United States Fidelity & Guaranty Co. v. Tate County

Mississippi Supreme Court
United States Fidelity & Guaranty Co. v. Tate County, 114 Miss. 1 (Miss. 1917)
74 So. 769
Smith

United States Fidelity & Guaranty Co. v. Tate County

Opinion of the Court

Smith, C. J.,

delivered the opinion of the court.

The rule announced in Armfield v. Nash, 31 Miss. 361, followed in Williams v. Luckett, 77 Miss. 394, 26 So. 967, and relied upon by counsel for appellee, has no application here; for, while Clarke’s compensation for working the roads was to be paid him in installments, his work upon the roads was not to be performed by installments, but was to be continuous, so that his obligation under the contract was not divisible, but was entire. When he unqualifiedly refused to continue to work the roads, and appellee, as it ha'd the right to do, treated his refusal as a total breach of the contract, and made other arrangements for the working of its roads, his contract with appellee was thereby terminated, and appellee had thereafter only a cause of action against him for the damages sustained by it because of the breach by him of the contract. It had the right to sue upon this cause of action at once, or at any time thereafter, within the limits of the statute of limitations, and recover all damages then or thereafter to be sustained, but had not the right to institute separate suits for each new item of damage resulting from its original cause of action; for “it is a rule of law that a man shall not be twice vexed for one and the same cause.”

“The true criterion whether damages can be recovered for nonperformance of a whole contract, including damages not sustained when the action is brought and -the suit is tried, is whether there has been such a breach as authorizes the plaintiff to treat it as entirely putting an end to the contract. If the breach is entire and total, the plaintiff may recover damages for an entire nonfulfillment; but if it is only partial and temporary, he can recover only such damages as he has already sustained, and must still accept performance of the re*4sidue of the contract if the other party will fulfill it. The question depends upon whether the damages are a new cause of action, or are only new damages resulting from the original cause of action.. In the former case a new action may and must be brought, while in the latter all the damages may and must be recovered in a single action.” 8 R. C. L. 550.

See, also, 3 Elliott on Contracts, section 2141; Roehm v. Horst, 178 U. S. 1, 20 Sup. Ct. 780, 44 L. Ed. 953.

It follows, from the foregoing views, that appellant’s plea of res adjudicata was good; and, since the matters alleged therein appear from the record and are admitted by counsel for appellee to be true, the judgment of the court below will be reversed, and the cause dismissed.

Reversed and dismissed.

Reference

Cited By
2 cases
Status
Published
Syllabus
Judgment. Res judicata. Entire cause of action. Where a road contractor, contracted with a county to work its roads for a term of two years, hut abandoned his contract and refused to carry it out and the board of supervisors notified his bondsmen, requesting them to carry out the contract which they refused to do and the contract was then relet' to the lowest bidder, who carried it out, and the county recovered judgment against the original contractor's, bondsmen for the amount of money which the county paid the second contractor for one year’s work over that agreed to be paid the first contractor, such judgment was res judipata of the county’s rights in the premises and the county could not bring a second suit for the failure of the first contractor to perform his contract for the second year, since the contract for working the roads for two years called for continuous work, not work to be performed by installments so that the original contractor’s obligation was entire, not divisible, and on his failure to perform, the county had the right to recover all. damages then and thereafter to be sustained, but it had no right to bring separate suits for each new item of damages resulting from its original cause of action. .....-, a rule of law that a man shall not be twice vexed for one and the same cause.