Yazoo & Mississippi Valley Railroad v. Neal
Yazoo & Mississippi Valley Railroad v. Neal
Opinion of the Court
delivered the opinion of the court.
The agreed statement of facts shows that in June, 1906, E. E. and E. N. Neal instituted two suits against the railroad, company, under section 4058, Code 1906 (section 3561, Ann.
This case is controlled by the case of Railroad Co. v. Odeneal, 74 Miss. 827, 21 South. 52. This suit was a pending suit from the date of judgment to the date it was settled on December 4, 1906, and, while this appeal was pending no other suit could have been instituted. No sufficient time had elapsed after the settlement of the suit in which to give the railroad company an opportunity to repair this stock gap.
It is further contended by appellee that, by the terms of the agreement of compromise, the railroad was only released up to the 20th day of July. We find nothing in the agreement between the parties to justify us in adopting this view. The whole settlement between the parties was reduced to writing, and concludes as follows: “Plaintiff agrees to accept two hundred and fifty dollars in full satisfaction of all damages arising out of the failure to construct and maintain said cattle guards up to this date.” This agreement bears no date whatever, and seems to have been used as a voucher by the parties making the
Reversed and dismissed.
Reference
- Full Case Name
- Yazoo & Mississippi Valley Railroad Company v. Ralph E. Neal
- Cited By
- 1 case
- Status
- Published
- Syllabus
- Hailroads. Code 1906, § 4058. Cattle guards and stock gaps. Second penalty. Suit for. Under Code 1906, § 4058, providing a civil penalty against a railroad company lor failing to maintain proper stock gaps and cattle guards where its track passes through enclosed land:— (a) A recovery by a plaintiff precludes a suit for a second penalty until the railroad company has had a reasonable time thereafter to repair the stock gap or cattle guard; and (c) An undated writing, evidencing a compromise, of such a suit, reciting that plaintiff accepted a sum of money therein named in full satisfaction of all damages because of the company’s failure, speaks from the date payment is received and the writing signed, as regards the time within which another suit may not be brought, although it was agreed upon sometime before.