J. J. White Lumber Co. v. McComb City Turpentine Co.
J. J. White Lumber Co. v. McComb City Turpentine Co.
Opinion of the Court
delivered the opinion of the court.
This is an appeal from a decree of the chancery court of Pike county, Hon. Bobert B. Mayes, special chancellor. The appellee, McComb City Turpentine Company, complainant in the court below, filed its bill, claiming, among other things, that the appellant, J. J. White Lumber Company, defendant below, leased to appellee, through Carr Bros., for turpentine purposes, six thousand, nine hundred and thirteen acres of merchantable pine f timber, suitable for turpentine purposes, for which it paid appellant twenty-five thousand, fifteen dollars and eighty cents, and that appellant failed to deliver the quantity, six thousand, nine hundred and thirteen acres of pine timber as contracted; that the shortage in the delivery amounted to one thousand, four hundred and eleven acres, which was a breach of the contract — and seeking' to recover the purchase price and damages of appellant therefor. The lumber company, defendant below, answered, and, among other things, contended that appellee could not recover for the alleged shortage of one thous- and, four hundred and eleven acres, for two reasons: First, that as a matter of fact, under the contract of lease, there is no shortage of one thousand, four hundred and eleven acres, or any amount whatever, and if there be any shortage at all, it is inconsiderable; second, that the •contract of lease is a contract “in bulk” or “in gross,” and that the shortage or variation, if any, is allowable to the lessor, under the contract here involved. There was a decree in favor of appellee as to the shortage of one thousand four hundred and eleven acres, and for other damages claimed in the bill, and appellant prosecutes this appeal. We here set out the material parts of the contract involved,: ,,
This contract and agreement made and entered into in duplicate this the 27 day of October, A. D. 1905, by and between the J. J. White Lumber Company, a corporation existing under the laws of the state of Mississippi,
Sec. Acres,
S Yz of S % 22 120
S V2 of S y> WW of NE"l4, SW 14, W % of SE %, and 23 150
SE % of SE % 25 340
All on section 26 480
All on section = 27 520
sy2 of NE 14 S Vo 28[ 400 28$
E i/o of SE % 29 80
SE % 31 50
S Vo 32 200
All on 33 630
N y> and N y> of SE 14 N y> of NW % of SW 14 N y2 and N y> of S W SW % of SW 14 and S y9 of SE % 34| 360 34$ 35l 560 35$
W y> of N y. and* S % of NW % SW % of NE 14 and N % of SE 14 All in Township One (1) North of 36[ 360 36$
Range Six- (6) East, Amite county, Miss.
Township One (1) North of Range 7 East, Pike County, Mississippi. N % of NW % and SW U of NW % 1 120
NE % of NW %, E % of NW % of NW % 12 50 Township One (1) South, Range Six (6) East, Tangipahoa Parish Louisiana.
S i/o of NE %, E y2 of NW Ni, and E y2 2] of W y> of NE % [ 400 'SW %, NW y4. of SE U 2J
16 E % of SW % of SE % 3
40 SE % of NE % and NE % of SE % 9
220 NE i/4, S 1/0 of NW Ni, and NW 1/4 of SW % 10
40 'SW % of NW 1/4 and NW 1/4 of SW % 11
W i/2 of N % 4 50
N y2 of NE- % and S % of SE % 5 60
All in section 37 437
W y, of NW % 6 40
NW % of NW %, N 1/2 of SW % of NWi/4 and SE % of NE and fraction of SE i/4 165
N i/2 of NW 1/4, SW 1/4 of NW 1/4, and fraction of SW y." 8 122
Ninety acres on the N y2, N and W sides Township Ohe (1) South, Range Six (6) East, St. Helena Parish, Louisiana. 38 90
Lots 1, 2 and 3 1 70
And fractional' NE corner of the George Gordon section 55 to make 90 acres with lot 1 of 1 90
Fraction. E y> of NW % of NE 1/1 and NE % of NE % 12 40
Fractional SE corner 56 20
Fractional east side section 37 143
—being in all approximately six thousand, nine hundred and thirteen acres of timbered land.
It is understood and agreed by this contract,
First. That the term merchantable pine timber shall mean any pine tree of sufficient size to square not less, than four inches (4") by four inches (4").
Second. That the parties of the second part hereby pay unto the party of the first part the sum of five thous- and dollars ($5,000.) to bind this contract, receipt whereof is hereby acknowledged, the balance or deferred payments to twenty thousand, fifteen & S0/100 ($20',015.80) r making the total amount to be paid for the lease of the-aforesaid lands for turpentining purposes at the rate of three dollars and sixty cents per acre, to be paid by the parties of the. second part to the party of the first part on or before the first day of December, A. D. 1905.
Third. For the above consideration the party of the first part conveys and warrants to the parties of the second part their heirs or assigns the right to enter upon said lands, to box, work and use for turpentine purposes the aforesaid pine timber for the purpose of producing and manufacturing resin and spirits of turpentine for the full end and term of three (3) years from the date of entry thereon as hereinafter provided or until the third crop of turpentine is gathered from the said pine timber.
