Tatum v. Garrett
Tatum v. Garrett
Opinion of the Court
delivered, the opinion of the court.
Per Curiam. Affirmed.
ON Suggestion oe Error.
Appellant suggests that the decision of this case may affect other suits pending between the appellee and W. 0. Tatum, son of appellant, and for that reason this court should have written an opinion, giving its reasons for affirming the judgment of the court below.
The case was affirmed because we believed that the trial court did not err in directing the jury to find for the plaintiff below. Appellee was employed by appellant to bore an experimental oil well. The price to be paid was agreed to before the work began. Several
Appellant’s son testified that appellee refused to deliver this,book, and he refused to pay him. the balance due; that the delivery of the book w.as a material part of the consideration for the contract. It appears that this book contained valuable information to geologists, and would largely control their advice as to whether or not appellant -would be justified in boring other wells in that vicinity; that if an expert should, after an examination of the data recorded in the book, advise further borings-,-appellant might have followed his advice, and might have won a fortune, dr, on the other hand, he might have sunk a small fortune in a hole in the ground. The record shows that appellee refused to deliver the book, as stated by appellant’s son; but it also shows that appellee offered to give appellant a copy of the book. The record also shows that the book itself was tendered, after this suit was brought, and appellant refused to accept same. This suit was brought by appellant to recover for the agreed price of his labor.
We think that the offer of a copy of the book was a substantial compliance with the contract, and the tender of the book itself was a complete compliance. It is also a matter of doubt whether the failure to deliver
Overruled.