, notwithstanding a demand on the part of plaintiff that it cease so doing, to continue such obstruction and interference.
Defendant admits that on October 22, 1902, “plaintiff purchased and acquired from defendant, for use in its business of manufacturing, selling and dealing in brick, that certain piece, parcel or tract of land lying and being in the city of St. Louis, Missouri, described in plaintiff’s petition, and that in connection with the purchase and acquisition of said piece of property, plaintiff also acquired from defendant permission to cross defendant’s railroad tracks, at or near Scanlan avenue and Fyler avenue in said city.” Also
Defendant further admits that on or about August 1, 1908, or at .some time prior thereto, it obstructed plaintiff in the exercise of said easement and that it still continues so to do, “thereby preventing-plaintiff from driving across the same.”
In justifying its conduct in obstructing plaintiff’s easement, the answer pleads that, pursuant to an ordinance of the city of St. Louis, defendant received permission and authority from the city to carry Fyler avenue over its tracks, by the erection of a bridge, with suitable abutments and retaining walls, and that said bridge was opened at some time prior to August 1, 1908, and that by means of such bridge plaintiff is afforded “direct and convenient ingress and egress to and from its said property. ’ ’
The evidence shows that prior to October, 1902, the defendant had formulated plans for using this tract of land for yard and roundhouse purposes; also that Fyler avenue and Frisco avenue, the latter paralleling defendant’s track on the east, were at all times mentioned, public streets duly established and used as such; and that on Fyler avenue crossing-planks had been laid between the rails of defendant’s tracks and on the outside thereof, for the purpose of facilitating vehicles in crossing .the same at that point.
From October 22, 1902, the date when plaintiff acquired said right of way over defendant’s tracks, the physical situation in the vicinity under consideration had not changed a particle until up to August 1, 1908, the date when the defendant obstructed said way of the plaintiff, except in the meantime the former had erected an elevated bridge over Fyler avenue, in pursuance to the ordinance mentioned in
The distance from plaintiff’s plant to its easement or way across the defendant’s tracks, at Scanlan avenue, was considerably shorter than-was the distance to the elevated bridge, constructed by defendant at Fyler avenue; the witnesses testified, from two to five blocks; also that distance nearer the market for its brick. The grade of the road to the Scanlan crossing, the easement right of way, was a much better and easier grade than the one leading to. Fyler avenue crossing, notwithstanding one short, steep grade in the former. It was generally used by the teamsters, because of that fact, and because it was the more convenient route.
The survey of this route, made by Julius Fitzman, an engineer, together with the profile drawings on the same, show that the drive over the bridge is not only longer, but a long, steep grade, practically all the way, and less convenient for plaintiff.
By this reading the terms of the grant of the right of way it will be seen that it is impressed with a condition subsequent composed of two provisions, namely: first, that it should continue until such time as a street or highway might be established and opened in that vicinity; and, second, thereby giving and securing the plaintiff as direct and convenient ingress and
The question before ns for determination is, has this condition subsequent been fulfilled? If that question is to be answered in the affirmative, then the decree of the circuit court enjoining the defendant from obstructing the right of way of the plaintiff must be reversed and the bill dismissed; but if it is to be answered in the negative, then the decree of the circuit court must be affirmed.
We will consider the two elements of the condition in the order stated.
Attending the first: Has a street or highway been established and opened in that vicinity since the grant was made?
That question must be answered in the negative. In fact, there is not a scintilla of evidence preserved in this record tending to show that fact; but upon the contrary the undisputed evidence conclusively shows that the physical conditions in that vicinity had not changed a particle since the date of the grant of the way to plaintiff down to the date of its obstruction by the defendant, except the latter constructed an elevated bridge over its tracks at Pyler avenue, which the greater weight of the evidencé shows was about eight hundred feet out of plaintiff’s way in hauling its brick to market.
The construction of this bridge is the only shadow of justification defendant makes for obstructing plaintiff’s way, and that is made upon the theory that the building of said elevated bridge was equivalent to the establishment and opening of a highway within the terms of the grant of the way to plaintiff.
That contention is wholly untenable. The construction of the bridge was neither in the letter nor spirit of the grant.
We therefore decide this against the defendant.
That is almost conclusively shown by the fact that the teamsters generally use the Seanlan avenue route in preference to the bridge route.
Moreover, the survey and drawings made by Mr. Pitzman, a competent engineer, showing the physical conditions and supported by the weight of the testimony of the eye-witnesses, leaves but little doubt as to the fact that the granted way was much more direct and convenient for the plaintiff than was the bridge route; and we therefore answer the second question in the negative.
Entertaining these views, we are of the opinion that the findings and decree of the circuit court were correct, and should be affirmed.
It is so ordered.