Fourth. It is agreed and understood that the party of the second part shall not commence operation upon said land before the first day of January 1907, and may box for turpentine purposes not more than fifteen hundred acres (1500) of said timber each year or turpentine season during the life of this contract, except that should the parties hereafter agree to use more or less of said timber each year, the same shall be agreed to in writing. Provided, however, that on January the first, 1910, that the said party of the first part shall have the right to proceed
Fifth. The party of the first part shall on or before the first day of November in each year, locate and designate the land upon which the pine timber shall be turpentined for the first time during the next twelve months and furnish to tire parties of the second part, abstracts of the title to said lands and maps showing the location of said land.
Sixth. It is the purpose of this contract to allow the parties of the second part to take the turpentine from the pine timber on said lands for three (3) consecutive years, In such locations as will be convenient for the party of the first part to cut and manufacture the pine timber so turpentined at its saw mill plant at McCoimb City, Mississippi, as soon after the termination of the turpentine period of three (3) years as is practicable.
Seventh. The party of the first part agrees to allow the parties of the second part and hereby conveys to them the right to erect, construct and locate stores, storehouses, turpentine distilleries and other buildings necessary to be used in gathering, storing or manufacturing the turpentine and resin products gathered from said lands on the lands owned by the party of the first part, .and to remove or sell for purpose of removal of said "buildings or other fixtures at or before the termination ■of this contract, and the party of the first part further grants unto the parties of the second part to cut wood, "building and barrel timber from its said lands necessary to be used in the manufacture and barreling the turpentine or resin products that are gathered from the aforesaid land, and the rights granted in this section shall be free from cost to the parties of the second part.
* * *
Twelfth. The parties of the second part, their heirs or assigns shall have the right to assign or transfer this
Thirteenth. In consideration of the foregoing" covenants and promises and the consideration paid and to be-paid, the party of the first part hereby warrants and defends and will during the term of this contract and lease, warrant and defend the parties of the second part in the possession of the above-described land and premises.
In witness whereof, the parties to this contract and lease have hereunto set their hands and seals in duplicate-this 24th day of October, A. D. 190-5.
J. J. White Lumber Company.
By J. J. White, Pres. [Seal],
J. A. Carr, for Carr Bros.
Attest: H. L. White, Sec.
The record in this case is voluminous, and we have-given it-a careful examination and patient consideration. We find it necessary, in order to properly construe the contract here, to take into consideration the circumstances, and surroundings of the parties at the time the lease was agreed upon. The appellee wanted to lease the pine timber for turpentine purposes. The appellant lumber company had about eight; thousand, three hundred acres of land lying scattered in two counties in this state and two parishes in Louisiana, upon which stood merchantable pine trees suitable for turpentine purposes. Mr. Carr, appellee, testified that just prior to entering into-the contract:
“They represented to me that they had something like about eight thousand acres of land there in Amite and Pike counties, and in St. Helena and St. Tammany parishes, which contained something like six thousand* nine hundred acres of timber.”
The lower court arrived at the shortage of one thousand, four hundred and eleven acres of timber by the survey made by Clark and Ball, employed by appellee. Clark testified as to the survey, and said that he had not surveyed the timber, hut surveyed the old fields and swamps, and* arrived at the amount of shortage in this way; and that he surveyed and included “only virgin timber,” leaving-out of his survey all other timber regardless of size, or
After an exhaustive study of the contract and evidence,, and the authorities bearing on the questions involved, we are firmly convinced that the able chancellor erred in his finding against appellant for the one thousand, four hundred and eleven acres under the terms of the contract in this case. There is no escape from the conclusion that, the contract includes all merchantable pine timber suitable for turpentine purposes, regardless of whether it be virgin timber, cutover timber, old field timber, swamp timber, or 4x4 timber, on the eight thousand, three hundred acres of land. The surveyors Clark and Ball, for appellee, testified that they left out of their survey all of the merchantable pine timber suitable for turpentine purposes, except the “virgin timber.” This was wrong. The contract does not specify “virgin timber.” This being true, there was no way for the chancellor to determine, from the eviden.ce before him, how much timber was left out by appellee’s surveyors in their survey; and, being unable to say how much of the six thousand, nine hundred and thirteen acres is short, if any at all, and the burden of proof being on the complainant below to prove its case, the chancellor certainly could not rightfully decree
We hold, also, from the whole record in this case that the contract of lease is a contract “in gross,” or “in bulk,” and that no recovery can be toiaintained for the shortage or variation here, if any, it not amounting to deception or fraud, in the quantity of timbered land. Am. & Eng. Ency. Law, vol. 20, p. 875; Phipps v. Tarpley, supra; Kerr v. Kuykendall, 44 Miss. 137; Tyson v. Hardesty, 29 Md. 305; Hurt v. Stull, supra; Oaks v. De Lancey, 133 N. Y. 227, 30 N. E. 974, 28 Am. St. Rep. 628; Pen
In view of these conclusions, the case is reversed as to that part of the decree for the one thousand, four hundred •and eleven acres of timber, and the claim dismissed, and in all other respects is affirmed.. Let all the court costs be •assessed equally against appellee and appellant.
Reversed and affirmed in part.