R. T. Clark & Co. v. Miller
R. T. Clark & Co. v. Miller
Opinion of the Court
delivered the opinion of the court.
(After stating" the case as above.) It is true, as contended by the revenue agent, that the positive refusal to perform a contract is a breach of it, although the time for performance has not arrived, The Law of Public Contracts (Donnelly), section 304, p. 435; but the mere assertion of a party to a contract that he ivill be unable, or will refuse, to perform his contract is not sufficient to constitute a breach. There must be a distinct, unequivocal, and absolute refusal to perform, treated and acted upon as such by the other party to the contract. A mere assertion of inability to go on with the contract is not a repudiation of the contract. The intention to abandon the contract at some future date is not a breach of it unless such intention is declared in positive terms and unconditionally. When it is so declared, the other
The negotiations between the contractors and the levee board, bearing on the question, cover a period of something like two or three months of the first part of the year 1918, and, while they wore going on, the contractors were proceeding with the work under their contract — never stopping, nor expressing any intention of abandoning the work, unless, and until, they were overtaken by bankruptcy. On the contrary, they gave the levee board to understand that they would continue the work as long as their creditors would permit them, although it was thoroughly understood by both parties that, if the prevailing prices of labor and materials going into the work, brought about by the World War, continued, bankruptcy would ensue. There is no other reasonable interpretation that can be put upon the orders and resolutions of the levee board, taken in connection with the other evidence in the case, than that the increase of fifty per cent, in the contract price was granted by the levee board in order to insure against the contractors ’ abandoning their contract at some future time. The increase, therefore, was not in recognition or acceptance of a breach of the con
The record shows that the unfinished levee work was emergency work — necessary to be completed without delay in order to prevent disastrous floods from the Mississippi river. It is true that R. T. Clark & Co. were perfectly willing to abandon the contract if agreeable to the levee board, but the levee board was not willing for them to do so. Conditions were such that if the contract had been breached and the Guaranty Company had paid the levee board the full penalty of its bond, one hundred sixty thousand dollars, the levee board had no assurance that the contract for the work could be relet at the original price plus one hundred sixty thousand dollars, the proceeds of the bond. On the contrary, judging from the evidence in this record, the indications were that a re-letting of the contract would have resulted in an increase of more than fifty per cent, of the original contract price. In other words, viewing the situation as it existed, at the time, it appeared to the levee board that the best interest of the district required that R. T. Clark & Co. carry out their contract instead of breaching it, and to that end they seem not to have left anything* undone.
The facts and circumstances relied on by the revenue agent as constituting a reletting of the contract, do not show a reletting, but instead a method adopted which the
There seems no escape from the conclusion that everything that was done by R. T. Clark & Co. and the levee board, relied on by the revenue agent as constituting a breach of the contract, and the reletting of the contract, was done by agreement between the parties. There is no such thing known to the law as the breach of a contract by agreement of the parties.
The revenue agent contends that there was a dissolution of the firm of R. T. Clark & Co., two of the members going out of the firm, and a reletting of the contract to a new firm with the same name but with different partners, and for those reasons the contract was breached. We do not think there is any merit in that contention. The evidence shows that one of the partners, Dulaney, had never entered upon the work, and, after the work began, another, Cheshire, dropped out, because his equipment necessary to do the levee work had been taken from him by his creditors. The other partners proceeded with the work without objection from the levee board, carrying on the work for and on behalf of the partnership. There was no dissolution of the partnership as between the partners. When one partner undertakes to perform a contract entered into by his partnership and later quits and turns the performance of the contract over to his copartner, the performance by the latter is on behalf of
The result is that the amount paid E. T. Clark & Co. by the levee board above the contract price was simply an overpayment. The rule is that sureties on bonds for the performance of contracts are not liable for moneys improperly paid. Edwards County v. Jennings (Tex. Civ. App.), 33 S. W. 585; Gage & Spencer v. Road Improvements Dist., 159 Ark. 642, 252 S. W. 922; McGregor & Hengerr. Escajeda (Tex. Civ. App.), 216 S. W. 398.
E. T. Clark & Co. contend that the participation of the United States in the World War rendered the performance of the contract on their part legally impossible.; that the exercise by the Federal government of its war powers .under, the Constitution made the contract impossible to perform, because of the drafting’ of their labor and the enormous increase in the costs of labor and materials necessary to carry on the levee work, and, therefore, the increase in price was justified and legal. The principle upon which this contention is based is that the war powers of the Federal government under the Constitution are paramount to all state authority, including the Constitution of the state. The contract in question was entered into November 1, 1916; the World War began August, 1914. For two years thereafter there were many aggressions by Germany against the sovereignty of the United States which indicated that the United 'States would become involved in the struggle. Among such indications was the enactment by Congress, on.June 3, 1916', at the suggestion and with the approval of the President, of the National Defense Act. In August, 1916, the Council of National Defense and the War Industries Board were created, and many executive orders were promulgated by the President preparatory to war. There
Under section 96 of the Constitution, E. T. Clark & Co. are liable to the levee board for the excess paid them above the contract price. Clark v. Miller, 142 Miss. 123, 105 So. 502. And this is true regardless of whether or not E. T. Clark & Co. had breached the contract. The levee board was -without authority either to increase the contract price or to relet the contract to E. T. Clark & Co. at a price above the contract price.
Reversed in part, and affirmed in part.
Reference
- Full Case Name
- R. T. Clark & Co. v. Miller, State Revenue Agent
- Cited By
- 1 case
- Status
- Published